District | South | Type | Retail Station | ||||||||
County | Lee | Status | OPEN | ||||||||
ID | 8519083 | Latitude | 26° 21' 2.985 | ||||||||
Name |
HOLE IN ONE FAIRWAYS LLC 10530 ROSEMARY DR |
Longitude | 81° 46' 44.3897 | ||||||||
BONITA SPRINGS, FL 34135 | LL Method | DPHO | |||||||||
Contact | ALEX | LL Status | REVIEWED | ||||||||
Phone | (239) 495-6565 | Status Date | 10/12/2023 | ||||||||
Account Owner Information | |||||||||||
Name | HOLE IN ONE FAIRWAYS LLC 10530 ROSEMARY DR BONITA SPRINGS, FL 34135 |
Effective Date | 05/15/2007 | ||||||||
Contact | ALEX | ||||||||||
Phone | (239) 495-6565 | ||||||||||
JIVANIALEX@GMAIL.COM | |||||||||||
Placard # / Date | 494628 - 10/14/2016 | ||||||||||
Property Owner Information | |||||||||||
Name | CONOCO PHILLIPS 10150 HIGHLAND MANOR DR #200 TAMPA, FL 33610 |
Effective Date | 10/14/2004 | ||||||||
Contact | STEVE BELIN | ||||||||||
Phone | (813) 314-2142 | ||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 9684 | Unleaded Gas (B) | 03/01/1996 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (E) Fiberglass (I) Double wall (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (P) Level gauges/alarms |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 9684 | Unleaded Gas (B) | 03/01/1996 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (E) Fiberglass (I) Double wall (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (P) Level gauges/alarms |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 10000 | Unleaded Gas (B) | 05/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (I) Suction piping system |
(8) Manually sampled wells | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 10000 | Unleaded Gas (B) | 05/01/1976 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(B) Steel/galvanized metal (I) Suction piping system |
(8) Manually sampled wells | |||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 02/13/2014 | 02/13/2016 | CRUM & FORSTER INDEMNITY | ||||||||
INSURANCE | 02/13/2014 | 02/13/2016 | CRUM & FORSTER INDEMNITY | ||||||||
INSURANCE | 02/13/2012 | 02/13/2014 | AMERICAN SAFETY | ||||||||
INSURANCE | 01/12/2011 | 01/12/2012 | ACE | ||||||||
INSURANCE | 09/10/2009 | 09/10/2010 | ZURICH-AMERICAN | ||||||||
INSURANCE | 05/15/2005 | 09/10/2008 | ZURICH-AMERICAN | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCR | 08/04/2005 | 08/04/2005 | IN-COMPLIANCE | J SAIYA | 0/2 | COMPLIANCE ASSURANCE | |||||
CWOE | 08/04/2005 | 08/04/2005 | J SAIYA | 0/2 | COMPLIANCE ASSURANCE | ||||||
RRBD | 06/10/2005 | 06/14/2005 | J SAIYA | 0/2 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RECEIVED DOCUMENTATION OF LINE TEST/MLLD VIA FAX DISCOVERY TANKS PASSED | |||||||||||
NCLI | 05/09/2005 | 05/09/2005 | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | ||||||
TCI | 05/06/2005 | 05/09/2005 | MINOR OUT-OF-COMPLIANCE | J SAIYA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes PIPING-DW FIBERGLASS RDRL-MONTHLY VISUALS/CHARLOTTE MONITORING | |||||||||||
CWOE | 06/24/2004 | 06/24/2004 | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | ||||||
RRBD | 06/24/2004 | 06/24/2004 | IN-COMPLIANCE | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | |||||
TCR | 05/25/2004 | 05/25/2004 | SIGNIFICANT OUT-OF-COMPLIANCE | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes 4-20-2004 - LLD TESTED/PASSED DISCOVERY APRIL 2004 - ATG CERT -CHARLOTTE MONITORING. | |||||||||||
NCLI | 04/23/2004 | 04/27/2004 | DEMACK,P | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 04/06/2004 | 04/06/2004 | SIGNIFICANT OUT-OF-COMPLIANCE | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes PIPING - DW FIBERGLASS RDRL - MONTHLY VISUALS NOTE: LAST 2 TCI INSPECTIONS FACILITY HAS NOTE HAD PAPERWORK AVAILABLE. | |||||||||||
TCR | 08/06/2003 | 09/16/2003 | IN-COMPLIANCE | S. JOHNSON | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes FACILITY HAS INSTALLED A TLS 300 VEETOR ROOT SYSTEM. SYSTEM DOES NOT INCLUDE A PRINTER. FACILITY MUST MANUALLY DOCUMENT MONTHLY LIQUID STATUS. | |||||||||||
TCI | 06/03/2003 | 06/18/2003 | SIGNIFICANT OUT-OF-COMPLIANCE | P.DEMACK | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes PIPING=DW FIBERGLASS RDRL=INTERSTITIAL MONITORING DW TANKS. | |||||||||||
TCR | 03/12/2002 | 03/25/2002 | IN-COMPLIANCE | DEMACK/PECK | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes CHARLOTTE MONITORING IS PERFORMING MONTHLY RELEASE DETECTION CHECKS | |||||||||||
TCI | 10/23/2001 | 10/24/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | PEREZ/DEMACK | 0/2 | COMPLIANCE ASSURANCE | |||||
TCR | 03/13/2001 | 03/19/2001 | IN-COMPLIANCE | HOENE | 2/0 | COMPLIANCE ASSURANCE | |||||
TCI | 11/22/2000 | 12/08/2000 | MINOR OUT-OF-COMPLIANCE | HOENE | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes \ | |||||||||||
TCI | 12/06/1999 | 01/03/2000 | IN-COMPLIANCE | HOENE | 0/2 | COMPLIANCE ASSURANCE | |||||
LTR | 04/08/1999 | 07/07/1999 | HOENE | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 02/12/1999 | 04/12/1999 | MINOR OUT-OF-COMPLIANCE | JOHNSON | 0/0 | COMPLIANCE ASSURANCE | |||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Enforcement Referral | 01/02/2025 | Accepted | PARKS_J_4 | Enforcement | |||||||
Enforcement Referral | 12/19/2024 | Accepted | PARKS_J_4 | Enforcement | |||||||
Enforcement Referral | 12/19/2024 | Accepted | PARKS_J_4 | Enforcement | |||||||
Phone Conversation | 02/27/2024 | Satisfied | PARKS_J_4 | Routine Compliance | |||||||
Site Inspection | 02/27/2024 | Major Out of Compliance | PARKS_J_4 | 0/2 | Routine Compliance | ||||||
Site Inspection | 06/07/2022 | Major Out of Compliance | PARKS_J_4 | 0/2 | Routine Compliance | ||||||
Phone Conversation | 06/07/2022 | Satisfied | PARKS_J_4 | Routine Compliance | |||||||
Letter | 07/01/2021 | Satisfied | KLEINMANN_K_1 | Compliance Assistance | |||||||
Electronic Communication | 06/01/2020 | Satisfied | KLEINMANN_K_1 | Routine Compliance | |||||||
Site Inspection | 06/01/2020 | Major Out of Compliance | KLEINMANN_K_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 02/12/2016 | In Compliance | ZIMMERMAN_CA_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 09/26/2014 | In Compliance | ZIMMERMAN_CA_1 | 0/2 | Non-Compliance | ||||||
Record Document | 07/02/2014 | Satisfied | ZIMMERMAN_CA_1 | Non-Compliance | |||||||
Site Inspection | 06/25/2014 | Minor Out of Compliance | ZIMMERMAN_CA_1 | 0/2 | Non-Compliance | ||||||
Letter | 02/21/2014 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Site Inspection | 02/21/2014 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
Enforcement Tracking | 06/18/2012 | Closed With Enforcement | FOXWORTH_S | Enforcement | |||||||
Site Inspection | 03/15/2012 | In Compliance | ZIMMERMAN_CA_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 03/15/2012 | Satisfied | ZIMMERMAN_CA_1 | Routine Compliance | |||||||
Site Inspection | 03/29/2011 | In Compliance | ZIMMERMAN_CA_1 | 0/2 | Routine Compliance | ||||||
Phone Conversation | 10/05/2010 | Satisfied | SAUTTER_M | Enforcement | |||||||
Site Inspection | 07/09/2010 | Minor Out of Compliance | ZIMMERMAN_CA_1 | 0/2 | Non-Compliance | ||||||
Enforcement Referral | 07/09/2010 | Accepted | MURPHY_EM | Enforcement | |||||||
Letter | 07/09/2010 | Satisfied | ZIMMERMAN_CA_1 | Non-Compliance | |||||||
Letter | 03/26/2010 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Site Inspection | 03/25/2010 | Minor Out of Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
Enforcement Referral | 11/23/2009 | Accepted | MELE_V | Enforcement | |||||||
Site Inspection | 06/26/2009 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Non-Compliance | ||||||
Site Inspection | 03/19/2009 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
Letter | 03/19/2009 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Record Document | 11/12/2008 | Satisfied | ZIMMERMAN_CA_1 | Non-Compliance | |||||||
Site Inspection | 11/07/2008 | In Compliance | JOHNSON_SG_1 | 0/4 | Non-Compliance | ||||||
Letter | 07/10/2008 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Site Inspection | 07/01/2008 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Non-Compliance | ||||||
Site Inspection | 04/08/2008 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
Letter | 04/08/2008 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Site Inspection | 09/06/2007 | Major Out of Compliance | ZIMMERMAN_CA_1 | 0/2 | Non-Compliance | ||||||
Letter | 06/08/2007 | Satisfied | JOHNSON_SG_1 | Non-Compliance | |||||||
Site Inspection | 05/29/2007 | Major Out of Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 02/09/2007 | Satisfied | JOHNSON_SG_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 09/22/2006 | Satisfied | JOHNSON_SG_1 | Routine Compliance | |||||||
Site Inspection | 06/01/2006 | In Compliance | JOHNSON_SG_1 | 0/2 | Routine Compliance | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
02/27/2024 | 6012 | SNC-A | 2.9 No financial responsibility instrument or expired instrument for > 180 days. | FDEP to determine corrective action | |||||||
02/27/2024 | 6072 | Minor | 2.7 Integrity testing of secondary containment systems and interstitial spaces not performed per schedule. | Double-walled spill containment systems shall be tested by October 13, 2018, and every three years thereafter, not to exceed 36 months | |||||||
02/27/2024 | 6062 | Minor | 2.5 Release detection devices not tested annually. | FDEP to determine corrective actions | |||||||
06/07/2022 | 6012 | SNC-A | 2.9 No financial responsibility instrument or expired instrument for > 180 days. | FDEP to determine corrective actions. | |||||||
06/01/2020 | 4007 | Minor | 2.6 Registration fees not paid, placard not posted. | Submit registration fee | |||||||
06/01/2020 | 4014 | SNC-B | 2.9 Failure to maintain and demonstrate financial responsibility. This violation may lead to Placard Revocation and Delivery Prohibition. | Obtain insurance while tanks are on site. | |||||||
06/01/2020 | 4004 | Minor | 2.3 Registration Form not submitted for change in service or closure. | Update registration. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
03/05/1996 | COMPLETED | 31 | |||||||||
05/14/1991 | COMPLETED | 31 | PETROLEUM LIABILITY AND RESTORATION INSURANCE PROGRAM-ELIGIBLE | ||||||||