Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | South | Type | Retail Station | ||||||||
County | Collier | Status | OPEN | ||||||||
ID | 8837297 | Latitude | 26° 7' 28.8 | ||||||||
Name |
SUNSHINE #505 3396 TAMIAMI TRL E |
Longitude | 81° 45' 52.5 | ||||||||
NAPLES, FL 34112-4930 | LL Method | AGPS | |||||||||
Contact | STATION MANAGER | LL Status | REVIEWED | ||||||||
Phone | (239) 732-9203 | Status Date | 04/23/2003 | ||||||||
Account Owner Information | |||||||||||
Name | SUNSHINE GASOLINE DISTRIBUTORS INC 1650 NW 87TH AVE Doral, FL 33172-2614 |
Effective Date | 02/22/2016 | ||||||||
Contact | MARIO ZAMORA / VANESSA PALACIOS/BARBIE RUIZ | ||||||||||
Phone | (786) 606-0917 | ||||||||||
MZAMORA@SUNSHINEGASOLINE.COM | |||||||||||
Placard # / Date | 694586 - 06/25/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | SUNSHINE GASOLINE DISTRIBUTORS INC 1650 NW 87TH AVE Doral, FL 33172-2614 |
Effective Date | 06/21/2017 | ||||||||
Contact | MARIO ZAMORA / VANESSA PALACIOS/BARBIE RUIZ | ||||||||||
Phone | (786) 606-0917 | ||||||||||
MZAMORA@SUNSHINEGASOLINE.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 10000 | Unleaded Gas (B) | 06/01/1996 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(E) Fiberglass (I) Double wall (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 10000 | Unleaded Gas (B) | 06/01/1996 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(E) Fiberglass (I) Double wall (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (F) Double wall (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 10000 | Unleaded Gas (B) | 01/01/1988 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(G) Sacrificial anode CP (M) Spill containment bucket (O) Tight fill |
(E) Cathodic protection (J) Pressurized piping system |
(8) Manually sampled wells (H) Mechanical line leak detector (L) Automatic tank gauging - USTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 10000 | Unleaded Gas (B) | 12/01/1987 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (G) Sacrificial anode CP |
(C) Fiberglass (E) Cathodic protection |
(7) Automatically sampled wells (8) Manually sampled wells |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 10000 | Unleaded Gas (B) | 12/01/1987 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (G) Sacrificial anode CP |
(C) Fiberglass (E) Cathodic protection |
(7) Automatically sampled wells (8) Manually sampled wells |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 10000 | Unleaded Gas (B) | 12/01/1987 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (G) Sacrificial anode CP |
(C) Fiberglass (E) Cathodic protection |
(7) Automatically sampled wells (8) Manually sampled wells |
|||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 09/25/2021 | 09/25/2024 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 09/25/2020 | 09/25/2021 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 09/25/2019 | 09/25/2020 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 09/25/2018 | 09/25/2019 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 09/25/2017 | 09/25/2018 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 09/25/2016 | 09/25/2017 | NAUTILUS INSURANCE COMPANY | ||||||||
INSURANCE | 06/27/2015 | 06/27/2016 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 06/27/2014 | 06/27/2015 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 06/27/2013 | 06/27/2014 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 06/27/2011 | 06/27/2012 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 06/27/2010 | 06/27/2011 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 06/27/2009 | 06/27/2010 | COMMERCE & INDUSTRY | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
RRBD | 02/06/2006 | 02/09/2006 | OWEN_JA | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RD LOG & RECEIPT FOR PUMP OUT REC'D VIA FAX | |||||||||||
TCI | 12/09/2005 | 01/12/2006 | SIGNIFICANT OUT-OF-COMPLIANCE | OWEN_JA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes RELEASE DETECTION NOT BEING PERFORMED. INCLUDED LOG FOR FACILITY. NO PLACARD DISPLAYED, SUMPS & LINERS INACCESSABLE(STORMWATER) VIOLATION #'S 1115, 1062, 2003 | |||||||||||
LTR | 02/01/2005 | 02/03/2005 | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | ||||||
Completion Notes COVER FOR TCR | |||||||||||
CWOE | 01/18/2005 | 01/24/2005 | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CLOSED #157; #1115; #1117 | |||||||||||
TCR | 01/18/2005 | 01/24/2005 | IN-COMPLIANCE | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes LIQUIDS REMOVED FROM DISPENSER LINERS & ANNUAL TESTS REC'D | |||||||||||
TCI | 01/11/2005 | 01/11/2005 | MINOR OUT-OF-COMPLIANCE | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes NEEDS ANNUAL TESTING & STORMWATER REMOVED FROM DISPENSER LINERS | |||||||||||
NCLI | 04/23/2004 | 04/23/2004 | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CITED #157 | |||||||||||
TCR | 04/09/2004 | 04/12/2004 | IN-COMPLIANCE | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes REPLACED ROTTEN BULKHEADS AT DISPENSER LINERS...CLOSE #144 | |||||||||||
TCI | 03/30/2004 | 03/30/2004 | MINOR OUT-OF-COMPLIANCE | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes PIPING: DW FIBERGLASS | |||||||||||
NCLI | 10/06/2003 | 10/10/2003 | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | ||||||
Completion Notes DISPENSER LINERS FAILED HYDROSTATIC ..#144 | |||||||||||
RRBD | 10/01/2003 | 10/10/2003 | MINOR OUT-OF-COMPLIANCE | KOLANDA | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes DISPENSER LINERS FAILED HYDROSTATIC TEST .. CITE VIOLATION #144 | |||||||||||
CWOE | 04/15/2003 | 04/21/2003 | HOGAN_S | /0 | COMPLIANCE ASSURANCE | ||||||
RRBD | 04/15/2003 | 04/21/2003 | HOGAN_S | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes LLD TESTS PASSED. | |||||||||||
RRBD | 02/11/2003 | 02/25/2003 | HOGAN_S | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes TANK CERTIFICATION FOR REPAIRS TO XERXES TANK. | |||||||||||
TCI | 02/04/2003 | 02/04/2003 | MINOR OUT-OF-COMPLIANCE | HOGAN_S | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes REMOVE LIQUIDS FROM ALL DISPENSER LINERS. THE FOLLOWING MUST BE SUBMITTED AS STATED ON TCPI DATED 1/16/03: LLD TESTS, PSSSC FORM, XERXES TANK REPAIR CERTIFICATION. | |||||||||||
TCPI | 01/16/2003 | 01/23/2003 | MINOR OUT-OF-COMPLIANCE | HOGAN_S | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes ENVIRONMENTAL CONSULTANT DRILLED THROUGH TOP OF PREMIUM TANK. NO FUEL WAS DISCHARGED TO ENVIRONMENT. FACILITY DID NOT NOTIFY POLLUTION CONTROL. POLLUTION CONTROL DISCOVERED INCIDENT WHILE REPAIRS WERE BEING MADE. | |||||||||||
RRBD | 04/22/2002 | 06/18/2002 | HOGAN_S | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes TANKNOLOGY RESULTS. PIPING AND TANKS PASSED. | |||||||||||
TCI | 04/09/2002 | 04/09/2002 | MINOR OUT-OF-COMPLIANCE | HOGAN_S | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes REMOVE WATER FROM DISPENSER LINERS. | |||||||||||
CWOE | 05/21/2001 | 05/31/2001 | HOGAN_S | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CLOSED 76/A AND 157/N | |||||||||||
TCR | 05/21/2001 | 05/31/2001 | IN-COMPLIANCE | HOGAN_S | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes INSTALLED OVERFILL PROTECTION EQ-464. LLD'S TESTED | |||||||||||
LTR | 04/25/2001 | 04/27/2001 | HOGAN_S | 0/2 | DISCHARGE PROJECT | ||||||
Completion Notes SITE ASSESSMENT DUE BY 1/25/02 | |||||||||||
TDI | 04/23/2001 | 04/23/2001 | HOGAN_S | 0/2 | DISCHARGE PROJECT | ||||||
Completion Notes SHEEN WAS FOUND IN NE TANK MW | |||||||||||
TCI | 04/23/2001 | 04/23/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | HOGAN_S | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes NEEDS OVERFILL AND ANNUAL RD DEVICE TESTS | |||||||||||
NCLI | 01/28/2000 | 01/28/2000 | LAWSON_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 01/25/2000 | 01/25/2000 | MINOR OUT-OF-COMPLIANCE | LAWSON_D | 0/2 | COMPLIANCE ASSURANCE | |||||
CWOE | 08/17/1999 | 08/17/1999 | LAWSON_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
RRBD | 08/17/1999 | 08/17/1999 | LAWSON_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
NCLI | 08/06/1999 | 08/17/1999 | LAWSON_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCR | 07/27/1999 | 08/02/1999 | MINOR OUT-OF-COMPLIANCE | SILLERY_W | 0/2 | COMPLIANCE ASSURANCE | |||||
NCLI | 04/13/1999 | 08/17/1999 | LAWSON_D | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 03/22/1999 | 03/26/1999 | SIGNIFICANT OUT-OF-COMPLIANCE | SILLERY_W | 0/2 | COMPLIANCE ASSURANCE | |||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Enforcement Referral | 11/12/2024 | Accepted | STANDIFORD_JA | Enforcement | |||||||
Letter | 12/06/2023 | Satisfied | STANDIFORD_JA | Compliance Assistance | |||||||
Site Inspection | 11/29/2023 | Major Out of Compliance | STANDIFORD_JA | 0/2 | Routine Compliance | ||||||
Electronic Communication | 09/14/2021 | Satisfied | HERNANDEZ_N_5 | Compliance Assistance | |||||||
Letter | 09/14/2021 | Satisfied | HERNANDEZ_N_5 | Compliance Assistance | |||||||
Electronic Communication | 09/10/2021 | Satisfied | HERNANDEZ_N_5 | Compliance Assistance | |||||||
Letter | 09/09/2021 | Satisfied | HERNANDEZ_N_5 | Compliance Assistance | |||||||
Site Inspection | 09/09/2021 | Major Out of Compliance | HERNANDEZ_N_5 | 0/2 | Routine Compliance | ||||||
Electronic Communication | 09/01/2021 | Satisfied | HERNANDEZ_N_5 | Routine Compliance | |||||||
Record Document | 11/27/2019 | Satisfied | BATES_TD_1 | Compliance Assistance | |||||||
Letter | 11/27/2019 | Satisfied | BATES_TD_1 | Compliance Assistance | |||||||
Electronic Communication | 11/21/2019 | Satisfied | BATES_TD_1 | Compliance Assistance | |||||||
Site Inspection | 09/30/2019 | Minor Out of Compliance | BATES_TD_1 | 0/2 | Routine Compliance | ||||||
Letter | 09/30/2019 | Satisfied | BATES_TD_1 | Compliance Assistance | |||||||
Electronic Communication | 09/26/2019 | Satisfied | BATES_TD_1 | Routine Compliance | |||||||
Letter | 04/05/2017 | Satisfied | BATES_TD_1 | Non-Compliance | |||||||
Electronic Communication | 04/05/2017 | Satisfied | STANDIFORD_JA_2 | Non-Compliance | |||||||
Site Inspection | 03/31/2017 | Minor Out of Compliance | BATES_TD_1 | 0/2 | Routine Compliance | ||||||
Record Document | 09/02/2016 | Satisfied | STANDIFORD_JA_2 | Non-Compliance | |||||||
Letter | 08/31/2016 | Satisfied | STANDIFORD_JA_2 | Closure | |||||||
TCAR | 08/15/2016 | Satisfied | STANDIFORD_JA_2 | Closure | |||||||
Letter | 06/15/2016 | Satisfied | GRIFFIN_N_1 | Non-Compliance | |||||||
Letter | 06/14/2016 | Satisfied | GRIFFIN_N_1 | Non-Compliance | |||||||
Record Document | 05/23/2016 | Satisfied | STANDIFORD_JA_2 | Non-Compliance | |||||||
Record Document | 05/23/2016 | Satisfied | STANDIFORD_JA_2 | Non-Compliance | |||||||
Site Inspection | 05/17/2016 | Minor Out of Compliance | STANDIFORD_JA_2 | 0/2 | Installation | ||||||
Site Inspection | 05/10/2016 | Minor Out of Compliance | STANDIFORD_JA_2 | 0/2 | Closure | ||||||
Record Document | 11/05/2015 | Satisfied | STANDIFORD_JA_2 | Non-Compliance | |||||||
Letter | 06/25/2015 | Satisfied | SNYDERBURN_PJ_2 | Non-Compliance | |||||||
Site Inspection | 06/24/2015 | Major Out of Compliance | STANDIFORD_J_1 | 0/2 | Routine Compliance | ||||||
Letter | 04/02/2014 | Satisfied | SPARKS_JD_1 | Non-Compliance | |||||||
Site Inspection | 04/02/2014 | Major Out of Compliance | SPARKS_JD_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 07/15/2013 | Satisfied | SPARKS_JD_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 08/24/2012 | Satisfied | SNYDERBURN_PJ_2 | Routine Compliance | |||||||
Site Inspection | 12/12/2011 | In Compliance | SNYDERBURN_PJ_2 | 0/2 | Non-Compliance | ||||||
Site Inspection | 12/11/2011 | Minor Out of Compliance | SNYDERBURN_PJ_2 | 0/2 | Routine Compliance | ||||||
Letter | 12/11/2011 | Satisfied | SNYDERBURN_PJ_2 | Non-Compliance | |||||||
Record Document | 08/20/2010 | Satisfied | NOVAK_KM_1 | Non-Compliance | |||||||
Site Inspection | 08/10/2010 | Minor Out of Compliance | NOVAK_KM_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/10/2010 | Satisfied | NOVAK_KM_1 | Routine Compliance | |||||||
Letter | 08/10/2010 | Satisfied | NOVAK_KM_1 | Non-Compliance | |||||||
Site Inspection | 07/29/2009 | In Compliance | NOVAK_KM_1 | 0/3 | Routine Compliance | ||||||
Emergency Preparedness Information | 07/29/2009 | Satisfied | NOVAK_KM_1 | Routine Compliance | |||||||
Record Document | 07/16/2008 | Satisfied | WILSON_KM | Non-Compliance | |||||||
Phone Conversation | 06/23/2008 | Satisfied | WILSON_KM | Non-Compliance | |||||||
Record Document | 06/06/2008 | Satisfied | WILSON_KM | Non-Compliance | |||||||
Site Inspection | 06/06/2008 | Major Out of Compliance | WILSON_KM | 0/2 | Routine Compliance | ||||||
Letter | 06/06/2008 | Satisfied | WILSON_KM | Non-Compliance | |||||||
Letter | 06/06/2008 | Satisfied | WILSON_KM | Non-Compliance | |||||||
Emergency Preparedness Information | 06/05/2008 | Satisfied | WILSON_KM | Routine Compliance | |||||||
Record Document | 02/11/2008 | Satisfied | SNYDERBURN_PJ_2 | Non-Compliance | |||||||
Record Document | 02/28/2007 | Satisfied | POTTS_CR | Non-Compliance | |||||||
Emergency Preparedness Information | 02/05/2007 | Satisfied | POTTS_CR | Routine Compliance | |||||||
Phone Conversation | 01/22/2007 | Satisfied | POTTS_CR | Non-Compliance | |||||||
Letter | 01/17/2007 | Satisfied | SNYDERBURN_PJ_2 | Non-Compliance | |||||||
Record Document | 01/16/2007 | Satisfied | POTTS_CR | Non-Compliance | |||||||
Site Inspection | 12/21/2006 | Major Out of Compliance | POTTS_CR | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 09/25/2006 | Satisfied | POTTS_CR | Routine Compliance | |||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
11/29/2023 | 7089 | Minor | 1.11 Integrity testing of secondary containment systems and interstitial spaces not performed per schedule. | Please perform and/or provide completed integrity test record via email to the Inspector within 90 days of the inspection date. | |||||||
11/28/2023 | 6073 | Minor | 4.9 Spill containment, dispenser liners, and piping sumps not accessible. Water or regulated substances not removed. | Within 90 days of the inspection date remove water and provide documentation via email to the Inspector stating water was removed and the associated sensor is no longer in alarm. | |||||||
11/28/2023 | 7075 | SNC-B | 3.1 Not repaired component or piping which has not caused a discharge or release. | Within 90 days of the inspection date: An integrity test must be performed to determine if UDC's 3/4, 5/6, and 7/8 are liquid tight. If the integrity test passes, the piping entry boots can be repaired/replaced. If the integrity test fails, an INF must be submitted and an investigation performed to determine if a discharge occurred. If it is determined a discharge occurred, the Incident will then be promoted to a discharge and then a site assessment will need to be performed along with sampling. Please perform integrity testing and provide the associated follow up documentation as required by rule via email to the Inspector within 90 days of the inspection date. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
04/23/2001 | COMPLETED | 6 | |||||||||
11/30/1988 | COMPLETED | 40 | EARLY DETECTION INCENTIVE-ELIGIBLE | ||||||||