Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
Cover Page Report | |||||||||||
Report Run Date: 05/09/2025 Last Data Refresh: 05/08/2025 Report Generated from DOPPLER | |||||||||||
District | Northeast | Type | Agricultural | ||||||||
County | Alachua | Status | OPEN | ||||||||
ID | 9816595 | Latitude | 29° 50' 7.2425 | ||||||||
Name |
AYR WELLNESS/ AYR CANNABIS DISPENSARY 18770 N CR 225 |
Longitude | 82° 16' 12.9974 | ||||||||
GAINESVILLE, FL 32609 | LL Method | DPHO | |||||||||
Contact | BRENT GADBOIS | LL Status | REVIEWED | ||||||||
Phone | (508) 989-6692 | Status Date | 11/05/2018 | ||||||||
Account Owner Information | |||||||||||
Name | DFMMJ INVESTMENTS 18770 N CR 225 GAINESVILLE, FL 32609 |
Effective Date | 02/28/2023 | ||||||||
Contact | WENDY RICHTER | ||||||||||
Phone | (386) 462-0141 | ||||||||||
WENDY.RICHTER@AYRWELLNESS.COM | |||||||||||
Placard # / Date | 705438 - 03/28/2025 | ||||||||||
Property Owner Information | |||||||||||
Name | DFMMJ INVESTMENTS 18770 N CR 225 GAINESVILLE, FL 32609 |
Effective Date | 02/28/2023 | ||||||||
Contact | WENDY RICHTER | ||||||||||
Phone | (386) 462-0141 | ||||||||||
WENDY.RICHTER@AYRWELLNESS.COM | |||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
1 | 3690 | Emerg Generator Diesel (G) | 09/01/2018 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel | (F) Double wall (L) Bulk product system (X) No piping associated w/tank |
||||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
7 | 2388 | Vehicular Diesel (D) | 06/01/2023 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
WG1 | 2310 | Vehicular Diesel (D) | 03/01/2025 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
WG2 | 2310 | Vehicular Diesel (D) | 03/01/2025 | ABOVEGROUND | In Service (U) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
2 | 2388 | Vehicular Diesel (D) | 04/01/2022 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
3 | 2388 | Vehicular Diesel (D) | 04/01/2022 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
5 | 2388 | Vehicular Diesel (D) | 06/01/2023 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Tank | Tank Size | Content | Installed | Placement | Status | ||||||
6 | 2388 | Vehicular Diesel (D) | 06/01/2023 | ABOVEGROUND | Removed from Site (B) | ||||||
Constructions | Pipings | Monitorings | |||||||||
(C) Steel (I) Double wall (M) Spill containment bucket |
(A) Abv, no soil contact (D) External protective coating (M) Double wall - pipe jacket (N) Approved synthetic material |
(F) Monitor dbl wall tank space (Q) Visual inspection of ASTs |
|||||||||
Insurance Documents | |||||||||||
FR Type | Effective Date | Expiration Date | Company Name | ||||||||
INSURANCE | 02/01/2024 | 02/01/2025 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 11/01/2019 | 11/01/2020 | ACE AMERICAN INSURANCE COMPANY | ||||||||
INSURANCE | 11/01/2018 | 11/01/2019 | ACE | ||||||||
No Legacy Data Found | |||||||||||
Compliance Activity Information | |||||||||||
Activity Code |
Date Completed |
Results | Inspector | AST/UST Count |
Description | ||||||
TCAR | 03/30/2025 | Satisfied | HARRINGTON_RD_1 | Closure | |||||||
Document Management | 03/30/2025 | Satisfied | HARRINGTON_RD_1 | Closure | |||||||
Phone Conversation | 03/06/2025 | Satisfied | HARRINGTON_RD_1 | Closure | |||||||
Document Management | 07/01/2024 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Discharge Reporting | 07/01/2024 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Site Inspection | 06/16/2024 | Minor Out of Compliance | HARRINGTON_RD_1 | 6/0 | Complaint | ||||||
Incident | 05/31/2024 | Has not led to Discharge | RAMSEY_TH_1 | Incident | |||||||
Document Management | 05/31/2024 | Satisfied | RAMSEY_TH_1 | Incident | |||||||
Document Management | 03/29/2024 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Enforcement Referral | 03/27/2024 | Accepted | HARRINGTON_RD_1 | Enforcement | |||||||
Enforcement Tracking | 03/27/2024 | Closed Without Enforcement | JACKSON_SM | Enforcement | |||||||
Electronic Communication | 03/26/2024 | Satisfied | HARRINGTON_RD_1 | Routine Compliance | |||||||
Site Inspection | 03/26/2024 | Major Out of Compliance | HARRINGTON_RD_1 | 6/0 | Routine Compliance | ||||||
Electronic Communication | 03/17/2024 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Site Inspection | 03/14/2024 | Minor Out of Compliance | HARRINGTON_RD_1 | 3/0 | Discharge | ||||||
Enforcement Tracking | 02/23/2024 | Closed Without Enforcement | JACKSON_SM | Enforcement | |||||||
Enforcement Referral | 02/21/2024 | Accepted | HARRINGTON_RD_1 | Enforcement | |||||||
Enforcement Referral | 02/21/2024 | Accepted | HARRINGTON_RD_1 | Enforcement | |||||||
Meeting | 08/15/2023 | Satisfied | RAMSEY_TH_1 | Discharge | |||||||
Discharge Reporting | 08/15/2023 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Electronic Communication | 05/25/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Record Document | 05/23/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Electronic Communication | 05/23/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Electronic Communication | 05/23/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Electronic Communication | 05/23/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Letter | 03/24/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Site Inspection | 03/12/2023 | Major Out of Compliance | HARRINGTON_RD_1 | 3/0 | Installation | ||||||
Electronic Communication | 03/12/2023 | Satisfied | HARRINGTON_RD_1 | Installation | |||||||
Record Document | 02/26/2023 | Satisfied | HARRINGTON_RD_1 | Compliance Assistance | |||||||
Document Management | 02/19/2023 | Satisfied | HARRINGTON_RD_1 | Discharge | |||||||
Site Inspection | 02/19/2023 | Major Out of Compliance | HARRINGTON_RD_1 | 1/0 | Complaint | ||||||
Site Inspection | 09/15/2020 | Major Out of Compliance | ZIMMERMAN_RA_2 | 1/0 | Routine Compliance | ||||||
Electronic Communication | 09/15/2020 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Letter | 09/15/2020 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Phone Conversation | 09/02/2020 | Satisfied | ZIMMERMAN_RA_2 | Compliance Assistance | |||||||
Site Inspection | 11/04/2018 | In Compliance | HARRINGTON_RD_1 | 1/0 | Installation | ||||||
No Open AOCs Found | |||||||||||
Open Violations | |||||||||||
Insp Date | Vio # | Significance | Violation Text | Corrective Action | |||||||
06/16/2024 | 7020 | Minor | 1.2 Integrity Testing of secondary containment systems and interstitial spaces not performed before being placed into service. | Provide containment box (spill containment box) integrity test results for Tanks 5,6 and 7. | |||||||
06/16/2024 | 6062 | Minor | 2.5 Release detection devices not tested annually. | Provide current interstice sensor and overfill test results for Tank 1 (genset). | |||||||
03/26/2024 | 6039 | Minor | 4.10 Small diameter piping with gravity head not properly installed or meeting standards. | Install anti-siphon valve as required. Check that all of the Western Global tanks have the appropriate anti siphon valves installed. Provide verification. | |||||||
03/22/2024 | 6053 | Minor | 4.7 Primary overfill protection not provided, registered, or tested as required. | Provide current overfill prevention device function tests for the regulated tanks. Please clarify test procedure for the Western Global tank overfill devices. | |||||||
No Discharges Found |