Report Run Date: 04/29/2025        Last Data Refresh: 04/28/2025        Report Generated from DOPPLER
 
District Southwest   Type    Retail Station
 
County Citrus   Status    CLOSED
 
ID 8503062   Latitude    28° 50' 3.733
 
Name BAXLEY OIL CO
110 S US HWY 41
Longitude    82° 19' 45.521
  INVERNESS, FL 32650-4849 LL Method    DGPS
 
Contact MICHAEL BUDZINSKI   LL Status    REVIEWED
 
Phone (352) 622-3614   Status Date    06/04/2003
 
Account Owner Information
 
Name K W BAXLEY INC DBA BAXLEY OIL CO
PO BOX 1179
OCALA, FL 34478-1179
Effective Date    09/27/1995
 
Contact MIKE BUDZINSKI
 
Phone (352) 622-3614
 
Email
  Placard # / Date    278501 - 06/06/2007
No Property Owner Information Found
 
 
Tank Tank Size Content Installed Placement Status
4 2000 Vehicular Diesel (D) 06/01/1983 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (Y) Unknown
 
 
Tank Tank Size Content Installed Placement Status
5 6000 Unleaded Gas (B) 06/01/1991 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(A) Ball check valve
(B) Internal lining
(C) Steel
(M) Spill containment bucket
(O) Tight fill
  (C) Fiberglass
(J) Pressurized piping system
(K) Dispenser liners
(M) Double wall - pipe jacket
(N) Approved synthetic material
(2) Visual inspect pipe sumps
(4) Visual inspect dispenser liners
(H) Mechanical line leak detector
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
6 10000 Vehicular Diesel (D) 06/01/1991 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(A) Ball check valve
(B) Internal lining
(C) Steel
(M) Spill containment bucket
(O) Tight fill
  (B) Steel/galvanized metal
(C) Fiberglass
(J) Pressurized piping system
(K) Dispenser liners
(M) Double wall - pipe jacket
(2) Visual inspect pipe sumps
(4) Visual inspect dispenser liners
(H) Mechanical line leak detector
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
7 10000 Unleaded Gas (B) 06/01/1991 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(A) Ball check valve
(B) Internal lining
(C) Steel
(M) Spill containment bucket
(O) Tight fill
  (C) Fiberglass
(J) Pressurized piping system
(K) Dispenser liners
(M) Double wall - pipe jacket
(N) Approved synthetic material
(2) Visual inspect pipe sumps
(4) Visual inspect dispenser liners
(H) Mechanical line leak detector
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
8 12000 Unleaded Gas (B) 06/01/2001 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(L) Compartmented
(M) Spill containment bucket
(N) Flow shut-Off
(O) Tight fill
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(J) Pressurized piping system
(L) Bulk product system
(1) Continuous electronic sensing
(F) Monitor dbl wall tank space
(H) Mechanical line leak detector
(L) Automatic tank gauging - USTs
(Q) Visual inspection of ASTs
(U) Annual piping pressure test
 
 
Tank Tank Size Content Installed Placement Status
1 5000 Unleaded Gas (B) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (Y) Unknown
 
 
Tank Tank Size Content Installed Placement Status
2 3000 Unleaded Gas (B) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (Y) Unknown
 
 
Tank Tank Size Content Installed Placement Status
3 3000 Leaded Gas (A) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (Y) Unknown
 
 
Insurance Documents
 
FR Type   Effective Date Expiration Date Company Name
INSURANCE   08/31/1993 04/15/2006 ZURICH-AMERICAN
 
 
Legacy Compliance Activity Information
 
Activity
Code
Date
Initiated
Date
Completed
Results Inspector AST/UST
Count
Description
NCLI 04/20/2006 04/20/2006 HARMAN_GR 0/0 COMPLIANCE ASSURANCE
 
TCI 04/03/2006 04/20/2006 SIGNIFICANT OUT-OF-COMPLIANCE HARMAN_GR 1/3 COMPLIANCE ASSURANCE
 
NCLI 05/25/2005 05/31/2005 MOLLI_SA 0/0 COMPLIANCE ASSURANCE
 
TCI 05/20/2005 05/31/2005 MINOR OUT-OF-COMPLIANCE MOLLI_SA 0/3 COMPLIANCE ASSURANCE
 
RRBD 06/09/2004 06/10/2004 IN-COMPLIANCE MOLLI_SA 0/0 COMPLIANCE ASSURANCE
 
CWOE 06/09/2004 06/10/2004 MOLLI_SA 0/0 COMPLIANCE ASSURANCE
 
RRBD 06/02/2004 06/04/2004 MOLLI_SA 0/0 COMPLIANCE ASSURANCE
 
NCLI 05/12/2004 05/12/2004 MOLLI_SA 1/3 COMPLIANCE ASSURANCE
 
TCI 04/29/2004 05/12/2004 MINOR OUT-OF-COMPLIANCE MOLLI_SA 1/3 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING FOR THE AST IS ABOVE GROUND STEEL. PIPING FOR THE 3 UST'S IS DOUBLE WALLED SYNTHETIC MATERIAL.
 
NCLI 01/27/2003 01/27/2003 SUMNER_C 0/0 COMPLIANCE ASSURANCE
 
TCI 01/24/2003 01/27/2003 MINOR OUT-OF-COMPLIANCE SUMNER_C 1/3 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING IS ABOVE GROUND STEEL FOR THE AST AND DIESEL UST. THE RUL UST'S PIPING IS AMERON FIBERGLASS PRIMARY IN A GRAY CORRUGATED SECONDARY AT THE STP BUT AT THE DISPENSER IT IS OPW PISCES BLACK FLEX IN A BLUE CORRUGATED SECONDARY. SUL IS OPW FLEX IN BLUE.
 
TCI 02/14/2002 02/14/2002 IN-COMPLIANCE SUMNER_C 1/3 COMPLIANCE ASSURANCE
 
CWOE 07/12/2001 07/16/2001 SUMNER_C 0/0 COMPLIANCE ASSURANCE
 
TIN 07/12/2001 07/16/2001 IN-COMPLIANCE SUMNER_C 1/3 COMPLIANCE ASSURANCE
 
TCI 02/15/2001 02/15/2001 SIGNIFICANT OUT-OF-COMPLIANCE SUMNER_C 0/3 COMPLIANCE ASSURANCE
 
NCLI 02/15/2001 02/15/2001 SUMNER_C 0/0 COMPLIANCE ASSURANCE
 
NCLI 04/15/2000 05/04/2000 SUMNER_C 0/0 COMPLIANCE ASSURANCE
 
TCI 04/05/2000 05/04/2000 MINOR OUT-OF-COMPLIANCE SUMNER_C 0/3 COMPLIANCE ASSURANCE
 
 
 
Compliance Activity Information
 
Activity
Code
Date
Completed
Results Inspector AST/UST
Count
Description
Enforcement Tracking 12/08/2022 Closed Without Enforcement BARRETT_Z Enforcement
 
Issue Document 07/18/2012 Satisfied PEDIGO_L Enforcement
 
Issue Document 01/27/2012 Satisfied PEDIGO_L Enforcement
 
TCAR 08/17/2010 Incomplete OSTENSEN_SA_1 Closure
 
Enforcement Referral 12/22/2008 Accepted PEDIGO_L Enforcement
 
Phone Conversation 02/14/2008 Satisfied OSTENSEN_SA_1 Non-Compliance
 
Letter 02/14/2008 Satisfied OSTENSEN_SA_1 Non-Compliance
 
Letter 04/24/2007 Satisfied HARMAN_GR Non-Compliance
 
Site Inspection 04/18/2007 Major Out of Compliance HARMAN_GR 1/7 Closure
 
Letter 04/18/2007 Satisfied HARMAN_GR Non-Compliance
 
Emergency Preparedness Information 02/12/2007 Satisfied HARMAN_GR Routine Compliance
 
Emergency Preparedness Information 09/25/2006 Satisfied BAUER_DR_1 Routine Compliance
 
Record Document 06/16/2006 Satisfied HARMAN_GR Non-Compliance
 
Record Document 06/05/2006 Satisfied HARMAN_GR Non-Compliance
 
 
 
No Open AOCs Found
 
 
No Open Violations Found
 
 
No Discharges Found