Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | Northeast | Type | Retail Station | ||||||||
County | Duval | Status | OPEN | ||||||||
ID | 8943516 | Latitude | 30° 27' 42.9419 | ||||||||
Name |
CIRCLE K #2726536 12405 N MAIN ST |
Longitude | 81° 38' 1.9013 | ||||||||
JACKSONVILLE, FL 32218-2609 | LL Method | DPHO | |||||||||
Contact | GRAHAM BIGGS | LL Status | REVIEWED | ||||||||
Phone | (919) 774-6700 | Status Date | 12/09/2003 | ||||||||
Account Owner Information | |||||||||||
Name | CIRCLE K STORES INC 1100 Situs Ct Raleigh, NC 27606-5446 |
Effective Date | 01/07/2016 | ||||||||
Contact | IRA LEWIS | ||||||||||
Phone | (423) 400-2480 | ||||||||||
ILEWIS@CIRCLEK.COM | |||||||||||
Placard # / Date | 697893 - 06/28/2024 | ||||||||||
Property Owner Information | |||||||||||
Name | BUCKHEAD DEVELOPMENT COMPANY 4521 ATLANTIC BLVD JACKSONVILLE, FL 32207 |
Effective Date | 08/28/2003 | ||||||||
Contact | JOHN RUMBLE | ||||||||||
Phone | (904) 398-8970 | ||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 20000 | Unleaded Gas (B) | 06/01/2005 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (I) Double wall (M) Spill containment bucket (O) Tight fill |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 20000 | Unleaded Gas (B) | 06/01/2005 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (I) Double wall (L) Compartmented (M) Spill containment bucket (O) Tight fill |
(J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket (N) Approved synthetic material |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 10000 | Unleaded Gas (B) | 02/01/1989 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 10000 | Unleaded Gas (B) | 02/01/1989 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 6000 | Unleaded Gas (B) | 02/01/1989 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 6000 | Vehicular Diesel (D) | 02/01/1989 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 6000 | Vehicular Diesel (D) | 02/01/1989 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (F) Fiberglass clad steel (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (L) Automatic tank gauging - USTs (S) Statistical Inventory Reconcile |
|||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
GUARANTEE | 04/28/2024 | 08/26/2025 | |||||||||
GUARANTEE | 04/30/2023 | 08/28/2024 | |||||||||
GUARANTEE | 04/24/2022 | 08/21/2023 | |||||||||
SELF-INSURANCE - LETTER FROM CHIEF FINANCIAL OFFICER | 04/24/2021 | 08/27/2022 | |||||||||
INSURANCE | 12/01/2020 | 12/01/2021 | NAVIGATORS SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2019 | 12/01/2020 | NAVIGATORS SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2018 | 12/01/2019 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2017 | 12/01/2018 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2016 | 12/01/2017 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2015 | 12/01/2016 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 11/01/2014 | 11/01/2015 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 12/01/2013 | 12/01/2016 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 11/01/2013 | 11/01/2014 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 11/01/2012 | 11/01/2013 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 11/01/2011 | 11/01/2012 | IRONSHORE SPECIALTY INSURANCE CO | ||||||||
INSURANCE | 11/01/2010 | 11/01/2011 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
INSURANCE | 11/01/2009 | 11/01/2010 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
INSURANCE | 11/01/2008 | 11/01/2009 | ENDURANCE AMERICAN SPECIALTY INS CO | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
TCI | 08/17/2005 | 08/19/2005 | IN-COMPLIANCE | HOLLOWAY | 0/2 | COMPLIANCE ASSURANCE | |||||
LTR | 07/13/2005 | 07/13/2005 | GRIFFIN | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes TCAR REQUIREMENTS SATISFIED. | |||||||||||
MDR | 07/11/2005 | 07/13/2005 | GRIFFIN | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes CLOSURE ASSESSMENT REPORT RECEIVED. | |||||||||||
LTR | 06/22/2005 | 06/22/2005 | ALLEN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CLOSURE - COMPLETE FUEL SYSTEM REMOVAL. | |||||||||||
TIN | 06/17/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes LINE & LLD TESTS BY KC PETRO. SYSTEM OPERATIONAL. | |||||||||||
TIV | 06/15/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes CONNECTING PIPE_SETTING DISPENSERS. | |||||||||||
TIV | 06/10/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes HYDRO SUMPS/DISPENSER LINERS/SPILL BUCKETS. PIPE STILL HOLDING PRESSURE. | |||||||||||
TIV | 06/09/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes AIR TEST PRIMARY PIPE AT 50 PSI & SECONDARY AT 5 PSI. 5 PSI TEST ON TANK AND VENT LINES. | |||||||||||
TXI | 06/09/2005 | 06/17/2005 | IN-COMPLIANCE | CARROLL | 0/5 | COMPLIANCE ASSURANCE | |||||
Completion Notes DISPENSERS AND LINERS REMOVED. | |||||||||||
TIV | 06/08/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes INTALLING WESTERN FIBERGLASS DW FLEX PIPE. | |||||||||||
SV | 06/07/2005 | 06/17/2005 | CARROLL | 0/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes TANKS REMOVED AFTER CLEANING OUT. PIPE REMOVAL STARTED | |||||||||||
TIV | 06/07/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes INSTALLING DISPENSER LINERS/BLUE LINE BOOTS/STP SUMPS/PIPE RISERS. BACKFILLING AROUND TANKS. | |||||||||||
LTR | 06/06/2005 | 06/07/2005 | ALLEN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CONTAMINATION WAS DISCOVERED AT THE ABOVE SITE ON 6/2/05. NOTIFICATION DETAILING ACTION TAKEN, DUE BY 7/2/05. | |||||||||||
TIV | 06/03/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes BOTH TANKS SET AND ANCHORED. NORTH TANK WOULD NOT HOLD VACUUM. REPAIR MADE TO VACUUM GUAGE. HOLDS 22" OK. | |||||||||||
CNLI | 06/03/2005 | 06/03/2005 | GRIFFIN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes SAR LETTER | |||||||||||
TR | 06/03/2005 | 06/03/2005 | GRIFFIN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes ANALYTICAL RESULTS REVIEW CONFIRMS DISCHARGE. | |||||||||||
DRFR | 06/03/2005 | 06/03/2005 | GRIFFIN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes ANALYTICAL RESULTS CONFIRM A PREVIOUSLY UNREPORTED DISCHARGE HAS OCCURRED. REC FROM TERRA COM | |||||||||||
TIV | 06/02/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes FIRST TANK SET | |||||||||||
DCCR | 06/02/2005 | 06/03/2005 | GRIFFIN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes CONFIRMED THRU ANALYTICAL RESULTS. | |||||||||||
TIV | 06/01/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes EXCAVATING FOR TANK PIT | |||||||||||
TII | 05/31/2005 | 06/29/2005 | IN-COMPLIANCE | CARROLL | 0/2 | COMPLIANCE ASSURANCE | |||||
Completion Notes SHEET PILE INSTALLATION | |||||||||||
IRFR | 05/24/2005 | 06/03/2005 | GRIFFIN | 0/0 | DISCHARGE PROJECT | ||||||
Completion Notes ELEVATED OVA DURING CLOSURE ACTIVITIES/TANKS TO BE REPLACED. | |||||||||||
SV | 05/24/2005 | 06/17/2005 | CARROLL | 0/5 | COMPLIANCE ASSURANCE | ||||||
Completion Notes REMOVING DIRT & CONCRETE AROUND TANKS | |||||||||||
CALL | 05/19/2005 | 05/20/2005 | CARROLL | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes 48/HRS - TANK INSTALLATION & TANK REMOVAL. COMMENCE ON OR ABOUT 5/24/05. | |||||||||||
CALL | 05/16/2005 | 05/17/2005 | CARROLL | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes 10/DAY - TANK INSTALLATION & TANK REMOVAL. COMMENCE ON OR ABOUT 5/24/05. | |||||||||||
TCI | 07/08/2004 | 07/14/2004 | IN-COMPLIANCE | HOLLOWAY_R | 0/5 | COMPLIANCE ASSURANCE | |||||
TCI | 07/24/2003 | 07/25/2003 | IN-COMPLIANCE | BORISADE_C | 0/5 | COMPLIANCE ASSURANCE | |||||
TCI | 09/25/2002 | 09/28/2002 | IN-COMPLIANCE | HOLLOWAY_R | 0/5 | COMPLIANCE ASSURANCE | |||||
TCI | 04/12/2002 | 04/16/2002 | IN-COMPLIANCE | MACK_W | 0/5 | COMPLIANCE ASSURANCE | |||||
TCI | 09/13/2000 | 09/18/2000 | IN-COMPLIANCE | TORSANKO_G | 0/5 | COMPLIANCE ASSURANCE | |||||
TCI | 09/27/1999 | 10/12/1999 | IN-COMPLIANCE | TORSANKO_G | 0/5 | COMPLIANCE ASSURANCE | |||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Document Management | 02/14/2025 | Satisfied | AMES_J | Incident | |||||||
Enforcement Referral | 12/02/2024 | Accepted | AMES_J | Enforcement | |||||||
Electronic Communication | 11/19/2024 | Satisfied | AMES_J | Compliance Assistance | |||||||
Electronic Communication | 11/19/2024 | Satisfied | AMES_J | Compliance Assistance | |||||||
Electronic Communication | 10/23/2024 | Satisfied | WESTERMAN_ML_1 | Compliance Assistance | |||||||
Electronic Communication | 10/01/2024 | Satisfied | WESTERMAN_ML_1 | Compliance Assistance | |||||||
Electronic Communication | 08/26/2024 | Satisfied | WESTERMAN_ML_1 | Incident | |||||||
Document Management | 08/26/2024 | Satisfied | WESTERMAN_ML_1 | Incident | |||||||
Site Inspection | 08/23/2024 | Major Out of Compliance | WESTERMAN_ML_1 | 0/2 | Routine Compliance | ||||||
Letter | 08/23/2024 | Satisfied | WESTERMAN_ML_1 | Compliance Assistance | |||||||
Letter | 12/13/2022 | Satisfied | RICHARDS_JE_1 | Component Closure | |||||||
Incident | 12/13/2022 | Has not led to Discharge | LAUGHLIN_MT_1 | Incident | |||||||
TCAR | 12/13/2022 | Satisfied | RICHARDS_JE_1 | Component Closure | |||||||
Letter | 10/14/2022 | Satisfied | LAUGHLIN_MT_1 | Compliance Assistance | |||||||
Incident | 09/19/2022 | Has not led to Discharge | LAUGHLIN_MT_1 | Incident | |||||||
Document Management | 08/29/2022 | Satisfied | LAUGHLIN_MT_1 | Incident | |||||||
Document Management | 08/29/2022 | Satisfied | LAUGHLIN_MT_1 | Incident | |||||||
Letter | 08/24/2022 | Satisfied | LAUGHLIN_MT_1 | Compliance Assistance | |||||||
Site Inspection | 08/22/2022 | Major Out of Compliance | LAUGHLIN_MT_1 | 0/2 | Routine Compliance | ||||||
Electronic Communication | 08/16/2022 | Satisfied | LAUGHLIN_MT_1 | Compliance Assistance | |||||||
Letter | 10/13/2021 | Satisfied | MCKINLEY_DN_1 | Compliance Assistance | |||||||
Incident | 04/02/2021 | Has not led to Discharge | RICHARDS_JE_1 | Incident | |||||||
Enforcement Tracking | 03/31/2021 | Closed Without Enforcement | CHRISTIAN_E | Enforcement | |||||||
Letter | 03/31/2021 | Satisfied | CHRISTIAN_E | Enforcement | |||||||
Enforcement Referral | 03/12/2021 | Accepted | GAINEY_H_1 | Enforcement | |||||||
Electronic Communication | 03/05/2021 | Satisfied | MACK_B_1 | Compliance Assistance | |||||||
Electronic Communication | 03/05/2021 | Satisfied | MACK_B_1 | Routine Compliance | |||||||
Electronic Communication | 03/05/2021 | Satisfied | MACK_B_1 | Routine Compliance | |||||||
Site Inspection | 12/29/2020 | Minor Out of Compliance | MACK_B_1 | 0/2 | Routine Compliance | ||||||
Letter | 12/29/2020 | Satisfied | MACK_B_1 | Compliance Assistance | |||||||
Letter | 03/26/2019 | Satisfied | BRADSHAW_B | Enforcement | |||||||
Enforcement Tracking | 03/26/2019 | Closed Without Enforcement | BRADSHAW_B | Enforcement | |||||||
Incident | 02/15/2019 | Has not led to Discharge | MONDO_PW_1 | Incident | |||||||
Enforcement Referral | 02/14/2019 | Accepted | GREGORY_HM_1 | Enforcement | |||||||
Electronic Communication | 02/08/2019 | Satisfied | MONDO_PW_1 | Compliance Assistance | |||||||
Document Management | 10/31/2018 | Satisfied | MONDO_PW_1 | Incident | |||||||
Letter | 10/25/2018 | Satisfied | RICHARDS_JE_1 | Closure | |||||||
TCAR | 10/25/2018 | Satisfied | RICHARDS_JE_1 | Closure | |||||||
Site Inspection | 10/19/2018 | Major Out of Compliance | MONDO_PW_1 | 0/2 | Routine Compliance | ||||||
Electronic Communication | 10/19/2018 | Satisfied | MONDO_PW_1 | Routine Compliance | |||||||
Letter | 10/19/2018 | Satisfied | MONDO_PW_1 | Compliance Assistance | |||||||
Electronic Communication | 01/31/2017 | Satisfied | MONDO_PW_1 | Non-Compliance | |||||||
Site Inspection | 01/31/2017 | In Compliance | MONDO_PW_1 | 0/2 | Non-Compliance | ||||||
Letter | 12/30/2016 | Satisfied | RICHARDS_JE_1 | Non-Compliance | |||||||
Letter | 09/22/2016 | Satisfied | RICHARDS_JE_1 | Non-Compliance | |||||||
Electronic Communication | 09/14/2016 | Satisfied | WESTERMAN_ML_1 | Routine Compliance | |||||||
Site Inspection | 09/14/2016 | Minor Out of Compliance | WESTERMAN_ML_1 | 0/2 | Routine Compliance | ||||||
Electronic Communication | 08/29/2016 | Satisfied | WESTERMAN_ML_1 | Routine Compliance | |||||||
Electronic Communication | 08/29/2016 | Satisfied | WESTERMAN_ML_1 | Routine Compliance | |||||||
Electronic Communication | 09/10/2014 | Satisfied | WILLIAMS_AK_1 | Routine Compliance | |||||||
Site Inspection | 08/01/2014 | In Compliance | WILLIAMS_AK_1 | 0/2 | Routine Compliance | ||||||
Electronic Communication | 07/18/2014 | Satisfied | LUNN_RJ_1 | Installation | |||||||
Site Inspection | 07/18/2014 | In Compliance | LUNN_RJ_1 | 0/2 | Installation | ||||||
Electronic Communication | 07/18/2014 | Satisfied | LUNN_RJ_1 | Closure | |||||||
Site Inspection | 07/11/2014 | In Compliance | LUNN_RJ_1 | 0/2 | Closure | ||||||
Electronic Communication | 04/11/2013 | Satisfied | WILLIAMS_AK_1 | Non-Compliance | |||||||
Electronic Communication | 03/26/2013 | Satisfied | WILLIAMS_AK_1 | Routine Compliance | |||||||
Letter | 03/26/2013 | Satisfied | WILLIAMS_AK_1 | Non-Compliance | |||||||
Site Inspection | 03/25/2013 | Minor Out of Compliance | WILLIAMS_AK_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 03/15/2013 | Satisfied | WILLIAMS_AK_1 | Routine Compliance | |||||||
Electronic Communication | 10/07/2011 | Satisfied | RICHARDS_JE_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 09/23/2011 | Satisfied | RICHARDS_JE_1 | Routine Compliance | |||||||
Site Inspection | 09/23/2011 | In Compliance | RICHARDS_JE_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 08/06/2010 | In Compliance | HOLLOWAY_RW_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 07/30/2009 | In Compliance | HOLLOWAY_RW_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 07/16/2008 | Satisfied | HOLLOWAY_RW_1 | Routine Compliance | |||||||
Site Inspection | 07/16/2008 | In Compliance | HOLLOWAY_RW_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 07/23/2007 | Satisfied | HOLLOWAY_RW_1 | Routine Compliance | |||||||
Site Inspection | 07/17/2007 | In Compliance | HOLLOWAY_RW_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 02/09/2007 | Satisfied | HOLLOWAY_RW_1 | Routine Compliance | |||||||
Emergency Preparedness Information | 09/23/2006 | Satisfied | CARROLL_A | Routine Compliance | |||||||
Site Inspection | 08/17/2006 | In Compliance | HOLLOWAY_RW_1 | 0/2 | Routine Compliance | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
08/23/2024 | 6063 | SNC-B | 4.1 Not repaired or isolated component or piping which has not caused a discharge or release. | Facility must remove liquid from the interstitial space of the Regular product piping and must dispose of the liquid properly. Responsible Party must determine the source of the liquid and determine if a discharge to the environment occurred or not. Incident investigation and resolution documentation must be provided. Post liquid removal integrity testing may be required. Sampling may be required. | |||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
06/02/2005 | COMPLETED | 61 | |||||||||