Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/10/2025 Last Data Refresh: 05/09/2025 Report Generated from DOPPLER | |||||||||||
District | Northeast | Type | Retail Station | ||||||||
County | Taylor | Status | OPEN | ||||||||
ID | 8517106 | Latitude | 30° 6' 32.2932 | ||||||||
Name |
MUNCHIES FOOD STORE 1200 S BYRON BUTLER PKWY HWY 19 N |
Longitude | 83° 35' 19.8429 | ||||||||
PERRY, FL 32347-9375 | LL Method | DPHO | |||||||||
Contact | SHAFIQ ULLAH | LL Status | REVIEWED | ||||||||
Phone | (850) 584-4044 | Status Date | 04/07/2003 | ||||||||
Account Owner Information | |||||||||||
Name | TASANU INC 1200 S BYRON BUTLER PKWY PERRY, FL 32347 |
Effective Date | 04/01/2024 | ||||||||
Contact | SAHFIQ ULLAH | ||||||||||
Phone | (850) 584-4044 | ||||||||||
RIPON.ULLAHA@ICLOUD.COM | |||||||||||
Placard # / Date | 693520 - 06/22/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | TASANU INC 1200 S BYRON BUTLER PKWY PERRY, FL 32347 |
Effective Date | 04/01/2024 | ||||||||
Contact | SAHFIQ ULLAH | ||||||||||
Phone | (850) 584-4044 | ||||||||||
RIPON.ULLAHA@ICLOUD.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 1000 | Kerosene (K) | 07/01/1992 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment (M) Spill containment bucket (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (I) Suction piping system (K) Dispenser liners |
(4) Visual inspect dispenser liners (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
8 | 12000 | Unleaded Gas (B) | 02/01/2009 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (I) Double wall (L) Compartmented (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
9 | 16000 | Vehicular Diesel (D) | 02/01/2009 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (I) Double wall (L) Compartmented (M) Spill containment bucket (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 12000 | Vehicular Diesel (D) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1R1 | 6000 | Unleaded Gas (B) | 12/01/1986 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 4000 | Unleaded Gas (B) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2R1 | 6000 | Unleaded Gas (B) | 12/01/1986 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 3000 | Leaded Gas (A) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3R1 | 4000 | Unleaded Gas (B) | 12/01/1986 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 3000 | Leaded Gas (A) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4R1 | 4000 | Unleaded Gas (B) | 12/01/1986 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 3000 | Unleaded Gas (B) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off |
(C) Fiberglass (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5R1 | 12000 | Vehicular Diesel (D) | 12/01/1986 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (H) Impressed current CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (E) Cathodic protection (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 3000 | Unleaded Gas (B) | 07/01/1978 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (C) Fiberglass | (Y) Unknown | |||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 07/30/2021 | 07/30/2022 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 07/30/2020 | 07/30/2021 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 07/30/2019 | 07/30/2020 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 07/30/2018 | 08/30/2019 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 07/30/2017 | 07/30/2018 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 03/06/2015 | 03/06/2016 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 03/06/2014 | 03/06/2015 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 03/06/2013 | 03/06/2014 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 03/06/2010 | 03/06/2011 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 03/06/2009 | 03/06/2010 | COMMERCE & INDUSTRY | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCI | 09/20/2005 | 09/21/2005 | IN-COMPLIANCE | PAUL HUTCHERSON | 1/4 | COMPLIANCE ASSURANCE | |||||
TCI | 06/24/2005 | 07/28/2005 | MINOR OUT-OF-COMPLIANCE | ECT/BUSEN_K | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes 5 USTS ARE EXPECTED TO BE REMOVED AND REPLACED SUMMER OF 2005. | |||||||||||
CWOE | 05/04/2004 | 09/29/2004 | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CWOE | |||||||||||
RRBD | 05/04/2004 | 06/15/2004 | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RRBD SENSOR REPLACED | |||||||||||
TCR | 05/04/2004 | 10/28/2004 | IN-COMPLIANCE | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes TCR SENSOR REPLACED | |||||||||||
NCLI | 04/07/2004 | 04/14/2004 | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes NCLI | |||||||||||
TCI | 03/31/2004 | 04/14/2004 | MINOR OUT-OF-COMPLIANCE | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes TCI | |||||||||||
RRBD | 03/28/2003 | 08/12/2003 | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RRBD TESTS SUBMITTED BY J&J EQUIPMENT 03/28/2003 | |||||||||||
NCLI | 03/10/2003 | 03/17/2003 | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes NCLI | |||||||||||
TCI | 02/28/2003 | 03/17/2003 | MINOR OUT-OF-COMPLIANCE | GARRY ALLSHOUSE | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes 157 | |||||||||||
TCR | 02/25/2002 | 03/15/2002 | IN-COMPLIANCE | GARRY ALLSHOUSE | 1/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes ANTI-SYPHON VALVE | |||||||||||
CWOE | 02/25/2002 | 03/15/2002 | GARRY ALLSHOUSE | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes COMPLIED | |||||||||||
TCI | 12/05/2001 | 01/28/2002 | SIGNIFICANT OUT-OF-COMPLIANCE | ALLSHOUSE, G | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes ANNUAL INSPECTION | |||||||||||
RRBD | 04/17/2001 | 04/17/2001 | MEISSNER_R | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CLEARED VIOLATIONS | |||||||||||
TCR | 02/13/2001 | 03/06/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | MEISSNER_R | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes TWO VIOLATONS CLOSED | |||||||||||
PDNE | 01/16/2001 | 01/17/2001 | COMPLIANCE ASSURANCE | ||||||||
TCI | 11/30/2000 | 12/18/2000 | SIGNIFICANT OUT-OF-COMPLIANCE | MEISSNER_R | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes NEEDS LEAK DETECTION, LEAKING DISP & RUSTY SEC CONT | |||||||||||
TCR | 03/03/2000 | 03/16/2000 | IN-COMPLIANCE | MEISSNER_R | 0/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes ALL VIOLATIONS CLEARED | |||||||||||
TCR | 01/20/2000 | 02/09/2000 | IN-COMPLIANCE | MEISSNER_R | 0/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes ALL VIOLATIONS CLEARED EXCEPT FAILURE T0 CLOSE MONITORING WELLS | |||||||||||
TCI | 10/12/1999 | 11/23/1999 | SIGNIFICANT OUT-OF-COMPLIANCE | MEISSNER_R | 1/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes GIVEN 60 DAYS TO CORRECT VIOLATIONS | |||||||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Letter | 07/23/2024 | Satisfied | STERLING_C | Enforcement | |||||||
Enforcement Referral | 01/03/2024 | Accepted | ZIMMERMAN_RA_2 | Enforcement | |||||||
Electronic Communication | 11/07/2023 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 08/25/2023 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Site Inspection | 08/24/2023 | Minor Out of Compliance | ZIMMERMAN_RA_2 | 1/2 | Routine Compliance | ||||||
Letter | 08/24/2023 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 08/10/2023 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 05/09/2022 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Record Document | 05/09/2022 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 10/25/2021 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 10/25/2021 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Site Inspection | 10/25/2021 | Major Out of Compliance | ZIMMERMAN_RA_2 | 1/2 | Routine Compliance | ||||||
Phone Conversation | 09/09/2021 | Satisfied | ZIMMERMAN_RA_2 | Routine Compliance | |||||||
Electronic Communication | 05/21/2021 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Record Document | 05/21/2021 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 05/21/2021 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Site Inspection | 08/10/2019 | Minor Out of Compliance | ZIMMERMAN_RA_2 | 1/2 | Routine Compliance | ||||||
Electronic Communication | 08/10/2019 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 08/10/2019 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 07/25/2019 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 12/15/2017 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Site Inspection | 12/15/2017 | In Compliance | ZIMMERMAN_RA_2 | 1/2 | Compliance Assistance | ||||||
Phone Conversation | 12/01/2017 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Phone Conversation | 09/29/2017 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 08/31/2017 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Electronic Communication | 08/31/2017 | Satisfied | ZIMMERMAN_RA_2 | Routine Compliance | |||||||
Site Inspection | 08/31/2017 | Minor Out of Compliance | ZIMMERMAN_RA_2 | 1/2 | Routine Compliance | ||||||
Phone Conversation | 07/25/2017 | Satisfied | ZIMMERMAN_RA_2 | Routine Compliance | |||||||
Site Inspection | 11/10/2015 | In Compliance | GRAHAM_DL_1 | 1/2 | Routine Compliance | ||||||
Electronic Communication | 05/12/2014 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 04/17/2014 | Minor Out of Compliance | GRAHAM_DL_1 | 1/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 04/17/2014 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Letter | 04/17/2014 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Record Document | 09/12/2013 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Letter | 08/01/2013 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Letter | 03/07/2013 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 03/07/2013 | Minor Out of Compliance | GRAHAM_DL_1 | 1/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 03/07/2013 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 11/23/2010 | In Compliance | GRAHAM_DL_1 | 1/2 | Routine Compliance | ||||||
Electronic Communication | 04/06/2010 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Meeting | 04/06/2010 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Record Document | 04/02/2010 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Letter | 12/31/2009 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 12/31/2009 | Minor Out of Compliance | GRAHAM_DL_1 | 1/2 | Non-Compliance | ||||||
Record Document | 12/08/2009 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Phone Conversation | 12/04/2009 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Letter | 11/17/2009 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 10/05/2009 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Letter | 10/05/2009 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 10/05/2009 | Major Out of Compliance | GRAHAM_DL_1 | 1/2 | Routine Compliance | ||||||
Record Document | 06/23/2009 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 06/23/2009 | In Compliance | GRAHAM_DL_1 | 1/2 | Installation | ||||||
Letter | 06/19/2009 | Satisfied | GRAHAM_DL_1 | Closure | |||||||
TCAR | 06/19/2009 | Complete | GRAHAM_DL_1 | Closure | |||||||
Site Inspection | 04/10/2009 | In Compliance | GRAHAM_DL_1 | 1/5 | Closure | ||||||
Site Inspection | 11/05/2008 | In Compliance | GRAHAM_DL_1 | 1/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 11/05/2008 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 08/02/2007 | In Compliance | HUTCHERSON_P | 1/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/02/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 05/23/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 02/14/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 09/20/2006 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Site Inspection | 08/16/2006 | In Compliance | HUTCHERSON_P | 1/5 | Routine Compliance | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
08/24/2023 | 6001 | Minor | 2.1 No reasonable access provided. | Grant access to re-inspection; contact ACEPD to schedule compliance re-inspection. | |||||||
08/24/2023 | 6003 | Minor | 2.2 Registration Form not submitted for a new system, change in service, closure, owner change, or discovery of unregistered facility. | Contact tanks registration, change registration contact information – email corrected registration information from FDEP tanks registration section. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
07/11/1991 | ACTIVE | 30 | PETROLEUM LIABILITY AND RESTORATION INSURANCE PROGRAM-ELIGIBLE | ||||||||
12/01/1988 | COMPLETED | 78 | |||||||||