District | Southwest | Type | Fuel user/Non-retail | ||||||||
County | Polk | Status | OPEN | ||||||||
ID | 8626424 | Latitude | 27° 49' 51.8719 | ||||||||
Name |
TRANS-PHOS INC 5000 OLD HWY 37 S |
Longitude | 81° 58' 18.5482 | ||||||||
MULBERRY, FL 33860 | LL Method | DPHO | |||||||||
Contact | WILLIAM WHITNEY | LL Status | REVIEWED | ||||||||
Phone | (863) 534-1575 | Status Date | 07/27/2021 | ||||||||
Account Owner Information | |||||||||||
Name | TRANS PHOS INC PO BOX 9004 Bartow, FL 33831-9004 |
Effective Date | 01/26/2021 | ||||||||
Contact | WILLIAM WHITNEY | ||||||||||
Phone | (863) 581-0764 | ||||||||||
NWHITNEY@TRANSPHOS.COM | |||||||||||
Placard # / Date | 680506 - 06/05/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | TRANS PHOS INC PO BOX 9004 Bartow, FL 33831-9004 |
Effective Date | 01/26/2021 | ||||||||
Contact | WILLIAM WHITNEY | ||||||||||
Phone | (863) 581-0764 | ||||||||||
NWHITNEY@TRANSPHOS.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
18 | 16000 | Vehicular Diesel (D) | 04/01/2022 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (B) Steel/galvanized metal | (Q) Visual inspection of ASTs | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
TP3 | 10000 | Vehicular Diesel (D) | 12/18/2023 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (I) Double wall (K) AST containment (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill (P) Level gauges/alarms (Q) DEP approved protection |
(A) Abv, no soil contact (B) Steel/galvanized metal (D) External protective coating (F) Double wall |
(4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (Q) Visual inspection of ASTs (U) Annual piping pressure test |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
12 | 12000 | Leaded Gas (A) | 07/01/1975 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (Y) Unknown | (D) SPCC Plan | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
15 | 1000 | New/Lube Oil (O) | 07/01/1986 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(Q) Visual inspection of ASTs | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
16 | 1880 | Waste Oil (L) | 07/01/1986 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(Q) Visual inspection of ASTs | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
17 | 5000 | Vehicular Diesel (D) | 02/01/1995 | ABOVEGROUND | Moved to New Site (M) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (J) Pressurized piping system (K) Dispenser liners |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 14690 | Vehicular Diesel (D) | 07/01/1964 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(I) Not required | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 25570 | Misc Petrol-Based Product (X) | 07/01/1976 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(I) Not required | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 29230 | Misc Petrol-Based Product (X) | 07/01/1976 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(I) Not required | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
8 | 4000 | Leaded Gas (A) | 07/01/1975 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (Y) Unknown | (D) SPCC Plan | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
TPI01 | 16000 | Vehicular Diesel (D) | 01/01/2021 | ABOVEGROUND | Closed In Place (A) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (L) Compartmented (P) Level gauges/alarms |
(A) Abv, no soil contact (B) Steel/galvanized metal (D) External protective coating |
(2) Visual inspect pipe sumps (6) External piping monitoring (F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 20000 | Vehicular Diesel (D) | ABOVEGROUND | Removed from Site (B) | |||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment (Q) DEP approved protection |
(B) Steel/galvanized metal | (Y) Unknown | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
13 | 271460 | Fuel Oil - Distribution (N) | ABOVEGROUND | Removed from Site (B) | |||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(I) Not required | |||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
14 | 31000 | Fuel Oil - Distribution (N) | ABOVEGROUND | Removed from Site (B) | |||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (K) AST containment |
(A) Abv, no soil contact (B) Steel/galvanized metal (G) Pipe trench liner |
(I) Not required | |||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 11/09/2016 | 11/09/2017 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 11/09/2015 | 11/09/2016 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 11/09/2014 | 11/09/2015 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 11/09/2012 | 11/09/2013 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 11/09/2011 | 11/09/2012 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 11/09/2010 | 11/09/2011 | COMMERCE & INDUSTRY | ||||||||
SELF-INSURANCE - LETTER FROM CHIEF FINANCIAL OFFICER | 01/07/2010 | 01/06/2011 | |||||||||
INSURANCE | 03/26/2008 | 03/26/2009 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 03/26/2004 | 03/26/2005 | ILLINOIS NATIONAL | ||||||||
INSURANCE | 03/26/2002 | 03/26/2004 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 05/31/2000 | 05/31/2002 | RELIANCE NATIONAL INDEMNITY | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCI | 02/15/2006 | 02/24/2006 | IN-COMPLIANCE | HUGHES_J | 1/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes NO PHOTOS. PIPING: ALL PIPING WAS ABOVEGROUND SINGLE WALL STEEL. THE TANK HAD NO PRODUCT PIPING. | |||||||||||
TXI | 09/08/2005 | 09/22/2005 | IN-COMPLIANCE | HUGHES_J | 2/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes 4 PHOTOS TAKEN. CLOSED TANKS #15 & #16. ABOUT 10 ' OF PIPING ALSO REMOVED. | |||||||||||
CWOE | 04/06/2005 | 04/26/2005 | SACLARIDES_M | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCR | 04/06/2005 | 04/26/2005 | IN-COMPLIANCE | SACLARIDES_M | 1/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes 1 PHOTO TAKEN. RESOLVES VIOLATION #2131. SECONDARY CONTAINMENT SEALED WITH DUROMAR EQ-457. | |||||||||||
NCLI | 03/11/2005 | 03/11/2005 | SACLARIDES_M | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 02/16/2005 | 03/11/2005 | MINOR OUT-OF-COMPLIANCE | SACLARIDES_M | 3/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes 2 PHOTO TAKEN. PIPING: ABOVEGROUND SINGLE WALL STEEL. RESOLVES VIOLATION #70. | |||||||||||
NCLI | 04/09/2004 | 04/09/2004 | NEWBERG_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 03/25/2004 | 04/09/2004 | MINOR OUT-OF-COMPLIANCE | NEWBERG_D | 3/0 | COMPLIANCE ASSURANCE | |||||
Completion Notes 1 PHONE TAKEN. PIPING: ABOVEGROUND SINGLE WALL STEEL. | |||||||||||
RRBD | 07/26/2002 | 10/28/2002 | PEGUES_M | 0/0 | COMPLIANCE ASSURANCE | ||||||
CWOE | 07/26/2002 | 10/28/2002 | PEGUES_M | 0/0 | COMPLIANCE ASSURANCE | ||||||
NCLI | 07/12/2002 | 07/17/2002 | PEGUES_M | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 07/09/2002 | 07/17/2002 | MINOR OUT-OF-COMPLIANCE | PEGUES_M | 3/0 | COMPLIANCE ASSURANCE | |||||
TCI | 07/17/2001 | 07/18/2001 | IN-COMPLIANCE | RANDOLPH | 3/0 | COMPLIANCE ASSURANCE | |||||
CALL | 07/03/2001 | 07/23/2001 | RANDOLPH | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes SCHEDULE INSPECTION | |||||||||||
TCR | 08/28/2000 | 09/07/2000 | IN-COMPLIANCE | RANDOLPH | 2/0 | COMPLIANCE ASSURANCE | |||||
CWOE | 08/28/2000 | 09/07/2000 | RANDOLPH | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 07/26/2000 | 08/03/2000 | SIGNIFICANT OUT-OF-COMPLIANCE | RANDOLPH_L | 2/0 | COMPLIANCE ASSURANCE | |||||
TCI | 12/30/1999 | 01/10/2000 | IN-COMPLIANCE | MEDER_R | 3/0 | COMPLIANCE ASSURANCE | |||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Site Inspection | 07/27/2021 | Major Out of Compliance | GLENN_LE_1 | 1/0 | Installation | ||||||
Letter | 07/27/2021 | Satisfied | GLENN_LE_1 | Compliance Assistance | |||||||
Electronic Communication | 07/27/2021 | Satisfied | GLENN_LE_1 | Installation | |||||||
Electronic Communication | 07/27/2021 | Satisfied | GLENN_LE_1 | Installation | |||||||
Electronic Communication | 07/27/2021 | Satisfied | GLENN_LE_1 | Compliance Assistance | |||||||
Electronic Communication | 07/27/2021 | Satisfied | GLENN_LE_1 | Installation | |||||||
Letter | 08/31/2017 | Satisfied | JARRETT_SE_1 | Compliance Assistance | |||||||
Electronic Communication | 08/31/2017 | Satisfied | JARRETT_SE_1 | Routine Compliance | |||||||
Site Inspection | 08/31/2017 | In Compliance | JARRETT_SE_1 | 1/0 | Routine Compliance | ||||||
Electronic Communication | 08/31/2017 | Satisfied | JARRETT_SE_1 | Routine Compliance | |||||||
Electronic Communication | 08/25/2017 | Satisfied | JARRETT_SE_1 | Routine Compliance | |||||||
Electronic Communication | 04/02/2017 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Meeting | 03/19/2017 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Letter | 03/12/2017 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Electronic Communication | 03/12/2017 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Electronic Communication | 06/13/2015 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Letter | 06/13/2015 | Satisfied | JARRETT_SE_1 | Non-Compliance | |||||||
Site Inspection | 06/13/2015 | Minor Out of Compliance | JARRETT_SE_1 | 1/0 | Routine Compliance | ||||||
Site Inspection | 03/21/2013 | In Compliance | WINN_JP_1 | 1/0 | Routine Compliance | ||||||
Phone Conversation | 10/10/2012 | Satisfied | NEWBERG_DR_1 | Non-Compliance | |||||||
Site Inspection | 06/20/2012 | Minor Out of Compliance | CASSELS_CR_1 | 1/0 | Non-Compliance | ||||||
Letter | 06/20/2012 | Satisfied | CASSELS_CR_1 | Non-Compliance | |||||||
Letter | 04/19/2012 | Satisfied | CASSELS_CR_1 | Non-Compliance | |||||||
Phone Conversation | 04/06/2012 | Satisfied | CASSELS_CR_1 | Non-Compliance | |||||||
Electronic Communication | 03/06/2012 | Satisfied | CASSELS_CR_1 | Routine Compliance | |||||||
Site Inspection | 03/05/2012 | Minor Out of Compliance | CASSELS_CR_1 | 1/0 | Routine Compliance | ||||||
Letter | 03/05/2012 | Satisfied | CASSELS_CR_1 | Non-Compliance | |||||||
Phone Conversation | 11/17/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 11/17/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Enforcement Tracking | 11/17/2011 | Closed With Enforcement | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 11/17/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 11/04/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 11/01/2011 | Satisfied | DERY_WC_1 | Non-Compliance | |||||||
Phone Conversation | 11/01/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 11/01/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 10/05/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 10/05/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/30/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/30/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/30/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 09/30/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/19/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/08/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 09/08/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 09/08/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/08/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Electronic Communication | 09/08/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Phone Conversation | 09/06/2011 | Satisfied | JARRETT_SE | Enforcement | |||||||
Enforcement Referral | 09/01/2011 | Accepted | JARRETT_SE | Enforcement | |||||||
Letter | 09/01/2011 | Satisfied | WINN_JP_1 | Non-Compliance | |||||||
Meeting | 08/31/2011 | Satisfied | DERY_WC_1 | Non-Compliance | |||||||
Phone Conversation | 08/31/2011 | Satisfied | DERY_WC_1 | Non-Compliance | |||||||
Phone Conversation | 08/09/2011 | Satisfied | DERY_WC_1 | Non-Compliance | |||||||
Letter | 06/29/2011 | Satisfied | WINN_JP_1 | Non-Compliance | |||||||
Site Inspection | 06/29/2011 | Major Out of Compliance | WINN_JP_1 | 1/0 | Routine Compliance | ||||||
Phone Conversation | 08/13/2010 | Satisfied | BELL_JM_1 | Routine Compliance | |||||||
Meeting | 08/13/2010 | Satisfied | BELL_JM_1 | Routine Compliance | |||||||
Site Inspection | 02/25/2010 | In Compliance | WINN_JP_1 | 1/0 | Routine Compliance | ||||||
Phone Conversation | 02/25/2010 | Satisfied | WINN_JP_1 | Routine Compliance | |||||||
Phone Conversation | 03/26/2009 | Satisfied | NEWBERG_DR_1 | Routine Compliance | |||||||
Site Inspection | 03/26/2009 | In Compliance | NEWBERG_DR_1 | 1/0 | Routine Compliance | ||||||
Phone Conversation | 05/01/2008 | Satisfied | NEWBERG_DR_1 | Routine Compliance | |||||||
Site Inspection | 04/30/2008 | In Compliance | NEWBERG_DR_1 | 1/0 | Routine Compliance | ||||||
Site Inspection | 01/25/2007 | In Compliance | NEWBERG_DR_1 | 1/0 | Routine Compliance | ||||||
Phone Conversation | 01/17/2007 | Satisfied | NEWBERG_DR_1 | Routine Compliance | |||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
07/27/2021 | 5034 | SNC-B | 3.15 Storage tank system not installed according to reference guidelines for shop fabricated tank systems. | The dispensing system must be moved to provide the 50 feet clearance and the Department notified. - Please note, if the local Fire Marshal allows the fuel dispensing device to be closer than 50 feet, then the Department will accept their judgement; however, a copy of their determination must be provided to the Department. | |||||||
07/27/2021 | 5168 | Minor | 1.2 Storage tank system equipment not registered with the Department. | The manufacturer or vendor of the tank must request for and be granted an equipment approval for the tank with the approval documentation provided to the Department. The necessary paperwork can be found here - https://floridadep.gov/waste/permitting-compliance-assistance/content/storage-tank-system-equipment-registration. - If an equipment approval cannot be obtained from FDEP, then the tank is NOT authorized to be used as an Aboveground Storage Tank (AST) in the State of Florida and must be properly closed with the required notification given to the Department. | |||||||
07/27/2021 | 5012 | Minor | 1.7 Incomplete documentation demonstrating financial responsibility. | The Financial Mechanisms for Storage Tanks either the FDEP Storage Tank Insurance Endorsement – Part C Form or the FDEP Storage Tank Certificate of Insurance – Part D Form (but not both – usually found as last few pages in full policy packet) must be provided to the Department. | |||||||
07/27/2021 | 5044 | Minor | 3.24 Fillbox covers not marked according to requirements for shop fabricated tank systems. | Product label must be applied and the Department notified. | |||||||
07/27/2021 | 5012 | Minor | 1.7 Incomplete documentation demonstrating financial responsibility. | CFR-Part P form must be completed by facility personnel and a copy provided to the Department. | |||||||
07/27/2021 | 5004 | Minor | 1.4 Registration fees not paid, placard not posted. | A copy of the Current Storage Tank Registration Placard must be obtained and posted at the facility with a copy provided to the Department. | |||||||
07/27/2021 | 5011 | SNC-B | 1.6 Failure to maintain and demonstrate financial responsibility. | Financial responsibility must be obtained for the fuel storage system with a signed copy of the full insurance policy, including all endorsements and amendments provided to the Department. | |||||||
07/27/2021 | 5034 | SNC-B | 3.15 Storage tank system not installed according to reference guidelines for shop fabricated tank systems. | Normal and emergency venting must be installed and the Department notified. | |||||||
07/27/2021 | 5127 | Minor | 3.17 Exterior Coatings not maintained to prevent corrosion for shop fabricated storage tank systems. | Piping must be coated to prevent corrosion and the Department notified. | |||||||
07/27/2021 | 5042 | SNC-B | 3.22 Failure to provide approved overfill protection for shop fabricated tank systems. | An approved/registered overfill protection device must be installed and the Department notified. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
12/05/1995 | COMPLETED | ||||||||||
11/06/1995 | COMPLETED | ||||||||||
12/10/1993 | COMPLETED | 5 | PETROLEUM CLEANUP PARTICIPATION PROGRAM-ELIGIBLE | ||||||||