Report Run Date: 04/19/2025        Last Data Refresh: 04/18/2025        Report Generated from DOPPLER
 
District Northwest   Type    Federal Government
 
County Bay   Status    OPEN
 
ID 8518667   Latitude    30° 10' 43.2347
 
Name NAVAL SUPPORT ACTIVITY PANAMA CITY
101 VERNON AVE
Longitude    85° 45' 16.785
  PANAMA CITY BEACH, FL 32407-7018 LL Method    DPHO
 
Contact CHARLOTTE A COPE   LL Status    REVIEWED
 
Phone (850) 235-5888   Status Date    10/13/2003
 
Account Owner Information
 
Name US NAVY - NAVAL SUPPORT ACTIVITY PC
101 VERNON AVE
Panama City Beach, FL 32407
Effective Date    08/30/1999
 
Contact PUBLIC WORKS ENVIRONMENTAL
 
Phone (850) 235-5888
 
Email CHARLOTTE.A.COPE.CIV@US.NAVY.MIL
  Placard # / Date    698183 - 07/01/2024
Property Owner Information
 
Name US NAVY - NAVAL SUPPORT ACTIVITY PC
101 VERNON AVE
Panama City Beach, FL 32407
Effective Date    06/20/1985
 
Contact PUBLIC WORKS ENVIRONMENTAL
 
Phone (850) 235-5888
 
Email CHARLOTTE.A.COPE.CIV@US.NAVY.MIL
 
 
 
 
 
 
 
 
 
Tank Tank Size Content Installed Placement Status
172R1 2000 Unleaded Gas (B) 08/01/1997 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(N) Flow shut-Off
(O) Tight fill
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
278AR1 15000 Vehicular Diesel (D) 02/01/1989 UNDERGROUND In Service (U)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(I) Double wall
(M) Spill containment bucket
(N) Flow shut-Off
  (A) Abv, no soil contact
(C) Fiberglass
(D) External protective coating
(I) Suction piping system
(J) Pressurized piping system
(2) Visual inspect pipe sumps
(F) Monitor dbl wall tank space
(K) Monitor dbl wall pipe space
 
 
Tank Tank Size Content Installed Placement Status
278BR1 15000 Vehicular Diesel (D) 02/01/1989 UNDERGROUND In Service (U)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(I) Double wall
(M) Spill containment bucket
(N) Flow shut-Off
  (A) Abv, no soil contact
(C) Fiberglass
(D) External protective coating
(I) Suction piping system
(J) Pressurized piping system
(2) Visual inspect pipe sumps
(F) Monitor dbl wall tank space
(K) Monitor dbl wall pipe space
 
 
Tank Tank Size Content Installed Placement Status
327CR1 2000 Unleaded Gas (B) 05/28/2019 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(N) Flow shut-Off
(O) Tight fill
(P) Level gauges/alarms
(X) Concrete
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(N) Approved synthetic material
(4) Visual inspect dispenser liners
(F) Monitor dbl wall tank space
(H) Mechanical line leak detector
(Q) Visual inspection of ASTs
(R) Monitor tank bottom space
 
 
Tank Tank Size Content Installed Placement Status
350GT 722 Emerg Generator Diesel (G) 08/18/2015 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(D) External protective coating
(I) Suction piping system
(D) SPCC Plan
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
544GT 8000 Emerg Generator Diesel (G) 10/01/2023 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(A) Ball check valve
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(I) Suction piping system
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
551-N 30000 Jet Fuel (F) 11/01/2002 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(J) Pressurized piping system
(1) Continuous electronic sensing
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
551-S 30000 Jet Fuel (F) 11/01/2002 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(J) Pressurized piping system
(1) Continuous electronic sensing
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
577 2000 Vehicular Diesel (D) 01/01/2005 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(J) Pressurized piping system
(K) Dispenser liners
(1) Continuous electronic sensing
(4) Visual inspect dispenser liners
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
591ER1 6000 Used Oil (J) 12/15/2016 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(6) External piping monitoring
(D) SPCC Plan
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
591WR1 6000 Used Oil (J) 12/15/2016 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(6) External piping monitoring
(D) SPCC Plan
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
600 8000 Waste Oil (L) 10/01/2011 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
654D 20000 Vehicular Diesel (D) 04/11/2016 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(C) Fiberglass
(D) External protective coating
(F) Double wall
(I) Suction piping system
(3) Electronic monitor pipe sumps
(D) SPCC Plan
(F) Monitor dbl wall tank space
(G) Electronic line leak detector
(Q) Visual inspection of ASTs
(R) Monitor tank bottom space
(S) Statistical Inventory Reconcile
(V) Suction pump check valve
 
 
Tank Tank Size Content Installed Placement Status
654M 12000 Unleaded Gas (B) 04/11/2016 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(C) Fiberglass
(D) External protective coating
(F) Double wall
(I) Suction piping system
(3) Electronic monitor pipe sumps
(F) Monitor dbl wall tank space
(G) Electronic line leak detector
(Q) Visual inspection of ASTs
(R) Monitor tank bottom space
 
 
Tank Tank Size Content Installed Placement Status
G300R1 1000 Emerg Generator Diesel (G) 06/01/1995 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(L) Compartmented
(M) Spill containment bucket
(P) Level gauges/alarms
(X) Concrete
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(D) External protective coating
(I) Suction piping system
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
G470 806 Emerg Generator Diesel (G) 04/23/2024 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(I) Suction piping system
(N) Approved synthetic material
(1) Continuous electronic sensing
(2) Visual inspect pipe sumps
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
G608 660 Emerg Generator Diesel (G) 01/01/2010 ABOVEGROUND In Service (U)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(I) Suction piping system
(D) SPCC Plan
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
12 11200 Vehicular Diesel (D) 07/01/1943 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
13 11200 Unleaded Gas (B) 07/01/1943 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
172 2000 Unleaded Gas (B) 07/01/1980 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
(N) Flow shut-Off
  (D) External protective coating
(I) Suction piping system
(D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
241 6000 Unleaded Gas (B) 07/01/1958 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
242 6000 Leaded Gas (A) 07/01/1958 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
243 6000 Unleaded Gas (B) 07/01/1980 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
278A 7500 Vehicular Diesel (D) 07/01/1977 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
278B 7500 Vehicular Diesel (D) 07/01/1964 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
278C 7500 Vehicular Diesel (D) 07/01/1977 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
278D 7500 Vehicular Diesel (D) 07/01/1964 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
300A 2500 Emerg Generator Diesel (G) 07/01/1972 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (D) External protective coating (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
307 5000 Vehicular Diesel (D) 07/01/1964 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
307R1 6000 Vehicular Diesel (D) 02/01/1989 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(I) Double wall
(M) Spill containment bucket
(N) Flow shut-Off
  (C) Fiberglass
(F) Double wall
(I) Suction piping system
(J) Pressurized piping system
(K) Dispenser liners
(F) Monitor dbl wall tank space
 
 
Tank Tank Size Content Installed Placement Status
318B 300 Waste Oil (L) 07/01/1984 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
324 300 Waste Oil (L) 07/01/1984 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
325A 20000 Jet Fuel (F) 07/01/1976 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
  (D) External protective coating (8) Manually sampled wells
 
 
Tank Tank Size Content Installed Placement Status
325B 20000 Jet Fuel (F) 07/01/1976 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
  (D) External protective coating (8) Manually sampled wells
 
 
Tank Tank Size Content Installed Placement Status
325C 20000 Jet Fuel (F) 07/01/1976 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
  (D) External protective coating (8) Manually sampled wells
 
 
Tank Tank Size Content Installed Placement Status
327 2500 Unleaded Gas (B) 07/01/1983 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass   (C) Fiberglass (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
327A 1000 Unleaded Gas (B) 08/01/1991 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
  (A) Abv, no soil contact
(C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(4) Visual inspect dispenser liners
(F) Monitor dbl wall tank space
(H) Mechanical line leak detector
(M) Manual tank gauging - USTs
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
327C 2000 Unleaded Gas (B) 06/01/1998 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(4) Visual inspect dispenser liners
(D) SPCC Plan
(F) Monitor dbl wall tank space
(H) Mechanical line leak detector
(K) Monitor dbl wall pipe space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
333 550 Waste Oil (L) 07/01/1979 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass   (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
362A 12000 Vehicular Diesel (D) 07/01/1981 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
(N) Flow shut-Off
(P) Level gauges/alarms
  (C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(1) Continuous electronic sensing
(2) Visual inspect pipe sumps
(3) Electronic monitor pipe sumps
(4) Visual inspect dispenser liners
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
362B 12000 Vehicular Diesel (D) 07/01/1981 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
(N) Flow shut-Off
(P) Level gauges/alarms
  (C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(1) Continuous electronic sensing
(2) Visual inspect pipe sumps
(3) Electronic monitor pipe sumps
(4) Visual inspect dispenser liners
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
362C 12000 Vehicular Diesel (D) 07/01/1981 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
(N) Flow shut-Off
(P) Level gauges/alarms
  (C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(1) Continuous electronic sensing
(2) Visual inspect pipe sumps
(3) Electronic monitor pipe sumps
(4) Visual inspect dispenser liners
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
362D 12000 Unleaded Gas (B) 07/01/1981 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
(N) Flow shut-Off
(P) Level gauges/alarms
  (C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(K) Dispenser liners
(1) Continuous electronic sensing
(2) Visual inspect pipe sumps
(3) Electronic monitor pipe sumps
(4) Visual inspect dispenser liners
(K) Monitor dbl wall pipe space
(L) Automatic tank gauging - USTs
 
 
Tank Tank Size Content Installed Placement Status
362E 2000 Vehicular Diesel (D) 05/01/1999 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(F) Fiberglass clad steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (B) Steel/galvanized metal
(C) Fiberglass
(F) Double wall
(J) Pressurized piping system
(3) Electronic monitor pipe sumps
(4) Visual inspect dispenser liners
(F) Monitor dbl wall tank space
(K) Monitor dbl wall pipe space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
363 6000 Waste Oil (L) 07/01/1981 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(E) Fiberglass
(M) Spill containment bucket
  (C) Fiberglass (8) Manually sampled wells
 
 
Tank Tank Size Content Installed Placement Status
439 4900 Waste Oil (L) 07/01/1988 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(K) AST containment
  (Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
439R1 5000 Waste Oil (L) 01/01/2004 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(M) Spill containment bucket
(P) Level gauges/alarms
  (A) Abv, no soil contact
(B) Steel/galvanized metal
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
462E 6000 Waste Oil (L) 08/01/1996 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(D) SPCC Plan
(Q) Visual inspection of ASTs
(Z) DEP approved monitoring
 
 
Tank Tank Size Content Installed Placement Status
462W 6000 Waste Oil (L) 08/01/1996 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(D) SPCC Plan
(Q) Visual inspection of ASTs
(Z) DEP approved monitoring
 
 
Tank Tank Size Content Installed Placement Status
591-E 6000 Waste Oil (L) 03/01/2006 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(6) External piping monitoring
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
591-W 6000 Waste Oil (L) 03/01/2006 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(I) Double wall
(K) AST containment
(N) Flow shut-Off
(P) Level gauges/alarms
  (A) Abv, no soil contact
(D) External protective coating
(G) Pipe trench liner
(J) Pressurized piping system
(6) External piping monitoring
(F) Monitor dbl wall tank space
(Q) Visual inspection of ASTs
 
 
Tank Tank Size Content Installed Placement Status
G110A 500 Emerg Generator Diesel (G) 07/01/1957 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
G110AB 500 Emerg Generator Diesel (G) 07/01/1982 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(M) Spill containment bucket
  (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
G129 550 Emerg Generator Diesel (G) 07/01/1979 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(M) Spill containment bucket
(N) Flow shut-Off
  (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
G300-A 2500 Emerg Generator Diesel (G) 06/01/1972 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(M) Spill containment bucket
(N) Flow shut-Off
  (D) External protective coating (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
G322 1175 Emerg Generator Diesel (G) 07/01/1975 UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(M) Spill containment bucket
(N) Flow shut-Off
  (B) Steel/galvanized metal (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
G326 560 Emerg Generator Diesel (G) 07/01/1976 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(K) AST containment
(R) Double wall - tank jacket
  (B) Steel/galvanized metal (D) SPCC Plan
 
 
Tank Tank Size Content Installed Placement Status
G9-A 10000 Emerg Generator Diesel (G) 07/01/1973 ABOVEGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel
(K) AST containment
(R) Double wall - tank jacket
  (D) External protective coating (D) SPCC Plan
(I) Not required
 
 
Tank Tank Size Content Installed Placement Status
240 600 Waste Oil (L) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (Y) Unknown (X) None
 
 
Tank Tank Size Content Installed Placement Status
G101 150 Emerg Generator Diesel (G) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (B) Steel/galvanized metal (X) None
 
 
Tank Tank Size Content Installed Placement Status
G9 1200 Emerg Generator Diesel (G) UNDERGROUND Removed from Site (B)
 
Constructions   Pipings Monitorings
(C) Steel   (B) Steel/galvanized metal (X) None
 
 
Insurance Documents
 
FR Type   Effective Date Expiration Date Company Name
EXEMPT-STATE OR FEDERAL GOVERNMENT ENTITY  
EXEMPT-STATE OR FEDERAL GOVERNMENT ENTITY   09/18/2018 09/18/2038
EXEMPT-STATE OR FEDERAL GOVERNMENT ENTITY   03/29/2009 03/29/2010
 
 
Legacy Compliance Activity Information
 
Activity
Code
Date
Initiated
Date
Completed
Results Inspector AST/UST
Count
Description
TCI 12/21/2005 01/06/2006 IN-COMPLIANCE BRAZILE 7/6 COMPLIANCE ASSURANCE
 
TCI 07/20/2005 07/21/2005 IN-COMPLIANCE BRAZILE 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes POST HURRICANE DENNIS INSPECTION, NO DAMAGE AT THE TIME OF THE INSPECTION
 
TXI 02/08/2005 02/14/2005 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
 Completion Notes CLOSURE OF TANK 362E AND PIPING
 
DPRI 02/08/2005 02/14/2005 IN-COMPLIANCE PINKOVSKY 0/0 TERMINAL FACILITY PROJECT
 
 Completion Notes DPRC #099950
 
TCI 02/08/2005 02/14/2005 IN-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL AND DW AMERON FIBERGLASS, DPRC #099950
 
TXI 12/16/2004 12/17/2004 IN-COMPLIANCE PINKOVSKY 2/0 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL AND DW AMERON; CLOSURE OF TANKS 462 E & W
 
TIN 09/30/2004 09/30/2004 IN-COMPLIANCE PINKOVSKY 6/9 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL AND DW AMERON FIBERGLASS; VEEDER ROOT TLS350 PLUS ATG INSTALLATIONS AT 362, 278, 551, 172 AREAS
 
TCI 09/24/2004 09/28/2004 IN-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes POST HURRICANE IVAN INSPECTION
 
DSNR 08/11/2004 08/16/2004 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes VISUAL CHECKS AND OVA READINGS INDICATE NO FUEL LEAKS. POSSIBLY FAULTY ELECTRICAL CONNECTOR.
 
IRFR 08/05/2004 08/05/2004 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes INF FOR PERMALERT SENSOR CABLE ALARM IN DW PIPING.
 
TCR 06/14/2004 06/15/2004 IN-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL & AMERON DW
 
TIN 06/14/2004 06/15/2004 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL, NEW TANK 439R1
 
RRBD 03/24/2004 03/25/2004 PINKOVSKY 0/0 COMPLIANCE ASSURANCE
 
TCI 03/23/2004 03/25/2004 SIGNIFICANT OUT-OF-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL & DW AMERON FIBERGLASS; DPRI, CERTIFICATE #099936
 
DPRI 03/23/2004 03/25/2004 IN-COMPLIANCE PINKOVSKY 9/6 TERMINAL FACILITY PROJECT
 
 Completion Notes CERTIFICATE #099936
 
TXI 01/14/2004 01/28/2004 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL
 
DSNR 10/15/2003 10/15/2003 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes DSNR FOR TANK 362-D (TWO SIR INCONCLUSIVES)--TANK AND LINE TESTS DONE 8/6/2003, RECEIVED 10/15/2003.
 
TCR 09/30/2003 10/01/2003 IN-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: ABOVEGROUND- IRON; UNDERGROUND AMERON DOUBLEWALLED FIBERGLASS
 
TIN 08/15/2003 08/20/2003 IN-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: STEEL, INSTALL TWO 3000 GALLON ASTS
 
IRFR 07/23/2003 07/23/2003 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes INF FOR TWO CONSECUTIVE INCONCLUSIVE SIR REPORTS, TANK 362D. TANK TIGHTNESS TEST BEING ARRANGED.
 
DSNR 04/24/2003 04/29/2003 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes DSNR FOR INVESTIGATION REPORT RECEIVED FROM S. PUMP AND TANK--NO WATER IN TANK INTERSTICE AND SENSORS REPLACED.
 
IRFR 03/27/2003 03/28/2003 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes INF FOR WATER ALARM IN TANK 278BRI INTERSTICE.
 
TCI 03/26/2003 03/31/2003 MINOR OUT-OF-COMPLIANCE PINKOVSKY 9/6 COMPLIANCE ASSURANCE
 
 Completion Notes PIPING: IRON, FIBERGLASS (AMERON) NEW DPRI CERTIFICATE #099925
 
DPRI 03/26/2003 03/31/2003 PINKOVSKY 9/6 TERMINAL FACILITY PROJECT
 
 Completion Notes CERTIFICATE # 099925
 
LTR 08/27/2002 08/27/2002 PINKOVSKY 0/0 COMPLIANCE ASSURANCE
 
 Completion Notes NOTIFICATION OF COUNTY REVIEW FOR DPRI
 
DSNR 06/05/2002 06/06/2002 DREW PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes RELEASE CONFINED TO SECONDARY PIPING, PER 30 MAY 2002 LTR.
 
TCR 04/26/2002 04/29/2002 IN-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
TCI 03/28/2002 04/01/2002 MINOR OUT-OF-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
IRFR 03/27/2002 03/29/2002 PINKOVSKY 0/0 DISCHARGE PROJECT
 
 Completion Notes INCIDENT REPORT FOR SENSOR CABLE ALARM IN DOUBLEWALLED PIPING
 
TXI 12/26/2001 12/27/2001 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
 Completion Notes CLOSING OLD PIPELINE NEAR BLDG 370, 393, 431(OLD TANK #11 AREA)
 
TCI 03/28/2001 03/28/2001 IN-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
TCR 08/02/2000 08/04/2000 IN-COMPLIANCE PINKOVSKY 0/2 COMPLIANCE ASSURANCE
 
TCR 06/26/2000 06/28/2000 MINOR OUT-OF-COMPLIANCE PINKOVSKY 0/0 COMPLIANCE ASSURANCE
 
TCI 03/22/2000 03/27/2000 MINOR OUT-OF-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
TXI 02/23/2000 02/24/2000 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
TXI 10/13/1999 10/13/1999 IN-COMPLIANCE PINKOVSKY 1/0 COMPLIANCE ASSURANCE
 
TIN 05/20/1999 06/01/1999 IN-COMPLIANCE PINKOVSKY 0/0 COMPLIANCE ASSURANCE
 
TIN 02/19/1999 03/17/1999 IN-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
TCI 02/18/1999 03/16/1999 MINOR OUT-OF-COMPLIANCE PINKOVSKY 7/6 COMPLIANCE ASSURANCE
 
TXI 01/15/1999 03/11/1999 IN-COMPLIANCE PINKOVSKY 0/0 COMPLIANCE ASSURANCE
 
 
 
Compliance Activity Information
 
Activity
Code
Date
Completed
Results Inspector AST/UST
Count
Description
Phone Conversation 04/11/2025 Satisfied GARTIN_D Routine Compliance
 
Site Inspection 04/11/2025 Major Out of Compliance GARTIN_D 15/2 Routine Compliance
 
Letter 04/10/2025 Satisfied GARTIN_D Compliance Assistance
 
Electronic Communication 04/10/2025 Satisfied GARTIN_D Routine Compliance
 
Letter 04/10/2025 Satisfied GARTIN_D Compliance Assistance
 
Discharge Reporting 02/20/2025 Satisfied GARTIN_D Discharge
 
Site Inspection 02/20/2025 In Compliance GARTIN_D 13/2 Discharge
 
Enforcement Tracking 12/20/2023 Closed Without Enforcement GILLMAN_M Enforcement
 
Enforcement Referral 08/07/2023 Accepted KHAN_MR_1 Enforcement
 
Letter 05/18/2023 Satisfied WILSON_ML_1 Compliance Assistance
 
Site Inspection 05/18/2023 Major Out of Compliance KHAN_MR_1 13/2 Routine Compliance
 
Issue Document 08/16/2021 Satisfied WILSON_ML_1 Compliance Assistance
 
Letter 08/16/2021 Satisfied WILSON_ML_1 Compliance Assistance
 
Electronic Communication 08/13/2021 Satisfied PANGAHAS_RL_1 Compliance Assistance
 
Letter 05/21/2021 Satisfied WILSON_ML_1 Compliance Assistance
 
Issue Document 05/21/2021 Satisfied WILSON_ML_1 Compliance Assistance
 
Phone Conversation 05/20/2021 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Electronic Communication 05/20/2021 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Site Inspection 05/20/2021 Minor Out of Compliance PANGAHAS_RL_1 13/2 Routine Compliance
 
Electronic Communication 05/20/2021 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Electronic Communication 05/20/2021 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Record Document 06/28/2019 Satisfied PANGAHAS_RL_1 Closure
 
Site Inspection 06/28/2019 In Compliance PANGAHAS_RL_1 13/2 Closure
 
Issue Document 06/25/2019 Satisfied WILSON_ML_1 Installation
 
Site Inspection 06/24/2019 In Compliance PANGAHAS_RL_1 13/2 Installation
 
Site Inspection 05/30/2019 In Compliance GILLMAN_M 13/2 QA/QC
 
Issue Document 10/01/2018 Satisfied WILSON_ML_1 Routine Compliance
 
Letter 10/01/2018 Satisfied WILSON_ML_1 Routine Compliance
 
Site Inspection 09/28/2018 In Compliance PANGAHAS_RL_1 13/2 Routine Compliance
 
Phone Conversation 09/27/2018 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Electronic Communication 09/27/2018 Satisfied PANGAHAS_RL_1 Routine Compliance
 
Site Inspection 12/22/2016 In Compliance BRAZILE_DO_1 2/0 Installation
 
Site Inspection 11/21/2016 In Compliance BRAZILE_DO_1 13/2 Routine Compliance
 
Site Inspection 06/12/2015 In Compliance BRAZILE_DO_1 1/0 Installation
 
Site Inspection 05/13/2015 In Compliance BRAZILE_DO_1 9/2 Routine Compliance
 
Site Inspection 05/30/2013 In Compliance BRAZILE_DO_1 11/2 Routine Compliance
 
Site Inspection 05/10/2012 In Compliance BRAZILE_DO_1 9/2 Routine Compliance
 
Site Inspection 03/06/2012 In Compliance BRAZILE_DO_1 1/35 Closure
 
Site Inspection 03/06/2012 In Compliance BRAZILE_DO_1 1/0 Installation
 
Site Inspection 02/24/2012 In Compliance BRAZILE_DO_1 9/2 Non-Compliance
 
Letter 11/23/2011 Satisfied CLEMONS_AM_1 Closure
 
TCAR 11/23/2011 Satisfied PURDY_EM_1 Closure
 
Enforcement Tracking 10/10/2011 Closed With Enforcement GILLMAN_M Enforcement
 
Document Management 10/10/2011 Complete GILLMAN_M Enforcement
 
Document Management 10/10/2011 Complete GILLMAN_M Enforcement
 
TCAR 09/30/2011 Satisfied CLEMONS_AM_1 Closure
 
Letter 09/30/2011 Satisfied CLEMONS_AM_1 Closure
 
Site Inspection 08/22/2011 In Compliance BRAZILE_DO_1 0/5 Closure
 
Document Management 08/09/2011 Complete GILLMAN_M Enforcement
 
Site Inspection 07/28/2011 In Compliance BRAZILE_DO_1 0/5 Routine Compliance
 
Letter 05/02/2011 Satisfied RHOADS_KM_1 Non-Compliance
 
Site Inspection 04/27/2011 Major Out of Compliance BRAZILE_DO_1 9/6 Routine Compliance
 
Letter 07/26/2010 Satisfied PIERCE_LL_1 Non-Compliance
 
Site Inspection 07/16/2010 Major Out of Compliance BRAZILE_DO_1 9/6 Non-Compliance
 
Enforcement Referral 06/07/2010 Accepted GILLMAN_M Enforcement
 
Letter 06/02/2010 Satisfied PIERCE_LL_1 Non-Compliance
 
Site Inspection 06/02/2010 Major Out of Compliance BRAZILE_DO_1 9/6 Routine Compliance
 
Complaint 03/13/2009 Satisfied BRAZILE_DO_1 Complaint
 
Site Inspection 02/12/2009 In Compliance BRAZILE_DO_1 9/6 Routine Compliance
 
Site Inspection 02/16/2008 In Compliance BRAZILE_DO_1 9/6 Routine Compliance
 
Site Inspection 12/21/2006 In Compliance BRAZILE_DO_1 9/6 Routine Compliance
 
Site Inspection 06/23/2006 In Compliance BRAZILE_DO_1 2/0 Installation
 
 
 
No Open AOCs Found
 
 
Open Violations
 
Insp Date Vio # Significance Violation Text Corrective Action
04/10/2025 6072 Minor 2.7 Integrity testing of secondary containment systems and interstitial spaces not performed per schedule. Have integrity testing conducted for the 3 Dispenser sumps for tank 654M and 654D; Piping and Transition sumps associated with tank 654M/654D, 278AR1, and 278BR1; Double Wall Spill Bucket 278AR1 and 278BR1 and provide current integrity testing results to Daniel.Gartin@flhealth.gov.
 
04/10/2025 6062 Minor 2.5 Release detection devices not tested annually. Provide current annual operability testing for release detection devices of the Spill bucket gauges for tank 278AR1 and 278BR1 and the Automatic Tank Gauge systems with sensor monitoring for tank 278AR1 and 278BR1 to Daniel.Gartin@flhealth.gov.
 
04/10/2025 6021 SNC-B 4.1 Failure of secondary containment to meet standards including: impervious spill containment, liners, allowing for release detection, allow for monitoring point, and hydrant pit secondary containment. Unless concrete meets requirements of secondary containment and can serve to collect potential discharge without release occurring, the system is required to either remove single wall piping for double wall piping installation or make secondary containment meet requirements for impervious to petroleum product. If the concrete trench is designed to be impervious, that information is required to be provided that demonstrates the concrete containment is impervious and capable of holding maximum capacity of a potential discharge from pressurized piping. Ensure Daniel.Gartin@flhealth.gov and Mark.Gillman@FloridaDEP.gov, and Sara.Merritt@FloridaDEP.gov are included regarding communication with this item and the actions the facility will be taking.
 
04/10/2025 7072 Minor 1.8 Annual operability testing of release detection systems not completed. Have annual operability testing for release detection conducted for the following devices: Rupture Basin alarm for tank 591ER1, 591WR1, 350GT, G608, G470, and G300R1; Krueger At-A-Glance Leak Gauge for tank 600 and 544GT; Automatic Tank Gauge systems with interstitial monitoring sensor for 551S, 551N, 654M, 654D, 577, and 172R1. Submit the testing results to Daniel.Gartin@flhealth.gov.
 
04/10/2025 6062 Minor 2.5 Release detection devices not tested annually. Provide the annual operability testing for the line leak detectors of tank 278AR1 and 278BR1 to Daniel.Gartin@flhealth.gov.
 
04/10/2025 7089 Minor 1.11 Integrity testing of secondary containment systems and interstitial spaces not performed per schedule. Submit testing for the double wall piping line's integrity to Daniel.Gartin@flhealth.gov. Note this testing is required to be conducted once within at least every 36 months.
 
04/10/2025 6053 Minor 4.7 Primary overfill protection not provided, registered, or tested as required. Provide current annual operability testing conducted for the Flapper Valve for tank 278AR1 and 278BR1 to Daniel.Gartin@flhealth.gov.
 
04/10/2025 7041 Minor 1.10 Failure to designate, register, or annually test primary overfill protection device, Have the annual operability for overfill prevention testing conducted for the following overfill prevention devices installed on tanks: OPW fuel level gauge for tank 591ER1, 591WR1, and 172R1; Rochester Gauge for tank G608 and G470; Krueger Fuel Level Gauge for tank 600, G300R1, and 350GT [note 350GT has unknown additional fuel gauge on separate compartment requiring testing]; Morrison Clock Gauge for tank 654M, 654D, 551S, 551N and 544GT; Veeder Root overfill alarm for tank 577. Submit associated testing results to Daniel.Gartin@flhealth.gov
 
 
 
Discharge Information
 
Discharge
Date
  Clean Up
Status
Score Eligibility Info Site Manager Phone
08/24/2024   INACTIVE
 
08/11/1997   INACTIVE 9
 
07/17/1997   INACTIVE 9 BOUTWELL_CJ
 
09/17/1996   INACTIVE 9
 
08/25/1995   INACTIVE 9
 
07/17/1995   COMPLETED
 
07/03/1995   INACTIVE 10
 
05/16/1995   INACTIVE 10
 
02/16/1994   INACTIVE 10
 
09/03/1992   INACTIVE 9
 
06/30/1992   INACTIVE 10