Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | Northwest | Type | Retail Station | ||||||||
County | Leon | Status | OPEN | ||||||||
ID | 8510230 | Latitude | 30° 30' 15.54 | ||||||||
Name |
Circle K #2705990 3424 THOMASVILLE RD |
Longitude | 84° 15' 7.36 | ||||||||
TALLAHASSEE, FL 32308-3404 | LL Method | WGPS | |||||||||
Contact | Ira Lewis | LL Status | REVIEWED | ||||||||
Phone | (984) 389-1300 | Status Date | 09/23/2003 | ||||||||
Account Owner Information | |||||||||||
Name | CIRCLE K STORES INC 1100 Situs Ct Raleigh, NC 27606-5446 |
Effective Date | 04/17/2006 | ||||||||
Contact | IRA LEWIS | ||||||||||
Phone | (423) 400-2480 | ||||||||||
ILEWIS@CIRCLEK.COM | |||||||||||
Placard # / Date | 697493 - 06/28/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | CIRCLE K STORES INC 1100 Situs Ct Raleigh, NC 27606-5446 |
Effective Date | 07/07/2015 | ||||||||
Contact | IRA LEWIS | ||||||||||
Phone | (423) 400-2480 | ||||||||||
ILEWIS@CIRCLEK.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
10 | 10000 | Vehicular Diesel (D) | 09/01/1991 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (S) DEP approved containment |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 10000 | Vehicular Diesel (D) | 09/01/1991 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (S) DEP approved containment |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
8 | 10000 | Unleaded Gas (B) | 09/01/1991 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (S) DEP approved containment |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
9 | 10000 | Unleaded Gas (B) | 09/01/1991 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (S) DEP approved containment |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 8000 | Leaded Gas (A) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 8000 | Unleaded Gas (B) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 8000 | Unleaded Gas (B) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 8000 | Vehicular Diesel (D) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 8000 | Vehicular Diesel (D) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 8000 | Vehicular Diesel (D) | 07/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel |
(B) Steel/galvanized metal (D) External protective coating |
(8) Manually sampled wells | |||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
SELF-INSURANCE - LETTER FROM CHIEF FINANCIAL OFFICER | 04/28/2024 | 08/26/2025 | |||||||||
SELF-INSURANCE - LETTER FROM CHIEF FINANCIAL OFFICER | 04/30/2023 | 08/28/2024 | |||||||||
FULLY FUNDED TRUST | 04/24/2022 | 08/21/2023 | |||||||||
INSURANCE | 12/01/2019 | 12/01/2020 | NAVIGATORS SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 08/27/2018 | 08/27/2018 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2015 | 12/01/2016 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2014 | 12/01/2015 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2013 | 12/01/2014 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2011 | 12/01/2013 | CHUBB | ||||||||
INSURANCE | 12/01/2011 | 12/01/2012 | CHUBB | ||||||||
INSURANCE | 12/17/2010 | 12/17/2011 | CHUBB | ||||||||
INSURANCE | 12/18/2009 | 12/17/2010 | CHUBB | ||||||||
INSURANCE | 12/17/2008 | 12/17/2009 | AMERICAN INTERNATIONAL SPECIALTY LINES | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCR | 01/16/2006 | 03/03/2006 | IN-COMPLIANCE | FRENCH | 0/4 | COMPLIANCE ASSURANCE | |||||
CWOE | 01/16/2006 | 03/03/2006 | FRENCH | 0/4 | COMPLIANCE ASSURANCE | ||||||
RRBD | 01/13/2006 | 01/18/2006 | FRENCH | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes AREAS OF CONCERN WILL BE ADDRESSED | |||||||||||
TCR | 01/10/2006 | 01/18/2006 | IN-COMPLIANCE | FRENCH | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes REPAIRS WERE PERFORMED IN THE PREMIUM SUMP BUT NOT IN THE AREA OF CONCERN. LEON COUNTY SHOWED THE TECH THE AREAS OF CONCERN DURING THE REINSPECT. THE ENTRY BOOTS WILL BE ADDRESSED ASAP ACCORDING TO THE TECH. | |||||||||||
WLI | 11/10/2005 | 11/15/2005 | FRENCH | 0/3 | COMPLIANCE ASSURANCE | ||||||
CALL | 10/20/2005 | 11/15/2005 | FRENCH | 0/3 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CALLLED JACKIE BURNS WITH STOP-N-SAVE TO GET STATUS OF REPAIRS. MS. BURNS STATED SHE HAD NOT RECEIVED NCLI. LEON CO. FAXED COPY OF LETTER. | |||||||||||
NCLI | 10/07/2005 | 10/07/2005 | FRENCH | 0/4 | COMPLIANCE ASSURANCE | ||||||
TCI | 09/28/2005 | 10/07/2005 | MINOR OUT-OF-COMPLIANCE | FRENCH | 0/4 | COMPLIANCE ASSURANCE | |||||
TCI | 11/12/2004 | 12/01/2004 | IN-COMPLIANCE | HATCHER | 0/4 | COMPLIANCE ASSURANCE | |||||
TCI | 09/24/2003 | 09/25/2003 | IN-COMPLIANCE | HATCHER | 0/4 | COMPLIANCE ASSURANCE | |||||
TCI | 10/02/2002 | 10/15/2002 | IN-COMPLIANCE | HATCHER | 0/4 | COMPLIANCE ASSURANCE | |||||
CRDE | 05/11/2002 | 05/11/2002 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CASE REFERED TO NWD FOR TRACKING, NO SIGNED DRF SUBMITTED AND INCOMPLETE SAMPLING DONE AT CLOSURE. | |||||||||||
DCCR | 05/11/2002 | 05/11/2002 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
DDCR | 05/11/2002 | 05/11/2002 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes SCTL'S FOR BENZENE IN THE LEACHABILITY CATEGORY EXCEEDED. | |||||||||||
CNLI | 05/11/2002 | 05/11/2002 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
TIN | 05/06/2002 | 05/11/2002 | IN-COMPLIANCE | ROSS | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes INSTALLATION OF DW OPW PICES COAXIAL PIPING, NEW DISPENSING SYSTEM AND BALL CHECK VAVLE. | |||||||||||
IRFR | 02/26/2002 | 03/01/2002 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes ELEVATED OVA'S DURING PIPING CLOSURE | |||||||||||
TXI | 02/22/2002 | 03/01/2002 | IN-COMPLIANCE | ROSS | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes PIPING CLOSURE | |||||||||||
CWOE | 02/22/2002 | 03/01/2002 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes PIPING CLOSURE FOR DISPENSING SYSTEM AND PENDING INSTALL/UPGRADE ADDRESSES NON COMPLIANCE ITEMS. | |||||||||||
RRBD | 01/14/2002 | 01/15/2002 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes T-TEST RESULTS PROVIDED FOR DIESEL TANK. TANK TESTED12/19/01 | |||||||||||
NCLI | 12/12/2001 | 12/12/2001 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCR | 12/05/2001 | 12/12/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | ROSS | 0/4 | COMPLIANCE ASSURANCE | |||||
RRBD | 11/19/2001 | 12/12/2001 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes REPAIR RECORDS AND NOTIFICATION THAT SITE IS READY FOR TCR. | |||||||||||
DSNR | 10/24/2001 | 12/12/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes INVESTATION DONE AND TANKS TESTED TIGHT. | |||||||||||
RRBD | 10/24/2001 | 12/12/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes INVESTIGATION RESULTS AND TANK T-TESTS FOR (3) GASOLINE TANKS. | |||||||||||
NCLI | 10/11/2001 | 10/11/2001 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 10/04/2001 | 10/11/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | ROSS | 0/4 | COMPLIANCE ASSURANCE | |||||
IRFR | 08/20/2001 | 12/12/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CONSECUTIVE INC SIR'S FOR (3) GASOLINE TANKS. | |||||||||||
DSNR | 05/29/2001 | 06/13/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CSLD USED AS BACK UP SHOWS PASS FOR REG UL TANK. OK | |||||||||||
RRBD | 05/29/2001 | 06/13/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes INVESTIGATION RESULTS | |||||||||||
IRFR | 05/14/2001 | 06/13/2001 | ROSS | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CONSECUTIVE INCONCLUSIVES REG UL TANK. | |||||||||||
CWOE | 10/19/2000 | 10/25/2000 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes LEAK DETECTORS TESTED, WATER REMOVED FROM SUMPS | |||||||||||
TCR | 10/19/2000 | 10/25/2000 | IN-COMPLIANCE | SHEFFIELD | 0/4 | COMPLIANCE ASSURANCE | |||||
NCLI | 09/25/2000 | 09/25/2000 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 09/19/2000 | 09/22/2000 | MINOR OUT-OF-COMPLIANCE | SHEFFIELD | 0/4 | COMPLIANCE ASSURANCE | |||||
TCR | 01/11/2000 | 01/20/2000 | IN-COMPLIANCE | SHEFFIELD | 0/4 | COMPLIANCE ASSURANCE | |||||
CWOE | 01/11/2000 | 01/20/2000 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes COMPLIANCE WELLS CLOSED. ONE WELL LEFT OPEN TO CHECK FOR GROUND WATER DURING PERIODIC T-TESTING. OTHER ISSUES RESOLVED WITH RRBD'S. | |||||||||||
RRBD | 11/01/1999 | 11/03/1999 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes LD TEST RECORDS, RDRL PREVIOUSLY PROVIDE. | |||||||||||
NCLI | 08/27/1999 | 08/27/1999 | ROSS | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 08/12/1999 | 08/27/1999 | MINOR OUT-OF-COMPLIANCE | SHEFFIELD | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes NO RDRL OR ANNUAL TESTING OF LD DEVICES, OR RECORDS OF SAME. | |||||||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Enforcement Referral | 03/14/2025 | Accepted | FRENCH_EC_1 | Enforcement | |||||||
Letter | 03/11/2025 | Satisfied | FRENCH_EC_1 | Compliance Assistance | |||||||
Site Inspection | 12/27/2024 | Major Out of Compliance | FRENCH_EC_1 | 0/4 | Complaint | ||||||
Phone Conversation | 12/27/2024 | Satisfied | FRENCH_EC_1 | Complaint | |||||||
Letter | 10/16/2024 | Satisfied | FRENCH_EC_1 | Compliance Assistance | |||||||
Site Inspection | 10/16/2024 | Major Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Letter | 10/19/2022 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 10/19/2022 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Enforcement Tracking | 03/25/2022 | Closed With Enforcement | BRISTOL_S | Enforcement | |||||||
Incident | 02/04/2022 | Has not led to Discharge | BRISTOL_S | Incident | |||||||
Incident | 11/16/2021 | Has not led to Discharge | BRISTOL_S | Incident | |||||||
Enforcement Referral | 06/29/2021 | Accepted | FRENCH_EC_1 | Enforcement | |||||||
Letter | 10/30/2020 | Satisfied | HATCHER_JD_1 | Compliance Assistance | |||||||
Site Inspection | 10/30/2020 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Record Document | 10/31/2018 | Satisfied | HATCHER_JD_1 | Compliance Assistance | |||||||
Letter | 08/27/2018 | Satisfied | HATCHER_JD_1 | Compliance Assistance | |||||||
Site Inspection | 08/27/2018 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Site Inspection | 09/29/2016 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Site Inspection | 09/09/2015 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/28/2014 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 08/28/2014 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/20/2014 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 09/30/2013 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 10/01/2012 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 10/01/2012 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Site Inspection | 10/12/2011 | In Compliance | FRENCH_EC_1 | 0/4 | Non-Compliance | ||||||
Emergency Preparedness Information | 08/24/2011 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Letter | 08/18/2011 | Satisfied | HATCHER_JD_1 | Non-Compliance | |||||||
Site Inspection | 08/18/2011 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Site Inspection | 10/07/2010 | In Compliance | HATCHER_JD_1 | 0/4 | Non-Compliance | ||||||
Letter | 08/25/2010 | Satisfied | HATCHER_JD_1 | Non-Compliance | |||||||
Site Inspection | 08/25/2010 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/25/2010 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Document Management | 06/04/2010 | Complete | FRENCH_EC_1 | Incident | |||||||
Document Management | 05/19/2010 | Satisfied | FRENCH_EC_1 | Discharge | |||||||
Site Inspection | 12/22/2009 | In Compliance | HATCHER_JD_1 | 0/4 | Non-Compliance | ||||||
Letter | 08/31/2009 | Satisfied | HATCHER_JD_1 | Non-Compliance | |||||||
Site Inspection | 08/31/2009 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/31/2009 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 09/30/2008 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 09/30/2008 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Site Inspection | 07/21/2008 | In Compliance | HATCHER_JD_1 | 0/4 | Installation | ||||||
Record Document | 03/04/2008 | Satisfied | FRENCH_EC_1 | Non-Compliance | |||||||
Site Inspection | 11/20/2007 | In Compliance | FRENCH_EC_1 | 0/3 | Non-Compliance | ||||||
Letter | 07/31/2007 | Satisfied | HATCHER_JD_1 | Non-Compliance | |||||||
Site Inspection | 07/27/2007 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Site Inspection | 05/23/2007 | In Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 02/07/2007 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 09/28/2006 | Satisfied | HATCHER_JD_1 | Routine Compliance | |||||||
Letter | 04/28/2006 | Satisfied | FRENCH_EC_1 | Discharge | |||||||
Letter | 04/19/2006 | Satisfied | HATCHER_JD_1 | Non-Compliance | |||||||
Site Inspection | 04/19/2006 | Minor Out of Compliance | HATCHER_JD_1 | 0/4 | Routine Compliance | ||||||
TCAR | 04/12/2006 | Satisfied | HATCHER_JD_1 | Closure | |||||||
Site Inspection | 04/12/2006 | In Compliance | HATCHER_JD_1 | 0/4 | Installation | ||||||
Record Document | 04/05/2006 | Satisfied | HATCHER_JD_1 | Installation | |||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
12/27/2024 | 6042 | SNC-B | 4.3 Storage tank system not installed with a spill containment system at each tank fill connection. Does not meet performance requirements. | Replace fill riser cap on tank#2. | |||||||
12/27/2024 | 6073 | Minor | 4.9 Spill containment, dispenser liners, and piping sumps not accessible. Water or regulated substances not removed. | Remove water from the probe riser sump and replace the riser cap (see pic) | |||||||
12/27/2024 | 6063 | SNC-B | 4.1 Not repaired or isolated component or piping which has not caused a discharge or release. | Replace both probe riser caps and secure riser openings. Repair or replace spill bucket fill riser cap. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
10/09/1991 | ACTIVE | 10 | PETROLEUM LIABILITY AND RESTORATION INSURANCE PROGRAM-ELIGIBLE | ||||||||