District | Southwest | Type | Retail Station | ||||
County | Citrus | Status | CLOSED | ||||
ID | 8503062 | Latitude | 28° 50' 3.733 | ||||
Name |
BAXLEY OIL CO 110 S US HWY 41 |
Longitude | 82° 19' 45.521 | ||||
INVERNESS, FL 32650-4849 | LL Method | DGPS | |||||
Contact | MICHAEL BUDZINSKI | LL Status | REVIEWED | ||||
Phone | (352) 622-3614 | Status Date | 06/04/2003 | ||||
Account Owner Information | |||||||
Name | K W BAXLEY INC DBA BAXLEY OIL CO PO BOX 1179 OCALA, FL 34478-1179 |
Effective Date | 09/27/1995 | ||||
Contact | MIKE BUDZINSKI | ||||||
Phone | (352) 622-3614 | ||||||
Placard # / Date | 278501 - 06/06/2007 | ||||||
No Property Owner Information Found | |||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
4 | 2000 | Vehicular Diesel (D) | 06/01/1983 | UNDERGROUND | Removed from Site (B) | ||
Constructions | Pipings | Monitorings | |||||
(C) Steel | (C) Fiberglass | (Y) Unknown | |||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
5 | 6000 | Unleaded Gas (B) | 06/01/1991 | UNDERGROUND | Removed from Site (B) | ||
Constructions | Pipings | Monitorings | |||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs |
|||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
6 | 10000 | Vehicular Diesel (D) | 06/01/1991 | UNDERGROUND | Removed from Site (B) | ||
Constructions | Pipings | Monitorings | |||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(B) Steel/galvanized metal (C) Fiberglass (J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs |
|||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
7 | 10000 | Unleaded Gas (B) | 06/01/1991 | UNDERGROUND | Removed from Site (B) | ||
Constructions | Pipings | Monitorings | |||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs |
|||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
8 | 12000 | Unleaded Gas (B) | 06/01/2001 | ABOVEGROUND | Removed from Site (B) | ||
Constructions | Pipings | Monitorings | |||||
(C) Steel (I) Double wall (K) AST containment (L) Compartmented (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (J) Pressurized piping system (L) Bulk product system |
(1) Continuous electronic sensing (F) Monitor dbl wall tank space (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (Q) Visual inspection of ASTs (U) Annual piping pressure test |
|||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
1 | 5000 | Unleaded Gas (B) | UNDERGROUND | Removed from Site (B) | |||
Constructions | Pipings | Monitorings | |||||
(C) Steel | (C) Fiberglass | (Y) Unknown | |||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
2 | 3000 | Unleaded Gas (B) | UNDERGROUND | Removed from Site (B) | |||
Constructions | Pipings | Monitorings | |||||
(C) Steel | (C) Fiberglass | (Y) Unknown | |||||
Tank | Tank Size | Content | Installed | Placement | Status | ||
3 | 3000 | Leaded Gas (A) | UNDERGROUND | Removed from Site (B) | |||
Constructions | Pipings | Monitorings | |||||
(C) Steel | (C) Fiberglass | (Y) Unknown | |||||
Insurance Documents | |||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||
INSURANCE | 08/31/1993 | 04/15/2006 | ZURICH-AMERICAN | ||||
Legacy Compliance Activity Information | |||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |
NCLI | 04/20/2006 | 04/20/2006 | HARMAN_GR | 0/0 | COMPLIANCE ASSURANCE | ||
TCI | 04/03/2006 | 04/20/2006 | SIGNIFICANT OUT-OF-COMPLIANCE | HARMAN_GR | 1/3 | COMPLIANCE ASSURANCE | |
NCLI | 05/25/2005 | 05/31/2005 | MOLLI_SA | 0/0 | COMPLIANCE ASSURANCE | ||
TCI | 05/20/2005 | 05/31/2005 | MINOR OUT-OF-COMPLIANCE | MOLLI_SA | 0/3 | COMPLIANCE ASSURANCE | |
RRBD | 06/09/2004 | 06/10/2004 | IN-COMPLIANCE | MOLLI_SA | 0/0 | COMPLIANCE ASSURANCE | |
CWOE | 06/09/2004 | 06/10/2004 | MOLLI_SA | 0/0 | COMPLIANCE ASSURANCE | ||
RRBD | 06/02/2004 | 06/04/2004 | MOLLI_SA | 0/0 | COMPLIANCE ASSURANCE | ||
NCLI | 05/12/2004 | 05/12/2004 | MOLLI_SA | 1/3 | COMPLIANCE ASSURANCE | ||
TCI | 04/29/2004 | 05/12/2004 | MINOR OUT-OF-COMPLIANCE | MOLLI_SA | 1/3 | COMPLIANCE ASSURANCE | |
Completion Notes PIPING FOR THE AST IS ABOVE GROUND STEEL. PIPING FOR THE 3 UST'S IS DOUBLE WALLED SYNTHETIC MATERIAL. | |||||||
NCLI | 01/27/2003 | 01/27/2003 | SUMNER_C | 0/0 | COMPLIANCE ASSURANCE | ||
TCI | 01/24/2003 | 01/27/2003 | MINOR OUT-OF-COMPLIANCE | SUMNER_C | 1/3 | COMPLIANCE ASSURANCE | |
Completion Notes PIPING IS ABOVE GROUND STEEL FOR THE AST AND DIESEL UST. THE RUL UST'S PIPING IS AMERON FIBERGLASS PRIMARY IN A GRAY CORRUGATED SECONDARY AT THE STP BUT AT THE DISPENSER IT IS OPW PISCES BLACK FLEX IN A BLUE CORRUGATED SECONDARY. SUL IS OPW FLEX IN BLUE. | |||||||
TCI | 02/14/2002 | 02/14/2002 | IN-COMPLIANCE | SUMNER_C | 1/3 | COMPLIANCE ASSURANCE | |
CWOE | 07/12/2001 | 07/16/2001 | SUMNER_C | 0/0 | COMPLIANCE ASSURANCE | ||
TIN | 07/12/2001 | 07/16/2001 | IN-COMPLIANCE | SUMNER_C | 1/3 | COMPLIANCE ASSURANCE | |
TCI | 02/15/2001 | 02/15/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | SUMNER_C | 0/3 | COMPLIANCE ASSURANCE | |
NCLI | 02/15/2001 | 02/15/2001 | SUMNER_C | 0/0 | COMPLIANCE ASSURANCE | ||
NCLI | 04/15/2000 | 05/04/2000 | SUMNER_C | 0/0 | COMPLIANCE ASSURANCE | ||
TCI | 04/05/2000 | 05/04/2000 | MINOR OUT-OF-COMPLIANCE | SUMNER_C | 0/3 | COMPLIANCE ASSURANCE | |
Compliance Activity Information | |||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||
Enforcement Tracking | 12/08/2022 | Closed Without Enforcement | BARRETT_Z | Enforcement | |||
Issue Document | 07/18/2012 | Satisfied | PEDIGO_L | Enforcement | |||
Issue Document | 01/27/2012 | Satisfied | PEDIGO_L | Enforcement | |||
TCAR | 08/17/2010 | Incomplete | OSTENSEN_SA_1 | Closure | |||
Enforcement Referral | 12/22/2008 | Accepted | PEDIGO_L | Enforcement | |||
Phone Conversation | 02/14/2008 | Satisfied | OSTENSEN_SA_1 | Non-Compliance | |||
Letter | 02/14/2008 | Satisfied | OSTENSEN_SA_1 | Non-Compliance | |||
Letter | 04/24/2007 | Satisfied | HARMAN_GR | Non-Compliance | |||
Site Inspection | 04/18/2007 | Major Out of Compliance | HARMAN_GR | 1/7 | Closure | ||
Letter | 04/18/2007 | Satisfied | HARMAN_GR | Non-Compliance | |||
Emergency Preparedness Information | 02/12/2007 | Satisfied | HARMAN_GR | Routine Compliance | |||
Emergency Preparedness Information | 09/25/2006 | Satisfied | BAUER_DR_1 | Routine Compliance | |||
Record Document | 06/16/2006 | Satisfied | HARMAN_GR | Non-Compliance | |||
Record Document | 06/05/2006 | Satisfied | HARMAN_GR | Non-Compliance | |||
No Open AOCs Found | |||||||
No Open Violations Found | |||||||
No Discharges Found |