Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | Northwest | Type | Retail Station | ||||||||
County | Jefferson | Status | OPEN | ||||||||
ID | 9046782 | Latitude | 30° 24' 40.7638 | ||||||||
Name |
WALKERS AMOCO 9495 WAUKEENAH HWY |
Longitude | 83° 57' 11.3143 | ||||||||
MONTICELLO, FL 32344-9416 | LL Method | DPHO | |||||||||
Contact | ROBERT RICHEY | LL Status | REVIEWED | ||||||||
Phone | (941) 875-3756 | Status Date | 09/21/2023 | ||||||||
Account Owner Information | |||||||||||
Name | S&R HOSPITALITY LLC 8553 SW AVIARY RD ARCADIA, FL 34269 |
Effective Date | 10/27/2023 | ||||||||
Contact | ROBERT RICHEY | ||||||||||
Phone | (941) 875-3756 | ||||||||||
SHERRYL.BOB@GMAIL.COM | |||||||||||
Placard # / Date | 705587 - 04/15/2025 | ||||||||||
Property Owner Information | |||||||||||
Name | S&R HOSPITALITY LLC 8553 SW AVIARY RD ARCADIA, FL 34269 |
Effective Date | 10/27/2023 | ||||||||
Contact | ROBERT RICHEY | ||||||||||
Phone | (941) 875-3756 | ||||||||||
SHERRYL.BOB@GMAIL.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 12000 | Unleaded Gas (B) | 08/01/2008 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (L) Compartmented (M) Spill containment bucket (O) Tight fill (R) Double wall - tank jacket |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket |
(1) Continuous electronic sensing (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 8000 | Vehicular Diesel (D) | 08/01/2008 | UNDERGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (L) Compartmented (M) Spill containment bucket (O) Tight fill (R) Double wall - tank jacket |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners (M) Double wall - pipe jacket |
(1) Continuous electronic sensing (3) Electronic monitor pipe sumps (4) Visual inspect dispenser liners (F) Monitor dbl wall tank space (H) Mechanical line leak detector (K) Monitor dbl wall pipe space |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 8000 | Unleaded Gas (B) | 05/01/1990 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (G) Sacrificial anode CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 8000 | Unleaded Gas (B) | 05/01/1990 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (G) Sacrificial anode CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 8000 | Unleaded Gas (B) | 05/01/1990 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(A) Ball check valve (C) Steel (G) Sacrificial anode CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (S) Statistical Inventory Reconcile |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
4 | 8000 | Vehicular Diesel (D) | 05/01/1990 | UNDERGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (G) Sacrificial anode CP (M) Spill containment bucket (N) Flow shut-Off (O) Tight fill |
(C) Fiberglass (J) Pressurized piping system (K) Dispenser liners |
(2) Visual inspect pipe sumps (4) Visual inspect dispenser liners (H) Mechanical line leak detector (S) Statistical Inventory Reconcile |
|||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 01/25/2024 | 01/25/2025 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 12/29/2021 | 12/29/2022 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 12/29/2018 | 12/29/2019 | COMMERCE & INDUSTRY INSURANCE CO | ||||||||
INSURANCE | 12/29/2016 | 12/29/2017 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 12/29/2015 | 12/29/2016 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 12/29/2013 | 12/29/2014 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 12/29/2011 | 12/29/2012 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 12/29/2010 | 12/29/2011 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 12/29/2009 | 12/29/2010 | COMMERCE & INDUSTRY | ||||||||
INSURANCE | 09/17/2008 | 09/17/2009 | COMMERCE & INDUSTRY | ||||||||
Legacy Compliance Activity Information | |||||||||||
Activity Code |
Date Initiated |
Date Completed |
Results | Inspector | AST/UST Count |
Description | |||||
WLI | 11/29/2005 | 11/29/2005 | PAUL HUTCHERSON | 0/4 | COMPLIANCE ASSURANCE | ||||||
TCR | 11/22/2005 | 11/29/2005 | IN-COMPLIANCE | PAUL HUTCHERSON | 0/4 | COMPLIANCE ASSURANCE | |||||
WLI | 09/27/2005 | 09/28/2005 | PAUL HUTCHERSON | 0/4 | COMPLIANCE ASSURANCE | ||||||
TCI | 09/27/2005 | 09/28/2005 | SIGNIFICANT OUT-OF-COMPLIANCE | PAUL HUTCHERSON | 0/4 | COMPLIANCE ASSURANCE | |||||
CRDE | 09/27/2005 | 09/28/2005 | PAUL HUTCHIERSON | 0/4 | COMPLIANCE ASSURANCE | ||||||
NCLI | 04/08/2005 | 04/11/2005 | DAN MACDONALD | 0/4 | COMPLIANCE ASSURANCE | ||||||
TCI | 04/02/2005 | 04/11/2005 | MINOR OUT-OF-COMPLIANCE | DAN MACDONALD | 0/4 | COMPLIANCE ASSURANCE | |||||
CWOE | 05/10/2004 | 05/10/2004 | WAYNE ERATO | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCR | 05/10/2004 | 05/18/2004 | IN-COMPLIANCE | WAYNE ERATO | 0/1 | COMPLIANCE ASSURANCE | |||||
TCR | 05/10/2004 | 05/10/2004 | IN-COMPLIANCE | WAYNE ERATO | 0/1 | COMPLIANCE ASSURANCE | |||||
Completion Notes 1 TANK FAILED, TANK EMPTIED, PLACED IN T STATUS UNTIL IT CAN BE REMOVED. ALL VIOLATIONS CLOSED. | |||||||||||
WLI | 04/13/2004 | 04/15/2004 | WAYNE ERATO | 0/0 | COMPLIANCE ASSURANCE | ||||||
TCI | 03/25/2004 | 04/05/2004 | SIGNIFICANT OUT-OF-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
NCLI | 05/27/2003 | 06/09/2003 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes NON-COMPLIANCE LETTER SENT THIS DATE | |||||||||||
TCI | 05/16/2003 | 06/09/2003 | MINOR OUT-OF-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes COMPLIANCE INSPECTION DONE THIS DATE VIOLATION NOTED | |||||||||||
CWOE | 08/24/2001 | 08/31/2001 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes TESTING CLEARS VIOLATIONS | |||||||||||
RRBD | 08/24/2001 | 08/31/2001 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RECEIVED NOTICE OF TESTING DONE | |||||||||||
NCLI | 07/25/2001 | 07/30/2001 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes LETTER REQUESTING TESTING | |||||||||||
TCI | 07/17/2001 | 07/30/2001 | SIGNIFICANT OUT-OF-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes NO RECORD OF ANNUAL TESTING | |||||||||||
TCI | 07/10/2000 | 08/01/2000 | IN-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes IN COMPLIANCE | |||||||||||
CWOE | 11/23/1999 | 11/23/1999 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes SITE NOW COVERED BY SIR PROGRAM | |||||||||||
TCR | 11/23/1999 | 11/23/1999 | IN-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes SIR PROGRAM IN PLACE | |||||||||||
NCLI | 08/23/1999 | 10/22/1999 | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes NO PROOF OF METHOD OF RELEASES DETECTION | |||||||||||
TCI | 08/23/1999 | 08/30/1999 | MINOR OUT-OF-COMPLIANCE | WAYNE ERATO | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes SITE NEEDS TO PARTICIPATE IN SIR PROGRAM TO COME INTO COMPLIANCE | |||||||||||
CWOE | 06/08/1999 | 12/02/1999 | JEFF HARDEE | 0/4 | COMPLIANCE ASSURANCE | ||||||
Completion Notes RESPONSE RECEIVED BY DEPT | |||||||||||
RRBD | 06/08/1999 | 06/15/1999 | HARDEE_J | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes PROOF FROM WELL DRILLER THAT THE MW MEET REQUIRED STANDARDS | |||||||||||
NCLI | 03/04/1999 | 03/04/1999 | HARDEE_J | 0/0 | COMPLIANCE ASSURANCE | ||||||
Completion Notes NCLI FOR MW UPGRADE VIOLATIONS | |||||||||||
TIN | 02/25/1999 | 03/04/1999 | SIGNIFICANT OUT-OF-COMPLIANCE | HARDEE_J | 0/4 | COMPLIANCE ASSURANCE | |||||
Completion Notes UPGRADE INSTALLATION FOR DL, OF, CPTEST STATION, & PIPE ISOLATION | |||||||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
Document Management | 02/28/2025 | Satisfied | MERRITT_S | Enforcement | |||||||
Electronic Communication | 02/24/2025 | Satisfied | MERRITT_S | Enforcement | |||||||
Document Management | 09/06/2024 | Satisfied | MERRITT_S | Enforcement | |||||||
Letter | 08/07/2024 | Satisfied | MERRITT_S | Enforcement | |||||||
Electronic Communication | 08/06/2024 | Satisfied | MERRITT_S | Enforcement | |||||||
Enforcement Referral | 03/20/2024 | Accepted | HATCHER_JD_1 | Enforcement | |||||||
Letter | 03/20/2024 | Satisfied | FRENCH_EC_1 | Compliance Assistance | |||||||
Site Inspection | 02/29/2024 | Major Out of Compliance | HATCHER_JD_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 05/11/2022 | In Compliance | HATCHER_JD_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 12/12/2019 | In Compliance | HATCHER_JD_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 06/26/2019 | In Compliance | FRENCH_EC_1 | 0/2 | Non-Compliance | ||||||
Issue Document | 07/31/2017 | Satisfied | FRENCH_EC_1 | Routine Compliance | |||||||
Site Inspection | 07/17/2017 | In Compliance | HATCHER_JD_1 | 0/2 | Routine Compliance | ||||||
Issue Document | 05/31/2016 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 05/31/2016 | In Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
Phone Conversation | 04/19/2016 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Phone Conversation | 01/27/2016 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Phone Conversation | 01/13/2016 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Letter | 02/05/2015 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 10/30/2014 | Minor Out of Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
Emergency Preparedness Information | 10/30/2014 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Letter | 10/30/2014 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 08/31/2012 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 08/31/2012 | In Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 05/10/2011 | Minor Out of Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
Letter | 05/10/2011 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 05/10/2011 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Meeting | 09/01/2010 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Emergency Preparedness Information | 04/30/2010 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Letter | 04/30/2010 | Satisfied | GRAHAM_DL_1 | Non-Compliance | |||||||
Site Inspection | 04/30/2010 | Minor Out of Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
Site Inspection | 12/17/2008 | In Compliance | GRAHAM_DL_1 | 0/2 | Routine Compliance | ||||||
TCAR | 10/06/2008 | Satisfied | GRAHAM_DL_1 | Closure | |||||||
Letter | 10/06/2008 | Satisfied | GRAHAM_DL_1 | Closure | |||||||
Emergency Preparedness Information | 10/06/2008 | Satisfied | GRAHAM_DL_1 | Routine Compliance | |||||||
Site Inspection | 10/06/2008 | In Compliance | HUTCHERSON_P | 0/2 | Installation | ||||||
Site Inspection | 09/17/2008 | In Compliance | HUTCHERSON_P | 0/4 | Closure | ||||||
Site Inspection | 08/30/2007 | In Compliance | HUTCHERSON_P | 0/4 | Routine Compliance | ||||||
Emergency Preparedness Information | 08/30/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 05/23/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 02/12/2007 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Emergency Preparedness Information | 09/21/2006 | Satisfied | HUTCHERSON_P | Routine Compliance | |||||||
Site Inspection | 08/22/2006 | Major Out of Compliance | HUTCHERSON_P | 0/4 | Routine Compliance | ||||||
Letter | 08/22/2006 | Satisfied | HUTCHERSON_P | Non-Compliance | |||||||
No Open AOCs Found | |||||||||||
No Open Violations Found | |||||||||||
Discharge Information | |||||||||||
Discharge Date |
Clean Up Status |
Score | Eligibility Info | Site Manager | Phone | ||||||
12/02/1991 | COMPLETED | 30 | PETROLEUM CLEANUP PARTICIPATION PROGRAM-ELIGIBLE | ||||||||