District | Central | Type | Retail Station | ||||||||
County | Lake | Status | OPEN | ||||||||
ID | 8510141 | Latitude | 28° 48' 41.2857 | ||||||||
Name |
SQRL SERVICE STATION 336 1200 W MAIN ST |
Longitude | 81° 53' 1.89 | ||||||||
LEESBURG, FL 34748-4935 | LL Method | DPHO | |||||||||
Contact | MATT BONAMINIO | LL Status | REVIEWED | ||||||||
Phone | (501) 319-5315 | Status Date | 10/01/2003 | ||||||||
Account Owner Information | |||||||||||
Name | SQRL SERVICE STATIONS LLC 27 RAHLING CIRCLE STE C LITTLE ROCK, AR 72223 |
Effective Date | 03/15/2023 | ||||||||
Contact | JAMAL HIZAM | ||||||||||
Phone | (504) 595-7385 | ||||||||||
JAMAL@SQRLHOLDINGS.COM | |||||||||||
Placard # / Date | 661499 - 06/20/2023 | ||||||||||
Property Owner Information | |||||||||||
Name | RCP LEESBURG LLC 411 THEODORE FREMD AVENUE SUITE 206 S RYE, NY 10580 |
Effective Date | 03/15/2023 | ||||||||
Contact | ANDREW FEIN/DAVID SHENFELD (201) 575-0643 | ||||||||||
Phone | (914) 921-8269 | ||||||||||
ANDREW@RHINOCP.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 20000 | Unleaded Gas (B) | 11/01/2004 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (L) Compartmented (M) Spill containment bucket (N) Flow shut-Off (R) Double wall - tank jacket |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 4000 | Unleaded Gas (B) | 07/01/1974 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 4000 | Unleaded Gas (B) | 07/01/1974 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 4000 | Unleaded Gas (B) | 07/01/1974 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 4000 | Unleaded Gas (B) | 07/01/1974 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 4000 | Unleaded Gas (B) | 07/01/1965 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 4000 | Vehicular Diesel (D) | 07/01/1965 | UNDERGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (B) Internal lining (C) Steel (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(G) Electronic line leak detector (I) Not required (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile (U) Annual piping pressure test |
|||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 07/14/2023 | 07/14/2024 | LIBERTY SURPLUS INSURANCE CORPORATION | ||||||||
INSURANCE | 10/01/2021 | 10/01/2022 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 10/01/2020 | 10/01/2021 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 10/01/2019 | 10/01/2020 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 10/01/2018 | 10/01/2019 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 10/01/2017 | 10/01/2018 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 10/01/2015 | 10/01/2016 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 10/01/2013 | 10/01/2014 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 10/01/2011 | 10/01/2012 | ZURICH-AMERICAN | ||||||||
INSURANCE | 10/01/2010 | 10/01/2011 | ZURICH-AMERICAN | ||||||||
INSURANCE | 10/01/2009 | 10/01/2010 | ZURICH-AMERICAN | ||||||||
INSURANCE | 03/14/2008 | 03/14/2009 | AIG | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCR | 04/04/2006 | 04/18/2006 | MINOR OUT-OF-COMPLIANCE | COX | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes MLLDS TESTED 3/22/06(REG AND PREM) 3/29/06 (DIESEL). SENSOR OP. DONE 3/29/06. PREM. AND DIESEL SPILL BUCKETS HAVE CRACKED RINGS, TEST AND REPAIR. REG. AND PREM. STP SUMP LIDS DON'T FIT. PAINT VAPOR RECOVERY LIDS ORANGE. | |||||||||||
TCR | 03/16/2006 | 03/17/2006 | SIGNIFICANT OUT-OF-COMPLIANCE | COX/BOWERS | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes NO VIOLATIONS HAVE BEEN ADDRESSED. R/UL STP SUMP LIFTED AND LID DOES NOT FIT. | |||||||||||
TCI | 02/15/2006 | 02/16/2006 | MINOR OUT-OF-COMPLIANCE | BOWERS/COX | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes MISSING MARCH 05 THROUGH PRESENT LIQUID STATUS PRINT OUTS. MISSING CURRENT MLLD AND VR/SENSOR CERT. RD IS VISUALS AND "LIQUID STATUS". | |||||||||||
LTR | 03/11/2005 | 03/14/2005 | COX | 0/1 | COMPLIANCE ASSURANCE | ||||||
Completion Notes DIESEL MLLD TEST RECEIVED. | |||||||||||
TXP | 03/01/2005 | 03/01/2005 | COX | 0/6 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CONTAMINATION EVALUATION WELLS DRILLED, ATC ON SITE SAMPLING 2/15/05. | |||||||||||
TIN | 02/22/2005 | 03/01/2005 | IN-COMPLIANCE | COX | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes PLACARD ON SITE, ALL SHEAR VALVES ANCHORED, TLS 350 WORKING OK, STILL NEED PROOF OF DIESEL MLLD TEST. | |||||||||||
TIN | 02/15/2005 | 03/01/2005 | MINOR OUT-OF-COMPLIANCE | COX | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes INSTALLATION OF ONE 20,000 GAL. UST. AMERON DUOLOY PIPING, DIESEL HAS FLAPPER VALVE, R/UL AND PREMIUM FILLS HAVE BALLCHECK VALVES. NEED PROOF OF MLLD TESTS, TIGHTEN SHEAR VALVE ANCHORS, NO PLACARD ON SITE. | |||||||||||
TXI | 11/19/2004 | 12/02/2004 | IN-COMPLIANCE | BOWERS | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes REMOVAL OF 6 USTS BY PETRO PLUS, INC. (PCC#1256780). FACILITY HAS SITE ASSESSMENT IN PROGRESS, REQUIRING FULL CLOSURE OR COPY OF COMPLETED SITE ASSESSMENT WITHIN 60 DAYS. | |||||||||||
LTR | 11/01/2004 | 11/02/2004 | BOWERS | 0/6 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RECEIVED RESULTS OF TANK LINING TEST. ALL TANKS INSPECTED ON 9/9/04 - PASSED. 10 YEAR TEST WAS DONE 9/01. | |||||||||||
TCR | 08/25/2004 | 08/30/2004 | IN-COMPLIANCE | BOWERS | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes TANKNOLOGY ON SITE TO PERFORM TTT, MLLD & SPILL BUCKET TESTS. VERBLE PASSING, AWAITING TEST RESULTS. SPILL BUCKETS OK. | |||||||||||
TCR | 04/14/2004 | 04/21/2004 | IN-COMPLIANCE | COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes RECEIVED ALL REQUIRED RECORDS. LIQUID REMOVED FROM STPS AND SUMPS. | |||||||||||
TCI | 02/24/2004 | 02/26/2004 | MINOR OUT-OF-COMPLIANCE | COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes PLLD & 3YRTTTW/SIRS TESTED 4/25/03 AND 8/24/04. MISSING SIRS AND VISUALS, WATER IN DISP. AND R/UL STP. | |||||||||||
DCCR | 04/11/2003 | 05/05/2003 | BOWERS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes DRF SUBMITTED BY S&ME AS PART OF A PRE-BUY AUDIT BY SUN OIL CO. | |||||||||||
TCR | 03/11/2003 | 03/14/2003 | IN-COMPLIANCE | BOWERS | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes LIQUID REMOVED FROM DISP. 1/2 AND R/UL STP SUMP | |||||||||||
TCI | 02/20/2003 | 02/21/2003 | MINOR OUT-OF-COMPLIANCE | BOWERS/COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes SENSOR CERT. 5/02. AMARON, DW, RIDGED, FIB. PIPING. | |||||||||||
TCI | 02/21/2002 | 02/27/2002 | IN-COMPLIANCE | BOWERS/COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes ANNUAL COMPLIANCE-PLLD DONE 3/26/01, 3YRTTT W/SIR 12/3/01 | |||||||||||
TCI | 02/26/2001 | 03/02/2001 | MINOR OUT-OF-COMPLIANCE | BOWERS/COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes ANNUAL COMPLIANCE | |||||||||||
TCI | 03/27/2000 | 03/30/2000 | MINOR OUT-OF-COMPLIANCE | BOWERS/COX | 0/6 | COMPLIANCE ASSURANCE | |||||
Completion Notes ANNUAL COMPLIANCE | |||||||||||
TCI | 02/12/1999 | 03/16/1999 | SIGNIFICANT OUT-OF-COMPLIANCE | KRUSE | 0/6 | COMPLIANCE ASSURANCE | |||||
UTCI | 02/12/1998 | 02/24/1998 | SIGNIFICANT OUT-OF-COMPLIANCE | COMPLIANCE ASSURANCE | |||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Enforcement Referral | 09/09/2024 | Accepted | RIVERA_JX_2 | Enforcement | |||||||
Electronic Communication | 08/14/2024 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Site Inspection | 02/08/2024 | Major Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Letter | 02/08/2024 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/24/2024 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Electronic Communication | 04/03/2023 | Satisfied | COX_CD_1 | Incident | |||||||
Electronic Communication | 04/03/2023 | Satisfied | COX_CD_1 | Incident | |||||||
Electronic Communication | 02/15/2023 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Document Management | 02/15/2023 | Satisfied | COX_CD_1 | Incident | |||||||
Electronic Communication | 02/15/2023 | Satisfied | COX_CD_1 | Incident | |||||||
Electronic Communication | 02/15/2023 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Letter | 04/25/2022 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 04/25/2022 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 04/25/2022 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Letter | 01/13/2022 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Site Inspection | 01/13/2022 | Minor Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Phone Conversation | 01/03/2022 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 12/30/2021 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 12/30/2021 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Electronic Communication | 09/03/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Letter | 09/03/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 09/01/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 08/18/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 08/17/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 06/02/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 06/02/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Document Management | 06/02/2020 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Electronic Communication | 01/09/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/09/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/03/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/03/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/02/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Electronic Communication | 01/02/2020 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Site Inspection | 12/16/2019 | Major Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Electronic Communication | 12/16/2019 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Letter | 12/16/2019 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Phone Conversation | 11/07/2019 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 11/07/2019 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 11/04/2019 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 11/04/2019 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Electronic Communication | 02/28/2018 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Letter | 02/28/2018 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Letter | 02/15/2018 | Satisfied | RAUENZAHN_RA_1 | Compliance Assistance | |||||||
Phone Conversation | 02/15/2018 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Site Inspection | 11/28/2017 | Major Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Letter | 11/28/2017 | Satisfied | COX_CD_1 | Compliance Assistance | |||||||
Phone Conversation | 11/07/2017 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 11/07/2017 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 10/27/2017 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 10/27/2017 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Site Inspection | 12/04/2015 | In Compliance | COX_CD_1 | 0/1 | Non-Compliance | ||||||
Letter | 11/05/2015 | Satisfied | COX_CD_1 | Non-Compliance | |||||||
Site Inspection | 10/28/2015 | Minor Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Document Management | 09/29/2015 | Complete | COX_CD_1 | Routine Compliance | |||||||
Phone Conversation | 09/22/2015 | Satisfied | COX_CD_1 | Routine Compliance | |||||||
Letter | 01/28/2014 | Satisfied | COX_CD_1 | Non-Compliance | |||||||
Site Inspection | 01/27/2014 | Minor Out of Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Site Inspection | 02/14/2012 | In Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Site Inspection | 04/06/2011 | In Compliance | ZIMMERMAN_RA_1 | 0/1 | Non-Compliance | ||||||
Letter | 02/16/2011 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Site Inspection | 02/16/2011 | Minor Out of Compliance | ZIMMERMAN_RA_1 | 0/1 | Routine Compliance | ||||||
Site Inspection | 03/12/2010 | In Compliance | ZIMMERMAN_RA_1 | 0/1 | Non-Compliance | ||||||
Letter | 02/16/2010 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Site Inspection | 02/16/2010 | Minor Out of Compliance | ZIMMERMAN_RA_1 | 0/1 | Routine Compliance | ||||||
Site Inspection | 02/11/2009 | In Compliance | COX_CD_1 | 0/1 | Routine Compliance | ||||||
Record Document | 09/11/2008 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Record Document | 04/14/2008 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Site Inspection | 02/12/2008 | Minor Out of Compliance | ZIMMERMAN_RA_1 | 0/7 | Routine Compliance | ||||||
Letter | 02/12/2008 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Site Inspection | 03/30/2007 | In Compliance | ZIMMERMAN_RA_1 | 0/7 | Non-Compliance | ||||||
Letter | 02/27/2007 | Satisfied | ZIMMERMAN_RA_1 | Non-Compliance | |||||||
Site Inspection | 02/27/2007 | Minor Out of Compliance | ZIMMERMAN_RA_1 | 0/7 | Routine Compliance | ||||||
Emergency Preparedness Information | 02/08/2007 | Satisfied | ZIMMERMAN_RA_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 09/26/2006 | Satisfied | ZIMMERMAN_RA_1 | Routine Compliance | |||||||
Site Inspection | 05/03/2006 | Major Out of Compliance | COX_CD_1 | 0/7 | Non-Compliance | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
02/08/2024 | 6063 | SNC-B | 4.1 Not repaired or isolated component or piping which has not caused a discharge or release. | Submit proof of the repair of the premium spill bucket and a closure assessment of the bucket. | |||||||
02/02/2024 | 6066 | Minor | 4.4 Not repaired per applicable standards. | Clean and re-coat the components of the regular and premium STP sumps. Loosen the test boots in the dispensers and the STP sumps. | |||||||
02/02/2024 | 6073 | Minor | 4.9 Spill containment, dispenser liners, and piping sumps not accessible. Water or regulated substances not removed. | Remove the water from the premium and regular STP sumps. | |||||||