Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | Northeast | Type | Bulk Storage Facility | ||||||||
County | Levy | Status | OPEN | ||||||||
ID | 8510599 | Latitude | 29° 22' 46.9742 | ||||||||
Name |
TRI-COUNTY OIL DISTRIBUTORS INC 15 SW 7TH AVE |
Longitude | 82° 26' 53.6473 | ||||||||
WILLISTON, FL 32696-2916 | LL Method | DPHO | |||||||||
Contact | MIKE DOERR | LL Status | REVIEWED | ||||||||
Phone | (352) 528-3011 | Status Date | 04/07/2003 | ||||||||
Account Owner Information | |||||||||||
Name | TRI-CNTY OIL DISTRIBUTORS INC PO BOX 759 WILLISTON, FL 32696-759 |
Effective Date | 03/06/1987 | ||||||||
Contact | MIKE DOERR :FAX 352-528-6064 / TODD TUCKER | ||||||||||
Phone | (352) 528-3011 | ||||||||||
TODD@TRICOUNTYOIL.COM | |||||||||||
Placard # / Date | 688465 - 06/18/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | TRI-CNTY OIL DISTRIBUTORS INC PO BOX 759 WILLISTON, FL 32696-759 |
Effective Date | 01/23/2001 | ||||||||
Contact | MIKE DOERR :FAX 352-528-6064 / TODD TUCKER | ||||||||||
Phone | (352) 528-3011 | ||||||||||
TODD@TRICOUNTYOIL.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 15000 | Unleaded Gas (B) | 01/01/2015 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(B) Steel/galvanized metal (G) Pipe trench liner |
(Q) Visual inspection of ASTs | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
101 | 20000 | Ethanol E10 (8) | 01/01/2007 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(B) Steel/galvanized metal (F) Double wall (J) Pressurized piping system (K) Dispenser liners (N) Approved synthetic material |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
102 | 20000 | Unleaded Gas (B) | 01/01/2007 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(B) Steel/galvanized metal (F) Double wall (J) Pressurized piping system (K) Dispenser liners (N) Approved synthetic material |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
103 | 20000 | Vehicular Diesel (D) | 01/01/2007 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(B) Steel/galvanized metal (F) Double wall (J) Pressurized piping system (K) Dispenser liners (N) Approved synthetic material |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 15000 | Vehicular Diesel (D) | 01/01/2007 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (J) Pressurized piping system (K) Dispenser liners |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 15000 | Vehicular Diesel (D) | 01/01/2007 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(B) Internal lining (C) Steel (K) AST containment (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (J) Pressurized piping system (K) Dispenser liners |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 1012 | Leaded Gas (A) | 08/01/1982 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(B) Steel/galvanized metal (F) Double wall (J) Pressurized piping system (K) Dispenser liners (N) Approved synthetic material |
(4) Visual inspect dispenser liners (M) Manual tank gauging - USTs (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 1002 | Unleaded Gas (B) | 08/01/1982 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(B) Steel/galvanized metal (F) Double wall (J) Pressurized piping system (K) Dispenser liners (N) Approved synthetic material |
(4) Visual inspect dispenser liners (M) Manual tank gauging - USTs (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
8 | 1002 | Unleaded Gas (B) | 08/01/1982 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (B) Steel/galvanized metal | (Y) Unknown | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
9 | 2000 | Vehicular Diesel (D) | 08/01/1972 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (B) Steel/galvanized metal | (Y) Unknown | |||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 02/14/2023 | 02/14/2024 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 02/14/2022 | 02/14/2023 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 02/14/2021 | 02/14/2022 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 02/14/2020 | 02/14/2021 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 02/14/2019 | 02/14/2020 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 02/14/2018 | 02/14/2019 | ADMIRAL INSURANCE COMPANY | ||||||||
INSURANCE | 09/12/2015 | 09/12/2018 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 09/12/2014 | 09/12/2015 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 02/14/2011 | 02/14/2014 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
INSURANCE | 02/14/2011 | 02/14/2012 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
INSURANCE | 02/14/2011 | 02/14/2014 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
INSURANCE | 09/12/2009 | 09/12/2010 | ZURICH-AMERICAN | ||||||||
INSURANCE | 09/12/2008 | 09/12/2009 | ZURICH-AMERICAN | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TDI | 06/01/2005 | 06/20/2005 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | DISCHARGE PROJECT | |||||
Completion Notes DISCHARGE OCCURRED DUE TO CUSTOMER AT DISPENSER, NOT THRU EQUIPMENT FAILURE. REPORTED TO DEP EMERGENCY RESPONSE, JAMIE ROARLEO. CLEANUP BEGUN BY CREATIVE SOLUTIONS. | |||||||||||
TCI | 05/17/2005 | 05/24/2005 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
TCI | 06/03/2004 | 06/10/2004 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
TCI | 05/29/2003 | 06/10/2003 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes THE UNDERGROUND PORTION OF THE PIPING IS GREEN ENVIRON D/W FLEX | |||||||||||
TCI | 05/16/2002 | 06/14/2002 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
CFFE | 09/13/2001 | 09/13/2001 | DEFALCO_L | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CASE CLOSED FULL PAYMENT RECEIVED FROM SFCO | |||||||||||
PR | 09/05/2001 | 06/19/2001 | DEFALCO_L | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes FULL PAYMENT RECEIVED $6,200 CASE CLOSED | |||||||||||
TCR | 06/01/2001 | 06/05/2001 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
TCI | 05/10/2001 | 06/05/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
NCLI | 05/02/2001 | 05/02/2001 | DEFALCO_L | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes SEC.CONT NOT COATED, PIPING UPGRADES PERFORMED PEN. ASSESSED | |||||||||||
TIN | 12/22/2000 | 01/19/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
TCI | 05/25/2000 | 06/01/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
PDNE | 04/22/1999 | 04/22/1999 | COMPLIANCE ASSURANCE | ||||||||
TIN | 01/27/1999 | 04/22/1999 | IN-COMPLIANCE | SHEFFIELD_C | 6/0 | COMPLIANCE ASSURANCE | |||||
ATCI | 04/21/1998 | 05/15/1998 | MINOR OUT-OF-COMPLIANCE | COMPLIANCE ASSURANCE | |||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Enforcement Referral | 05/03/2024 | Accepted | RAMSEY_TH_1 | Enforcement | |||||||
Electronic Communication | 05/31/2023 | Satisfied | KEIM_MJ_1 | Routine Compliance | |||||||
Site Inspection | 05/31/2023 | Major Out of Compliance | KEIM_MJ_1 | 6/0 | Routine Compliance | ||||||
Letter | 05/31/2023 | Satisfied | KEIM_MJ_1 | Compliance Assistance | |||||||
TCAR | 05/16/2023 | Satisfied | RAMSEY_TH_1 | Closure | |||||||
Electronic Communication | 05/16/2023 | Satisfied | RAMSEY_TH_1 | Closure | |||||||
Document Management | 05/16/2023 | Satisfied | RAMSEY_TH_1 | Closure | |||||||
Letter | 05/16/2023 | Satisfied | RAMSEY_TH_1 | Closure | |||||||
Record Document | 06/16/2020 | Satisfied | KEIM_MJ_1 | Compliance Assistance | |||||||
Letter | 06/12/2020 | Satisfied | KEIM_MJ_1 | Compliance Assistance | |||||||
Site Inspection | 06/12/2020 | Major Out of Compliance | KEIM_MJ_1 | 6/0 | Routine Compliance | ||||||
Electronic Communication | 06/03/2020 | Satisfied | KEIM_MJ_1 | Routine Compliance | |||||||
Electronic Communication | 11/30/2017 | Satisfied | KEIM_MJ_1 | Routine Compliance | |||||||
Site Inspection | 11/30/2017 | In Compliance | KEIM_MJ_1 | 6/0 | Routine Compliance | ||||||
Phone Conversation | 11/30/2017 | Satisfied | KEIM_MJ_1 | Routine Compliance | |||||||
Issue Document | 11/30/2017 | Satisfied | KEIM_MJ_1 | Routine Compliance | |||||||
Discharge Reporting | 11/17/2015 | Satisfied | SHULAW_BJ_1 | Discharge | |||||||
Issue Document | 06/18/2015 | Satisfied | HOLTKAMP_JJ_1 | Non-Compliance | |||||||
Site Inspection | 06/10/2015 | In Compliance | SHULAW_BJ_1 | 6/0 | Non-Compliance | ||||||
Letter | 04/06/2015 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 10/27/2014 | Satisfied | SHULAW_BJ_1 | Routine Compliance | |||||||
Letter | 10/27/2014 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Site Inspection | 10/27/2014 | Minor Out of Compliance | SHULAW_BJ_1 | 6/0 | Routine Compliance | ||||||
Site Inspection | 10/23/2014 | In Compliance | SHULAW_BJ_1 | 0/0 | Discharge | ||||||
Site Inspection | 07/31/2012 | In Compliance | OYMAYAN_AJ_1 | 6/0 | Routine Compliance | ||||||
Letter | 06/04/2012 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Letter | 01/09/2012 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 01/09/2012 | Satisfied | SHULAW_BJ_1 | Routine Compliance | |||||||
Site Inspection | 01/09/2012 | Minor Out of Compliance | SHULAW_BJ_1 | 6/0 | Routine Compliance | ||||||
Enforcement Tracking | 05/25/2011 | Closed Without Enforcement | DEFALCO_L | Enforcement | |||||||
Issue Document | 05/25/2011 | Satisfied | DEFALCO_L | Enforcement | |||||||
Site Inspection | 05/24/2011 | In Compliance | SHULAW_BJ_1 | 6/0 | Non-Compliance | ||||||
Enforcement Referral | 04/19/2011 | Accepted | DEFALCO_L | Enforcement | |||||||
Site Inspection | 04/13/2011 | Minor Out of Compliance | SHULAW_BJ_1 | 6/0 | Non-Compliance | ||||||
Letter | 04/13/2011 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Letter | 02/10/2011 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Letter | 09/16/2010 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Site Inspection | 09/16/2010 | Minor Out of Compliance | SHULAW_BJ_1 | 6/0 | Routine Compliance | ||||||
Site Inspection | 08/05/2009 | In Compliance | SHULAW_BJ_1 | 6/0 | Non-Compliance | ||||||
Letter | 06/29/2009 | Satisfied | KASSEES_RP_1 | Non-Compliance | |||||||
Site Inspection | 02/27/2009 | Minor Out of Compliance | SHULAW_BJ_1 | 6/0 | Routine Compliance | ||||||
Letter | 02/27/2009 | Satisfied | SHULAW_BJ_1 | Non-Compliance | |||||||
Site Inspection | 06/24/2008 | In Compliance | OYMAYAN_AJ_1 | 6/0 | Non-Compliance | ||||||
Site Inspection | 01/17/2008 | Minor Out of Compliance | KASSEES_RP_1 | 6/0 | Routine Compliance | ||||||
Letter | 01/17/2008 | Satisfied | KASSEES_RP_1 | Non-Compliance | |||||||
Site Inspection | 06/25/2007 | In Compliance | KASSEES_RP_1 | 6/0 | Non-Compliance | ||||||
Emergency Preparedness Information | 05/24/2007 | Satisfied | KASSEES_RP_1 | Routine Compliance | |||||||
Letter | 02/26/2007 | Satisfied | KASSEES_RP_1 | Non-Compliance | |||||||
Letter | 02/26/2007 | Warning Letter Issued | KASSEES_RP_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 02/15/2007 | Satisfied | KASSEES_RP_1 | Routine Compliance | |||||||
Site Inspection | 01/10/2007 | Major Out of Compliance | KASSEES_RP_1 | 6/0 | Routine Compliance | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
06/12/2020 | 5101 | SNC-B | 3.9 Small diameter integral piping release detection requirements not met. | Have the line leak detectors installed with capabilities of shutting off the pump when a leak is detected. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
09/10/1987 | COMPLETED | 77 | EARLY DETECTION INCENTIVE-ELIGIBLE | ||||||||