04/10/2025 Editable Letter Activity Paul, Jennifer
Activity Title: Return to Compliance Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 04/10/2025
Comment: Finished
Events:
Event Type: Activity/Document has been approved Date: 04/10/2025
Comment: Approved by Shane Tierney: Return to compliance approved 4/10/25 SMT
Events:
Event Type: Activity has been submitted for approval Date: 04/10/2025
Comment: Submitted for approval by: Jennifer Paul
Attachments:
Attachment Date: 04/10/2025 User: PAUL_JK
Description: Return to Compliance Letter
View Attachment
04/04/2025 Electronic Communication Activity Paul, Jennifer
Activity Closed Date: 04/04/2025 Activity Status: Closed
Date: 04/04/2025
Recipient: Jay Seewald- jay@onthemovegas.com
Sender: Jennifer.Paul@FloridaDEP.gov
Subject: Facility 8507035 Remaining Violations
Message: Good Morning, Mr. Seewald, Per recent enforcement case review of the above referenced facilities, the following open violations have not been resolved (see attached copies of most recent inspection reports). In efforts to return these facilities to compliance prior to further agency action with penalty assessment, please provide the following required corrective action documentation for remaining violations: 8507035-San Juan Sunoco: 1. Repair and or replace dispenser 9-10 electrical boots. Perform hydrostatic test to ensure integrity of dispenser 9-10 sump. If hydrostatic testing passes no further action required. If hydrostatic test fails sampling will be required. 2. Dispenser 7-8 contains approximately 2 inches of liquid. Corrective Action: Investigate issue to determine if a discharge has occurred. 3. Facility must remove liquid from dispenser 7-8 sump and dispose of properly. Responsible Party must determine the source of the liquid and determine if a discharge to the environment occurred or not. Incident investigation documentation must be provided. Sampling may be required. 4. The Premium and Diesel tank #8 had 12 inches of Brine in the Interstice. Normal brine levels should be 7-9 inches. Corrective Action: Investigate issue to determine if a discharge has occurred. 5. Responsible Party must determine the source of the additional liquid in Tank #8 interstitial and determine if a discharge to the environment occurred or not. Incident investigation documentation must be provided. Sampling may be required. 6. Repair and or replace the Regular and Diesel STP sump lids. 8506649-Dunn Sunoco: 1. No facility representative was present for the inspection to provide access to the tank system. Corrective Action: Schedule an inspection with a facility representative present. 2. The Kerosene tank contains approximately 12 inches of fuel in the tank. The Regular 2 tank has approximately 7 inches of water in the tank. Annual monitoring of tanks 5,6,7,8 are not being conducted. Corrective Action: Investigate issue to determine if a discharge has occurred. Sampling may be required. 3. Repair damaged Regular fill area and provide documentation of repair/replacement. 8507168-Lane Sunoco: 1. Tanks # 6, 7 and 8 have little or no brine in the interstitials. Corrective Action: Investigate issue to determine if a discharge has occurred. 2. Responsible Party must determine where the brine liquid from tanks 6,7, and 8 went. Determine if a discharge to the environment occurred or not. Incident investigation documentation must be provided. Integrity testing and Sampling may be required. 3. Repair and or replace broken lid on tank #6. Repair and or replace the STP interior caps on Regular 2, Premium and Kerosene. 4. Access was not provided to the storage tank system or system components during the inspection. Corrective Action: Schedule an inspection to provide access to the storage tank system and all system components. Feel free to contact me with any questions. Sincerely, Jennifer Jennifer Paul Florida Department of Environmental Protection Northeast District-Waste Cleanup/Storage Tanks Environmental Consultant Jennifer.Paul@FloridaDEP.gov Office: 904-256-1619
Events:
Event Type: Activity has been finished Date: 04/04/2025
Comment: Finished
03/27/2025 Site Inspection Activity Open Alberchinski, Charles A
Activity Status: Open
On-Site Start Date: 03/19/2025
Events:
Event Type: Activity has been submitted for approval Date: 04/10/2025
Comment: Submitted for approval by: Charles A Alberchinski
Events:
Event Type: Activity has not been approved Date: 04/11/2025
Comment: Not approved by Janelle Ames: OOS tanks need to be corrected or cited.
06/03/2024 Document Management Activity Robbins, James
Activity Title: Incident Notification Form Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 06/03/2024
Comment: Finished
Attachments:
Attachment Date: 06/03/2024 User: ROBBINS_JL_1
Description: INF for interstice
View Attachment
06/03/2024 Document Management Activity Robbins, James
Activity Title: Incident Notification Form Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 06/03/2024
Comment: Finished
Attachments:
Attachment Date: 06/03/2024 User: ROBBINS_JL_1
Description: INF for facility pump out
View Attachment
06/03/2024 Electronic Communication Activity Robbins, James
Activity Closed Date: 06/03/2024 Activity Status: Closed
Date: 06/03/2024
Recipient: James Robbins
Sender: Don Bodie at Montrose Environmental
Subject: Resolving violations
Message: See violation resolution comments
Events:
Event Type: Activity has been finished Date: 06/03/2024
Comment: Finished
05/30/2024 Enforcement Tracking Activity Paul, Jennifer
Activity Status: Closed
Activity Result: Closed Without Enforcement Activity Closed Date: 04/10/2025
Events:
Event Type: Activity has been finished Date: 04/10/2025
Comment: Finished
05/30/2024 Enforcement Referral Activity Gainey, Helen
Activity Result: Accepted Activity Status: Closed
Activity Closed Date: 05/30/2024
Events:
Event Type: Activity has been submitted for approval Date: 05/30/2024
Comment: Submitted for approval by: Helen Gainey: Violations cited during routine compliance inspection.
Events:
Event Type: Activity has been finished Date: 05/30/2024
Comment: Finished
Events:
Event Type: Activity/Document was accepted on this date Date: 05/30/2024
Comment: Accepted by Jennifer Paul: Accepted
Events:
Event Type: Activity/Document was acknowledged on this date Date: 05/30/2024
Comment: Acknowledged and Assigned by Jennifer Paul
Events:
Event Type: Activity has been assigned Date: 05/30/2024
Comment: Assigned to Jennifer Paul
Comments:
Comment Date: 05/30/2024 User: GAINEY_H_1
Description: Violations cited during routine compliance inspection.
Attachments:
Attachment Date: 05/30/2024 User: GAINEY_H_1
Description: 8507035_CRDE Information Sheet_05-30-2024
View Attachment
05/20/2024 Electronic Communication Activity Robbins, James
Activity Closed Date: 05/20/2024 Activity Status: Closed
Date: 05/20/2024
Recipient: Jay Seewald, Rick Herweh, Don Bodi
Sender: James Robbins
Subject: 3rd final 90 day notice
Message: See attached
Events:
Event Type: Activity has been finished Date: 05/20/2024
Comment: Finished
05/06/2024 Electronic Communication Activity Robbins, James
Activity Closed Date: 05/06/2024 Activity Status: Closed
Date: 05/06/2024
Recipient: Jay Seewald, Rick Herweh, Don Bodi
Sender: James Robbins
Subject: 2nd 60 day reminder
Message: See attached
Events:
Event Type: Activity has been finished Date: 05/06/2024
Comment: Finished
04/02/2024 Electronic Communication Activity Robbins, James
Activity Closed Date: 04/02/2024 Activity Status: Closed
Date: 04/02/2024
Recipient: Jay Seewald, Rick Herweh, Don Bodi
Sender: James Robbins
Subject: 1st 30 day reminder
Message: See attached
Events:
Event Type: Activity has been finished Date: 04/02/2024
Comment: Finished
03/05/2024 Violation Closed Robbins, James
Significance: Minor Status: Closed
Criteria ID: 6073
Rule: 62-761.700(3)(b), 62-761.700(3)(b)1, 62-761.700(3)(b)2
03/05/2024 Editable Letter Activity Robbins, James
Activity Title: Compliance Assistance Offer Letter Activity Status: Closed
Description: PSC Signage 2
Events:
Event Type: Document has been sent Date: 03/05/2024
Comment: Sent
Events:
Event Type: Activity has been finished Date: 03/05/2024
Comment: Finished
Attachments:
Attachment Date: 03/05/2024 User: ROBBINS_JL_1
Description: Compliance Assistance Offer Letter
View Attachment
03/05/2024 Incident Activity Robbins, James
Activity Status: Open
03/05/2024 Incident Activity Robbins, James
Activity Status: Open
03/05/2024 Violation Closed Robbins, James
Significance: Minor Status: Closed
Criteria ID: 6015
Rule: 62-761.430(4), 62-761.430(5)
03/05/2024 Violation Closed Robbins, James
Significance: SNC-B Status: Closed
Criteria ID: 6014
Rule: 62-761.430(2)
03/05/2024 Violation Closed Robbins, James
Significance: Minor Status: Closed
Criteria ID: 6015
Rule: 62-761.430(4), 62-761.430(5)
03/05/2024 Violation Closed Robbins, James
Significance: Minor Status: Closed
Criteria ID: 6009
Rule: 62-761.405(3)
03/05/2024 Violation Closed Robbins, James
Significance: Minor Status: Closed
Criteria ID: 6009
Rule: 62-761.405(3)
03/05/2024 Violation Closed Robbins, James
Significance: SNC-B Status: Closed
Criteria ID: 6063
Rule: 62-761.700(1), 62-761.700(1)(a), 62-761.700(1)(a)1, 62-761.700(1)(a)2
03/05/2024 Violation Closed Robbins, James
Significance: SNC-B Status: Closed
Criteria ID: 6063
Rule: 62-761.700(1), 62-761.700(1)(a), 62-761.700(1)(a)1, 62-761.700(1)(a)2
03/05/2024 Violation Closed Robbins, James
Significance: SNC-B Status: Closed
Criteria ID: 6060
Rule: 62-761.600(2), 62-761.600(2)(a), 62-761.600(2)(a)1, 62-761.600(2)(a)2, 62-761.600(2)(a)3, 62-761.600(2)(a)4, 62-761.600(2)(a)5, 62-761.600(2)(a)6, 62-761.600(2)(a)6.a, 62-761.600(2)(a)6.b, 62-761.600(2)(a)7, 62-761.600(2)(a)8
03/05/2024 Violation Closed Robbins, James
Significance: SNC-B Status: Closed
Criteria ID: 6014
Rule: 62-761.430(2)
03/04/2024 Site Inspection Activity Closed Robbins, James
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 03/04/2024
Activity Closed Date: 03/05/2024 Activity Closed By: ROBBINS_JL_1
Events:
Event Type: Activity has been finished Date: 03/05/2024
Comment: Finished
12/14/2023 Enforcement Tracking Activity Paul, Jennifer
Activity Status: Closed
Activity Result: Closed Without Enforcement Activity Closed Date: 09/11/2024
Events:
Event Type: Activity has been finished Date: 09/11/2024
Comment: Finished
12/13/2023 Enforcement Referral Activity Gainey, Helen
Activity Result: Accepted Activity Status: Closed
Activity Closed Date: 12/14/2023
Events:
Event Type: Activity/Document was acknowledged on this date Date: 12/14/2023
Comment: Acknowledged and Assigned by Jennifer Paul
Events:
Event Type: Activity has been assigned Date: 12/14/2023
Comment: Assigned to Jennifer Paul
Events:
Event Type: Activity has been finished Date: 12/14/2023
Comment: Finished
Events:
Event Type: Activity/Document was accepted on this date Date: 12/14/2023
Comment: Accepted by Jennifer Paul: Accepted
Events:
Event Type: Activity has been submitted for approval Date: 12/13/2023
Comment: Submitted for approval by: Helen Gainey: SNC-A violation cited for immediate referral.
Comments:
Comment Date: 12/13/2023 User: GAINEY_H_1
Description: SNC-A violation cited for immediate referral.
Attachments:
Attachment Date: 12/13/2023 User: GAINEY_H_1
Description: 8507035_CRDE Information Sheet_12-13-2023
View Attachment
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6006
Rule: 62-761.400(5)
12/12/2023 Editable Letter Activity Branch, Bennis
Activity Title: 1st Non-Compliance Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 12/12/2023
Comment: Finished
Events:
Event Type: Document has been sent Date: 12/12/2023
Comment: Sent
Attachments:
Attachment Date: 12/12/2023 User: BRANCH_BL_1
Description: 8507035_San Juan Sunoco_NCL
View Attachment
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6072
Rule: 62-761.700(3), 62-761.700(3)(a), 62-761.700(3)(a)1, 62-761.700(3)(a)1.a, 62-761.700(3)(a)1.b, 62-761.700(3)(a)1.c, 62-761.700(3)(a)1.d, 62-761.700(3)(a)1.e, 62-761.700(3)(a)1.f, 62-761.700(3)(a)1.g, 62-761.700(3)(a)2
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6053
Rule: 62-761.500(7)(c), 62-761.500(7)(c)1, 62-761.500(7)(c)2, 62-761.500(7)(d)
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6062
Rule: 62-761.600(4)
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6001
Rule: 62-761.100(3)
12/12/2023 Violation Closed Branch, Bennis
Significance: SNC-B Status: Closed
Criteria ID: 6056
Rule: 62-761.600(1)(d), 62-761.600(1)(e), 62-761.600(1)(g)
12/12/2023 Violation Closed Branch, Bennis
Significance: SNC-A Status: Closed
Criteria ID: 6012
Rule: 62-761.420(2)
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6074
Rule: 62-761.710(1), 62-761.710(2), 62-761.710(2)(a), 62-761.710(2)(b), 62-761.710(2)(c), 62-761.710(2)(d), 62-761.710(3), 62-761.710(3)(a), 62-761.710(3)(b), 62-761.710(3)(c), 62-761.710(3)(d), 62-761.710(3)(e), 62-761.710(3)(f), 62-761.710(3)(g), 62-761.710(3)(h), 62-761.710(3)(i)
12/12/2023 Violation Closed Branch, Bennis
Significance: Minor Status: Closed
Criteria ID: 6002
Rule: 62-761.350(1), 62-761.350(1)(c), 62-761.350(1)(d), 62-761.350(3)(b)2, 62-761.350(5)(a), 62-761.350(5)(b), 62-761.350(5)(c), 62-761.350(7)
12/04/2023 Site Inspection Activity Closed Branch, Bennis
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 12/04/2023
Activity Closed Date: 12/12/2023 Activity Closed By: BRANCH_BL_1
Events:
Event Type: Activity has been finished Date: 12/12/2023
Comment: Finished
Comments:
Comment Date: 12/12/2023 User: BRANCH_BL_1
Description: Signature not captured due to the absence of a facility representative.
02/16/2022 Editable Letter Activity Quick, Victoria
Activity Title: Warning Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 07/13/2022
Comment: Finished
Attachments:
Attachment Date: 02/16/2022 User: QUICK_V
Description: Warning Letter
View Attachment
01/27/2022 Enforcement Tracking Activity Quick, Victoria
Activity Status: Closed
Activity Result: Closed Without Enforcement Activity Closed Date: 09/11/2024
Events:
Event Type: Activity has been finished Date: 09/11/2024
Comment: Finished
01/14/2022 Enforcement Referral Activity Gainey, Helen
Activity Result: Accepted Activity Status: Closed
Activity Closed Date: 01/27/2022
Events:
Event Type: Activity has been finished Date: 01/27/2022
Comment: Finished
Events:
Event Type: Activity has been submitted for approval Date: 01/14/2022
Comment: Submitted for approval by: Helen Gainey: Violations cited during routine compliance inspection.
Events:
Event Type: Activity has been assigned Date: 01/27/2022
Comment: Assigned to Victoria Quick
Events:
Event Type: Activity/Document was acknowledged on this date Date: 01/27/2022
Comment: Acknowledged and Assigned by Kajani Cole
Events:
Event Type: Activity/Document was accepted on this date Date: 01/27/2022
Comment: Accepted by Victoria Quick: ok
Comments:
Comment Date: 01/14/2022 User: GAINEY_H_1
Description: Violations cited during routine compliance inspection.
Attachments:
Attachment Date: 01/14/2022 User: GAINEY_H_1
Description: 8507035_CRDE Information Sheet_01-14-2022
View Attachment
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6001
Rule: 62-761.100(3)
10/18/2021 Editable Letter Activity McKinley, Donielle Nicole
Activity Title: Compliance Assistance Offer Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 10/18/2021
Comment: Finished
Events:
Event Type: Compliance Assistance Offer Verbal Date: 10/18/2021
Comment: Compliance Assistance Offer Verbal
Attachments:
Attachment Date: 10/18/2021 User: MCKINLEY_DN_1
Description: CAO letter
View Attachment
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: SNC-B Status: Closed
Criteria ID: 6011
Rule: 62-761.420(2)
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6062
Rule: 62-761.600(4)
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: SNC-B Status: Closed
Criteria ID: 6056
Rule: 62-761.600(1)(d), 62-761.600(1)(e), 62-761.600(1)(g)
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6053
Rule: 62-761.500(7)(c), 62-761.500(7)(c)1, 62-761.500(7)(c)2, 62-761.500(7)(d)
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6024
Rule: 62-761.500(1)(b)4, 62-761.500(1)(b)5, 62-761.500(1)(b)6, 62-761.500(1)(b)7
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6075
Rule: 62-761.710(4)
10/18/2021 Violation Closed McKinley, Donielle Nicole
Significance: Minor Status: Closed
Criteria ID: 6002
Rule: 62-761.350(1), 62-761.350(1)(c), 62-761.350(1)(d), 62-761.350(3)(b)2, 62-761.350(5)(a), 62-761.350(5)(b), 62-761.350(5)(c), 62-761.350(7)
10/13/2021 Site Inspection Activity Closed McKinley, Donielle Nicole
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 10/13/2021
Activity Closed Date: 10/18/2021 Activity Closed By: MCKINLEY_DN_1
Events:
Event Type: Activity has been finished Date: 10/18/2021
Comment: Finished
08/23/2021 Phone Conversation Activity McKinley, Donielle Nicole
Call Type: Outgoing Activity Status: Closed
Phone Number: (561) 732-4670 Activity Closed Date: 08/23/2021
Subject: Tried calling other numbers listed in FIRST, 561-732-4670 and 561-737-4670 both were disconnected.
Events:
Event Type: Activity has been finished Date: 08/23/2021
Comment: Finished
08/23/2021 Meeting Activity McKinley, Donielle Nicole
Activity Closed Date: 08/23/2021 Activity Status: Closed
Location: 4586 San Juan Ave
Subject: Drove to the site to try and talk to the manager about scheduling a compliance inspection. Left information, email, list of documents needed etc. with cashier and she said she would call the manager and try to get a hold of Jay to schedule the inspection. Have not heard back from anyone as of 8/23/2021.
Events:
Event Type: Activity has been finished Date: 08/23/2021
Comment: Finished
08/23/2021 Phone Conversation Activity McKinley, Donielle Nicole
Call Type: Outgoing Activity Status: Closed
Phone Number: (954) 520-0300 Activity Closed Date: 08/23/2021
Subject: Called one of the phone numbers listed in FIRST for Jay Seewald to try to schedule a compliance inspection. Left a voicemail, still have not heard back as of 8/23/2021.
Events:
Event Type: Activity has been finished Date: 08/23/2021
Comment: Finished
08/23/2021 Electronic Communication Activity McKinley, Donielle Nicole
Activity Closed Date: 08/23/2021 Activity Status: Closed
Date: 08/23/2021
Recipient: Jay Seewald
Sender: Donielle McKinley
Subject: Outreach to schedule inspections at 3 of his Sunoco Stations.
Message: See attached
Events:
Event Type: Activity has been finished Date: 08/23/2021
Comment: Finished
06/25/2020 Editable Letter Activity Harris, Matthew J
Activity Title: Return to Compliance Letter Activity Status: Closed
Description: 2020-02-25 TCI/CAO Email
Events:
Event Type: Activity has been finished Date: 06/25/2020
Comment: Finished
Attachments:
Attachment Date: 06/25/2020 User: OLIVA_L
Description: RTC
View Attachment
09/20/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4012
Rule: 62-761.405(3)
09/20/2019 Editable Letter Activity Lunn, Raynald
Activity Title: Compliance Assistance Offer Letter Activity Status: Closed
Events:
Event Type: Document has been sent Date: 09/20/2019
Comment: Sent
Events:
Event Type: Activity has been finished Date: 09/20/2019
Comment: Finished
Attachments:
Attachment Date: 09/20/2019 User: LUNN_RJ_1
Description: 8507035_CAO Letter_9-20-2019
View Attachment
09/20/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4068
Rule: 62-761.700(1), 62-761.700(1)(a), 62-761.700(1)(a)1., 62-761.700(1)(a)2.
08/29/2019 Site Inspection Activity Closed Lunn, Raynald
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 08/29/2019
Activity Closed Date: 09/20/2019 Activity Closed By: LUNN_RJ_1
Events:
Event Type: Activity has been finished Date: 09/20/2019
Comment: Finished
08/23/2019 Enforcement Tracking Activity O'Brien, Shelby A
Activity Status: Closed
Activity Result: Closed Without Enforcement Activity Closed Date: 06/25/2020
Events:
Event Type: Activity has been finished Date: 06/25/2020
Comment: Finished
08/02/2019 Attachment Gregory, Hali M
08/02/2019 Enforcement Referral Activity Gregory, Hali M
Activity Result: Accepted Activity Status: Closed
Activity Closed Date: 08/23/2019
Events:
Event Type: Activity has been finished Date: 08/23/2019
Comment: Finished
Events:
Event Type: Activity/Document was accepted on this date Date: 08/23/2019
Comment: Accepted by Shelby A O'Brien: .
Events:
Event Type: Activity has been submitted for approval Date: 08/02/2019
Comment: Submitted for approval by: Hali M Gregory: Violations cited during compliance inspection. A re inspection is approved by FLDEP and is to be scheduled soon.
Events:
Event Type: Activity/Document was acknowledged on this date Date: 08/05/2019
Comment: Acknowledged and Assigned by Matthew J Harris
Events:
Event Type: Activity has been assigned Date: 08/05/2019
Comment: Assigned to Shelby A O'Brien
Comments:
Comment Date: 08/02/2019 User: GREGORY_HM_1
Description: Violations cited during compliance inspection. A re inspection is approved by FLDEP and is to be scheduled soon.
Attachments:
Attachment Date: 08/02/2019 User: GREGORY_HM_1
Description: CRDE SHEET 8-2-2019
View Attachment
07/16/2019 Electronic Communication Activity Lunn, Raynald
Activity Closed Date: 07/16/2019 Activity Status: Closed
Date: 07/16/2019
Recipient: Rich Herweh
Sender: Ray Lunn
Subject: 7-16-19 E-mail Query Status of Violations
Message: See attahce
Events:
Event Type: Activity has been finished Date: 07/16/2019
Comment: Finished
06/25/2019 Record Document Activity Lunn, Raynald
Activity Status: Closed
Contact Name: Ray Lunn Activity Closed Date: 07/16/2019
Events:
Event Type: Activity has been finished Date: 07/16/2019
Comment: Finished
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4076
Rule: 62-761.700(3), 62-761.700(3)(a), 62-761.700(3)(a)1., 62-761.700(3)(a)1.a., 62-761.700(3)(a)1.b., 62-761.700(3)(a)1.c., 62-761.700(3)(a)1.d., 62-761.700(3)(a)1.e., 62-761.700(3)(a)1.f., 62-761.700(3)(a)2.
05/06/2019 Editable Letter Activity Lunn, Raynald
Activity Title: Compliance Assistance Offer Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 05/06/2019
Comment: Finished
Events:
Event Type: Document has been sent Date: 05/06/2019
Comment: Sent
Attachments:
Attachment Date: 05/06/2019 User: LUNN_RJ_1
Description: 8507035_CAO Letter_5-6-2019
View Attachment
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4015
Rule: 62-761.420(3), 62-761.420(4)
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4000
Rule: 62-761.100(3)
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4068
Rule: 62-761.700(1), 62-761.700(1)(a), 62-761.700(1)(a)1., 62-761.700(1)(a)2.
05/06/2019 Violation Closed Lunn, Raynald
Significance: SNC-B Status: Closed
Criteria ID: 4055
Rule: 62-761.500(7)(b), 62-761.500(7)(b)1., 62-761.500(7)(b)2., 62-761.500(7)(b)3.
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4079
Rule: 62-761.710(2), 62-761.710(2)(a), 62-761.710(2)(b), 62-761.710(2)(c), 62-761.710(2)(d)
05/06/2019 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 4012
Rule: 62-761.405(3)
04/15/2019 Site Inspection Activity Closed Lunn, Raynald
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 04/15/2019
Activity Closed Date: 05/06/2019 Activity Closed By: LUNN_RJ_1
Events:
Event Type: Activity has been finished Date: 05/06/2019
Comment: Finished
03/15/2019 Attachment Richards, Jean
04/18/2016 Attachment Lunn, Raynald
04/15/2016 Electronic Communication Activity Lunn, Raynald
Activity Closed Date: 04/15/2016 Activity Status: Closed
Date: 04/15/2016
Recipient: Rick Hereh and Ronnies Michaels
Sender: EQD
Subject: E-mailed inspection
Message: See attached
Events:
Event Type: Activity has been finished Date: 04/15/2016
Comment: Finished
04/11/2016 Site Inspection Activity Closed Lunn, Raynald
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 04/01/2016
Activity Closed Date: 04/14/2016 Activity Closed By: LUNN_RJ_1
Events:
Event Type: Activity has been finished Date: 04/14/2016
Comment: Finished
04/01/2016 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 1103
Rule: 62-761.640(4)(a)1., 62-761.640(4)(a)2., 62-761.640(4)(a)3., 62-761.640(4)(a)4.
Comments: Installation - verify that the line leak detector has been installed during the final installation inspection. Compliance - check to see that the unit is present. Examine the annual function test data - a pass alone is not sufficient. The tester must demonstrate 3.0 gph discharge detection for the mechanical (flow restrictor). Note that the electronic (auto shut off) line leak detector does not need an annual test, but must still be able to detect a 0.2 gph leak after it has been tripped at 150% line operating pressure. Replacements - unit must be tested out of the box - function must be proven. 3.0 gph = 185.4 ml/min (To convert milliliters/minute to gallons/hour, multiple the milliliters by 0.0162162; or, 1 gph equals 61.8 ml/min). Values greater than 186 ml/min fail. Values less than 185 ml/min mean that the line leak detector will activate at a more restrictive rate.
04/01/2016 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 1117
Rule: 62-761.700(1)(c)3.
Comments: Facility must prove that all release detection devices, such as in line leak detectors, sump and liner sensors, ATGs, etc. function properly. Sensing devices may be optical, vapor, float activated, discriminating, non-discriminating, or tied into electrical circuits. ATG probes inside of tanks require calibration testing, if used for release detection as well as inventory measurements.
04/01/2016 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 1122
Rule: 62-761.710(1)
Comments: Was reasonable access to the facility granted? If not, document the circumstances. Were the records available within the specified time frame? If five day pre-inspection notice was not given by the inspector, this item can not be marked as a discrepancy. Make note of the missing documents, and arrange a review period.
04/01/2016 Violation Closed Lunn, Raynald
Significance: Minor Status: Closed
Criteria ID: 1115
Rule: 62-761.700(1)(c)1.
Comments: Facility equipment shall be maintained to a degree to allow you access. Water in spill containment units, especially above the fill cap shall be removed. Water in any sumps and dispenser liners above the piping opening/penetration (invert) shall be removed. All regulated substance shall be removed from any of the specified system components. Regulated substances: sheen, free product, mixed product water. Petroleum contact water shall be disposed of in accordance with the Department Hazardous Waste Section's Ch. 62-740 F.A.C., "Petroleum Contact Water".
10/12/2015 Electronic Communication Activity Lunn, Raynald
Activity Closed Date: 10/12/2015 Activity Status: Closed
Date: 10/12/2015
Recipient: Rick Herweh
Sender: EQD
Subject: E-mailed per-inspection information
Message: See attached
Events:
Event Type: Activity has been finished Date: 10/12/2015
Comment: Finished
06/24/2014 Electronic Communication Activity Williams, April K.
Activity Closed Date: 06/24/2014 Activity Status: Closed
Date: 06/24/2014
Recipient: EQD
Sender: Michael Matri, Hess Corp
Subject: work-order for completed repairs
Message: 6-3-2014 Work-order for entry boot repairs submitted to Department.
Events:
Event Type: Activity has been finished Date: 06/24/2014
Comment: Finished
03/18/2014 Editable Letter Activity Richards, Jean
Activity Title: County Subsequent Non-Compliance Letter Activity Status: Closed
Description: email from contractor, closure report & pix 5/16/18
Events:
Event Type: Activity has been finished Date: 03/18/2014
Comment: Finished
Attachments:
Attachment Date: 03/18/2014 User: RICHARDS_JE_1
Description: 8507035_CSNCL Viol 1105_03-18-2014.pdf
View Attachment
03/04/2014 Electronic Communication Activity Williams, April K.
Activity Closed Date: 03/04/2014 Activity Status: Closed
Date: 03/04/2014
Recipient: EQD
Sender: Michael Matri
Subject: INF Submitted to Department
Message: INF has been submitted and an investigation has been conducted by the facility.
Events:
Event Type: Activity has been finished Date: 03/04/2014
Comment: Finished
01/03/2014 Editable Letter Activity Williams, April K.
Activity Title: 1st Non-Compliance Letter Activity Status: Closed
Description: Overfill protection device test email
Events:
Event Type: Activity has been finished Date: 01/03/2014
Comment: Finished
Attachments:
Attachment Date: 01/03/2014 User: RICHARDS_JE_1
Description: 8507035_1st County NCL Viol 1010_1105_01-03-2014.pdf
View Attachment
01/03/2014 Electronic Communication Activity Williams, April K.
Activity Closed Date: 01/06/2014 Activity Status: Closed
Date: 01/03/2014
Recipient: ustcompliance@hess.com
Sender: EQD
Subject: Emailed Compliance Report
Message: See Attachment
Events:
Event Type: Activity has been finished Date: 01/06/2014
Comment: Finished
12/19/2013 Violation Closed Williams, April K.
Significance: Minor Status: Closed
Criteria ID: 1010
Rule: 62-761.450(2)(a)1., 62-761.450(2)(a)2., 62-761.450(2)(a)3., 62-761.450(2)(a)4., 62-761.450(2)(a)5., 62-761.450(2)(a)6., 62-761.450(2)(a)7.
Comments: Multiple incidents occurring at the same time at the facility may be reported on one form. #1-3 - Evidence of these types of INF situations are generally found during the inspector's paperwork review. Ask the facility representative what action they took in response, and in what time frame. If the situations are resolved within 24 hours, the owner/operator is not required to submit an INF to the local program. However, the actions they took to resolve the issue must be documented. #4-5, and 7 - Evidence of these types of situations are generally found during the outside or physical portion of the inspection. Give the facility owner/operator 24 hours to resolve, provided they document their actions. If they can not resolve the issues then they must submit the INF, at which time the two week investigative window opens. #6 - Evidence of this type of situation may be found during the physical examination of the release detection device (e.g. alarm mode), or during the examination of the records associated with the method. Note: Inspectors may find events that qualify as incidents during their review of the facility's paperwork. Such issues must have been resolved within 24 hours if an INF was not submitted at the time of the event.
12/19/2013 Emergency Preparedness Information Activity Williams, April K.
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 12/19/2013
Events:
Event Type: Activity has been finished Date: 12/19/2013
Comment: Finished
12/19/2013 Site Inspection Activity Closed Williams, April K.
Activity Result: Minor Out of Compliance Activity Status: Closed
On-Site Start Date: 12/19/2013
Activity Closed Date: 01/03/2014 Activity Closed By: WILLIAMS_AK_1
Events:
Event Type: Activity has been finished Date: 01/03/2014
Comment: Finished
12/19/2013 Violation Closed Williams, April K.
Significance: Minor Status: Closed
Criteria ID: 1105
Rule: 62-761.700(1)(a)1.a., 62-761.700(1)(a)1.b., 62-761.700(1)(a)1.c., 62-761.700(1)(a)1.d.
Comments: Mark this as out of compliance if you observe a needed repair that hasn't been completed, and the potential for a release exists. Examples of components that would need repair include (but are not limited to) leaking dispensers, cracked spill containment, improperly anchored shear valves, or any compromised containment component. Upon the detection of one of the above conditions, has the facility initiated and completed repairs?
02/02/2012 Record Document Activity Cain, Michael
Activity Status: Closed
Contact Name: Hess Corporation Activity Closed Date: 02/02/2012
Events:
Event Type: Activity has been finished Date: 02/02/2012
Comment: Finished
02/01/2012 Emergency Preparedness Information Activity Cain, Michael
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 02/01/2012
Events:
Event Type: Activity has been finished Date: 02/01/2012
Comment: Finished
01/25/2012 Site Inspection Activity Closed Cain, Michael
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 01/26/2012
Activity Closed Date: 02/01/2012 Activity Closed By: CAIN_M_1
Events:
Event Type: Activity has been finished Date: 02/01/2012
Comment: Finished
09/14/2010 Attachment Holloway, Randall
09/08/2010 Attachment Holloway, Randall
09/05/2010 Site Inspection Activity Closed Holloway, Randall
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/09/2010
Activity Closed Date: 09/09/2010 Activity Closed By: HOLLOWAY_RW_1
Events:
Event Type: Activity has been finished Date: 09/09/2010
Comment: Finished
Comments:
Comment Date: 09/05/2010 User: HOLLOWAY_RW_1
Description: Proper notification given to Hess via e-mail at (ustcompliance@hess.com) prior to inspection. Hess contacted Steve Moore with Crompco and Steve contacted me via e-mail to set up the inspection dates and times. Paperwork inspection conducted on 9-5-10 and 9-9-10. Verified cover page information. Placard is current. This facility is a retail station and has two 20K USTs. Tank interstitials are brine filled. Tanks 7 contains unleaded fuel while tank 8 is compartmented into 12K premium and 8K diesel. Tanks use interstitial monitoring by an ATG for release detection. Piping uses interstitial monitoring by the ATG and visual inspections for release detection. Sumps and dispenser liners have electronic sensors for release detection. Spill buckets use visual inspections for release detection.
09/05/2010 Electronic Communication Activity Holloway, Randall
Activity Closed Date: 09/05/2010 Activity Status: Closed
Date: 09/05/2010
Recipient: Hess Corp
Sender: Randy Holloway
Subject: Set up date and time to conduct 28 Hess inspections
Message: I contacted Hess in early August 2010 via e-mail at ustcompliance@hess.com to set up these inspections. Hess contacted Mr. Steve Moore at Crompco and Mr. Moore contacted me via e-mail. Mr. Moore and I set up 28 Hess inspections to begin at 9:00 am on 9-7-10. Our first inspection site is 8944670 Hess #09377 and we will continue conducting inspections until all 28 facilities have been inspected.
Events:
Event Type: Activity has been finished Date: 09/05/2010
Comment: Finished
02/09/2010 Editable Letter Activity Griffin, Tom
Activity Title: Site Assessment Request Activity Status: Closed
Events:
Event Type: Document has been sent Date: 12/06/2006
Comment: Sent on Wed Dec 06 00:00:00 EST 2006
Events:
Event Type: Activity has been finished Date: 02/09/2010
Comment: Finished
Attachments:
Attachment Date: 02/09/2010 User: GRIFFIN_TW_1
Description: 8507035_Hess #09314_SAR Letter 12/06/2006
View Attachment
09/16/2009 Attachment Holloway, Randall
09/16/2009 Attachment Holloway, Randall
09/16/2009 Attachment Holloway, Randall
09/16/2009 Attachment Holloway, Randall
09/16/2009 Attachment Holloway, Randall
09/02/2009 Attachment Holloway, Randall
09/02/2009 Site Inspection Activity Closed Holloway, Randall
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/02/2009
Activity Closed Date: 09/16/2009 Activity Closed By: HOLLOWAY_RW_1
Comments:
Comment Date: 09/02/2009 User: HOLLOWAY_RW_1
Description: Proper notification given to Hess and Mr. Steve Moore of Crompco prior to inspection. Paperwork inspection conducted on 9-2-09 and Verified cover page information. Placard is current. Tanks use interstitial monitoring by a Veeder Root TLS 350 for release detection. Tank interstitials are brine filled. Tank 8 is compartmented into 12K premium and 8K diesel. Piping uses interstitial monitoring by the ATG for release detection. Piping also has line leak detectors. Sumps and dispenser liners have electronic sensors for release detection. Spill bucket uses visual inspections for release detection.
07/29/2008 Site Inspection Activity Closed Williams, April K.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 07/29/2008
Activity Closed Date: 08/27/2008 Activity Closed By: WILLIAMS_AK_1
Comments:
Comment Date: 08/27/2008 User: WILLIAMS_AK_1
Description: Facility ID Number: 8507035 Facility Name: Hess #9314 Miscellaneous ¿ Proper notification was given to _Susan Hairston_prior to the inspection. ¿ The facility RP supplying the records __Steven Brogan ¿ The records were review on 8/27/2008. Registration ¿ All systems are registered and match Placard (1001N): yes Financial Responsibility ¿ A Certificate of Financial Responsibility was made available (1004B): yes Notification & Reporting ¿ The facility responsibility party has reviewed the information on screens 1/13 & 3/13 for accuracy.
08/26/2007 Site Inspection Activity Closed Griffin, Tom
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 08/26/2007
Activity Closed Date: 09/06/2007 Activity Closed By: WILLIAMS_AK_1
Comments:
Comment Date: 09/05/2007 User: GRIFFIN_TW_1
Description: 8507035 Hess 09314 CHECKLIST Need to update EQ if available: These tanks were placed in service on 9/1/2006 and all testing was performed at that time. See UST test schedule. Miscellaneous The paperwork for this inspection was performed on 8-27-2007 & the site inspection was performed on 9-06-2007. Proper notification was given prior to the inspection and proper identification was presented to the facility responsible party upon entry to the premises. The method of release detection used at this facility is: continuous electronic monitoring of tan interstitial space, electronic monitoring of pipe sump & visual monitoring of secondary containment. The method of overfill protection used at this facility is: spill bucket, tight fill & flow shutoff. The site equipment list has been reviewed for accuracy. NEEDS REVISION Registration ¿ The Placard kept in view (1003N): YES Note: Registration Fees are due and payable no later than June 30 of each year. Financial Responsibility ¿ The Financial Responsibility Records were current and made available for review (1004B): YES ¿ A Certificate of Financial Responsibility was made available (1004B): YES Financial Responsibility must be renewed before04/29/2008 and a new Certificate of Responsibility completed. Notification & Reporting ¿ The facility responsibility party has reviewed the information on screens 1/13 & 3/13 and a registration form is being submitted with correct information. There is no information change requiring the submittal of a Registration Form. Performance Standards Category C Integral Pipe ¿ Category C system has a breach of integrity test (1020N): YES ¿ A monitoring point has been provided for secondary containment (1021N): YES ¿ Fill box or tank marked with color code or contents for Category C (1032N): YES ¿ Overfill provided that shuts off/restricts flow/alarms (1033B): YES ¿ Pressurized pipe has shear valve properly installed (1040N): YES Release Detection ¿ A release can be detected from any portion of system: 600(a) (1)1 - (1058N): YES ¿ The release detection system is operational: 600(1) (a) 2 - (1059N): YES ¿ Release detection performed monthly: 600(1) (1) d - (1062B): YES ¿ Is electronic leak detection system checked monthly: 600(1) (e) - (1063N): YES ¿ Is there interstitial monitoring for secondary containment? 600(1) (h) - (1066B): YES ¿ The RDRL matches the release detection method: 640(1) (c) (1082N): YES ¿ Problems found during monthly visual inspections noted: 640(2) (e) ¿ (1091N) YES ¿ Water fluctuations > 1.0 ¿not investigated or system tested: 640(3) (b) 4 - (1096N): NA ¿ ATG system in test mode every 30 days or operated continuously - 640(3) (d) (1099N): YES Repairs Operation & Maintenance ¿ Piping sump - excess water or fuel removed (1115N): YES ¿ Release detection devices tested annually: 700(1) (3) c - (1117N): YES Recordkeeping ¿ Required records made available within five working days ¿ access to system components(1122N): ¿ Required records have been kept for 2 yrs (1123): one year review ¿ Required records have been kept for the life of the system. (1124N): one year review Incident & Discharge Response ¿ During the physical inspection of the facility, no evidence of a new product
Comments:
Comment Date: 08/27/2007 User: GRIFFIN_TW_1
Description: 8507035_UST TEST SCHEDULE: TANK Five Year Category C Breach of Integrity Test ¿ 62-761.500(1) (e) 5 / (1020-N): For systems not performing continuous monitoring of annular space, requires a BIT every 5 years. Note: A BIT is performed at installation and the five year clock starts at that date. Last Breach of Integrity Test: 9/01/2006 (Tanks placed in service) Next Breach of Integrity Test: 9/01/2011 (Continuous monitoring will not require this test) ANNUAL LINE & LINE LEAK DETECTOR Pressurized Line Test - 62-761.610(3) (a) 2/ (1077B) (SW pipe in contact w/soil): (Able to detect a 0.1 gph leak 150% operating pressure) Last: 9/01/2006 (Placed in service) Due: 9/01/2007 (Double wall pipe-this test will not be required) Line Leak Detector - 62-761.640(4) (a)/ (1103N): (Able to detect a 0.2 gph leak in the test mode/3 gph while in operation) Last: 9/01/2006 Due: 9/01/2006 ANNUAL OPERABILITY OF LEAK DETECTION DEVICES- 62-761.700(1) (c) 3 ATG: TLS 350 Last: 9/01/2006 Due: 9/01/2006 Tank Sensors: Last: 9/01/2006 Due: 9/01/2006 Interstitial Probe: Last: 9/01/2006 Due: 9/01/2006 Sump Probe: Last: 9/01/2006 Due: 9/01/2006 Dispenser Liner Probe: Last: 9/01/2006 Due: 9/01/2006
08/26/2007 Emergency Preparedness Information Activity Griffin, Tom
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 08/27/2007
Comments:
Comment Date: 08/26/2008 User: GRIFFIN_TW_1
Description: Six dispensers - four multi grade unleaded accessible from both sides & two diesel accessible from both sides.
08/26/2007 Site Inspection Activity Closed Griffin, Tom
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 08/26/2007
Activity Closed Date: 09/06/2007 Activity Closed By: WILLIAMS_AK_1
Comments:
Comment Date: 09/05/2007 User: GRIFFIN_TW_1
Description: 8507035 Hess 09314 CHECKLIST Need to update EQ if available: These tanks were placed in service on 9/1/2006 and all testing was performed at that time. See UST test schedule. Miscellaneous The paperwork for this inspection was performed on 8-27-2007 & the site inspection was performed on 9-06-2007. Proper notification was given prior to the inspection and proper identification was presented to the facility responsible party upon entry to the premises. The method of release detection used at this facility is: continuous electronic monitoring of tan interstitial space, electronic monitoring of pipe sump & visual monitoring of secondary containment. The method of overfill protection used at this facility is: spill bucket, tight fill & flow shutoff. The site equipment list has been reviewed for accuracy. NEEDS REVISION Registration ¿ The Placard kept in view (1003N): YES Note: Registration Fees are due and payable no later than June 30 of each year. Financial Responsibility ¿ The Financial Responsibility Records were current and made available for review (1004B): YES ¿ A Certificate of Financial Responsibility was made available (1004B): YES Financial Responsibility must be renewed before04/29/2008 and a new Certificate of Responsibility completed. Notification & Reporting ¿ The facility responsibility party has reviewed the information on screens 1/13 & 3/13 and a registration form is being submitted with correct information. There is no information change requiring the submittal of a Registration Form. Performance Standards Category C Integral Pipe ¿ Category C system has a breach of integrity test (1020N): YES ¿ A monitoring point has been provided for secondary containment (1021N): YES ¿ Fill box or tank marked with color code or contents for Category C (1032N): YES ¿ Overfill provided that shuts off/restricts flow/alarms (1033B): YES ¿ Pressurized pipe has shear valve properly installed (1040N): YES Release Detection ¿ A release can be detected from any portion of system: 600(a) (1)1 - (1058N): YES ¿ The release detection system is operational: 600(1) (a) 2 - (1059N): YES ¿ Release detection performed monthly: 600(1) (1) d - (1062B): YES ¿ Is electronic leak detection system checked monthly: 600(1) (e) - (1063N): YES ¿ Is there interstitial monitoring for secondary containment? 600(1) (h) - (1066B): YES ¿ The RDRL matches the release detection method: 640(1) (c) (1082N): YES ¿ Problems found during monthly visual inspections noted: 640(2) (e) ¿ (1091N) YES ¿ Water fluctuations > 1.0 ¿not investigated or system tested: 640(3) (b) 4 - (1096N): NA ¿ ATG system in test mode every 30 days or operated continuously - 640(3) (d) (1099N): YES Repairs Operation & Maintenance ¿ Piping sump - excess water or fuel removed (1115N): YES ¿ Release detection devices tested annually: 700(1) (3) c - (1117N): YES Recordkeeping ¿ Required records made available within five working days ¿ access to system components(1122N): ¿ Required records have been kept for 2 yrs (1123): one year review ¿ Required records have been kept for the life of the system. (1124N): one year review Incident & Discharge Response ¿ During the physical inspection of the facility, no evidence of a new product
Comments:
Comment Date: 08/27/2007 User: GRIFFIN_TW_1
Description: 8507035_UST TEST SCHEDULE: TANK Five Year Category C Breach of Integrity Test ¿ 62-761.500(1) (e) 5 / (1020-N): For systems not performing continuous monitoring of annular space, requires a BIT every 5 years. Note: A BIT is performed at installation and the five year clock starts at that date. Last Breach of Integrity Test: 9/01/2006 (Tanks placed in service) Next Breach of Integrity Test: 9/01/2011 (Continuous monitoring will not require this test) ANNUAL LINE & LINE LEAK DETECTOR Pressurized Line Test - 62-761.610(3) (a) 2/ (1077B) (SW pipe in contact w/soil): (Able to detect a 0.1 gph leak 150% operating pressure) Last: 9/01/2006 (Placed in service) Due: 9/01/2007 (Double wall pipe-this test will not be required) Line Leak Detector - 62-761.640(4) (a)/ (1103N): (Able to detect a 0.2 gph leak in the test mode/3 gph while in operation) Last: 9/01/2006 Due: 9/01/2006 ANNUAL OPERABILITY OF LEAK DETECTION DEVICES- 62-761.700(1) (c) 3 ATG: TLS 350 Last: 9/01/2006 Due: 9/01/2006 Tank Sensors: Last: 9/01/2006 Due: 9/01/2006 Interstitial Probe: Last: 9/01/2006 Due: 9/01/2006 Sump Probe: Last: 9/01/2006 Due: 9/01/2006 Dispenser Liner Probe: Last: 9/01/2006 Due: 9/01/2006
02/15/2007 Emergency Preparedness Information Activity Griffin, Tom
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 02/15/2007
12/14/2006 Attachment Medicus, Kimberly N.
12/14/2006 Attachment Medicus, Kimberly N.
12/06/2006 Discharge Reporting Activity Griffin, Tom
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 02/09/2010
Events:
Event Type: Activity has been finished Date: 02/09/2010
Comment: Finished
09/19/2006 Emergency Preparedness Information Activity Medicus, Kimberly N.
Activity Result: Satisfied Activity Status: Closed
Activity Closed Date: 09/19/2006
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/08/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/08/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: TII - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 The concrete has been broken and removed for installation of the new double walled storage tanks. Two new underground storage tanks were delivered to the facility along with the dead men and the sump collars. The storage tanks are manufactured by Containment Solutions. They are double walled fiberglass tanks. A brine solution fills the interstitial space. The first tank is a 20,000 gallon compartmented tank. The compartments are 8,000 gallons and 12,000 gallons. The UL # is 99124. The second tank is a 20,000 gallon single compartment tank. The UL # is 99127.
Comments:
Comment Date: 09/08/2006 User: MEDICUS_KN
Description: TIV - The contractor has begun to set the sheet piling in preparation for excavating the tank hole.
Comments:
Comment Date: 09/12/2006 User: MEDICUS_KN
Description: TIV - The sheet pile driving continued.
Comments:
Comment Date: 09/14/2006 User: MEDICUS_KN
Description: TIV - The contractor completed driving the sheet piles and the well points have been placed.
Comments:
Comment Date: 09/21/2006 User: MEDICUS_KN
Description: TIV - The dispenser islands have been removed and the piping trench has been excavated. The former piping has also been removed. The contractor began setting the new dispenser sumps into place.
Comments:
Comment Date: 10/28/2006 User: MEDICUS_KN
Description: TIV - The contractor placed two twenty thousand gallon tanks into the excavated tank pit. The tank manufacturer is Containment Solutions. The tanks are double-walled fiberglass construction with a brine filled interstice. One of the tanks is an 8k/12k compartmented tank UL:99127, the second is a 20k single compartment tank UL:99124. There are four deadmen per tank. Each tank required six straps to be secured properly to the deadmen. The storage tanks were placed in the ground without incident.
Comments:
Comment Date: 09/26/2006 User: MEDICUS_KN
Description: TIV - Contaminated soil discovered in the tank pit has been removed to a disposal facility for incineration.
Comments:
Comment Date: 10/03/2006 User: MEDICUS_KN
Description: TIV - The contractor has removed the sheet piling and the dewatering system from the tank pit. The tank pit has been backfilled with pea gravel.
Comments:
Comment Date: 09/19/2006 User: MEDICUS_KN
Description: TIV - The stripping towers have been erected. On site dewatering has commenced.
Comments:
Comment Date: 10/12/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the seconary fuel lines and a hydro test on all sumps and dispenser liners. The air had been placed on the lines 2 hours prior to the inspection which took place at approximately noon. The regular, premium, and diesel secondary line pressure was set at 5psi and remained at 5psi for the duration of the test. There were no bubbles in the sumps or the dispenser liners. The water levels remained unchanged in the sumps and the dispener liners.
Comments:
Comment Date: 10/11/2006 User: MEDICUS_KN
Description: TIV - Contractor requested an air test on the primary fuel lines. The air had been paced on the lines at 7am and remained on the lines until approximately 1pm. The pressure on the regular, premium, and diesel lines all read 65 psi. There were no leaks.
Comments:
Comment Date: 12/04/2006 User: MEDICUS_KN
Description: 11/15/2006 TIN - Tank pit has been backfilled and the concrete has been laid. Installation complete. Contractor did not contact for final inspection. All test results are to be forwarded to ERMD/EQD upon receipt. Site photos taken.
09/07/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/07/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/06/2006 User: MEDICUS_KN
Description: SV - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 CBI was on site cleaning and vacuuming the storage tanks in preparation for removal. All of the dispensers were removed.
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: SV - All storage tanks except for the vehicular diesel tank have been removed and crushed for disposal. The fiberglass storage tank pieces are being placed within realco recycling containers.
Comments:
Comment Date: 10/20/2006 User: MEDICUS_KN
Description: SV - A small single-walled steel 'heating oil' tank was discovered while excavating the area area around the diesel tank in preparation for removal on October 17, 2006. The tank did not contain any product, but was instead filled with water. The volume was estimated at 500 gallons. The tank was removed on October 20, 2006 and taken to be recycled at Berman Brothers Inc. in Jacksonville, FL.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: 10/26/2006 - TXI Closure of storage tank systems complete. Facility has 60 days to submit a limited closure assessment report to ERMD/EQD. No new releases observed.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: SV 10/26/2006 Diesel fuel tank removed. Fiberglass in construction. Tank was crushed and sent to the land fill. All piping associated with tank removed.
09/07/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/07/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/06/2006 User: MEDICUS_KN
Description: SV - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 CBI was on site cleaning and vacuuming the storage tanks in preparation for removal. All of the dispensers were removed.
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: SV - All storage tanks except for the vehicular diesel tank have been removed and crushed for disposal. The fiberglass storage tank pieces are being placed within realco recycling containers.
Comments:
Comment Date: 10/20/2006 User: MEDICUS_KN
Description: SV - A small single-walled steel 'heating oil' tank was discovered while excavating the area area around the diesel tank in preparation for removal on October 17, 2006. The tank did not contain any product, but was instead filled with water. The volume was estimated at 500 gallons. The tank was removed on October 20, 2006 and taken to be recycled at Berman Brothers Inc. in Jacksonville, FL.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: 10/26/2006 - TXI Closure of storage tank systems complete. Facility has 60 days to submit a limited closure assessment report to ERMD/EQD. No new releases observed.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: SV 10/26/2006 Diesel fuel tank removed. Fiberglass in construction. Tank was crushed and sent to the land fill. All piping associated with tank removed.
09/07/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/07/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/06/2006 User: MEDICUS_KN
Description: SV - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 CBI was on site cleaning and vacuuming the storage tanks in preparation for removal. All of the dispensers were removed.
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: SV - All storage tanks except for the vehicular diesel tank have been removed and crushed for disposal. The fiberglass storage tank pieces are being placed within realco recycling containers.
Comments:
Comment Date: 10/20/2006 User: MEDICUS_KN
Description: SV - A small single-walled steel 'heating oil' tank was discovered while excavating the area area around the diesel tank in preparation for removal on October 17, 2006. The tank did not contain any product, but was instead filled with water. The volume was estimated at 500 gallons. The tank was removed on October 20, 2006 and taken to be recycled at Berman Brothers Inc. in Jacksonville, FL.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: 10/26/2006 - TXI Closure of storage tank systems complete. Facility has 60 days to submit a limited closure assessment report to ERMD/EQD. No new releases observed.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: SV 10/26/2006 Diesel fuel tank removed. Fiberglass in construction. Tank was crushed and sent to the land fill. All piping associated with tank removed.
09/07/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/07/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/06/2006 User: MEDICUS_KN
Description: SV - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 CBI was on site cleaning and vacuuming the storage tanks in preparation for removal. All of the dispensers were removed.
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: SV - All storage tanks except for the vehicular diesel tank have been removed and crushed for disposal. The fiberglass storage tank pieces are being placed within realco recycling containers.
Comments:
Comment Date: 10/20/2006 User: MEDICUS_KN
Description: SV - A small single-walled steel 'heating oil' tank was discovered while excavating the area area around the diesel tank in preparation for removal on October 17, 2006. The tank did not contain any product, but was instead filled with water. The volume was estimated at 500 gallons. The tank was removed on October 20, 2006 and taken to be recycled at Berman Brothers Inc. in Jacksonville, FL.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: 10/26/2006 - TXI Closure of storage tank systems complete. Facility has 60 days to submit a limited closure assessment report to ERMD/EQD. No new releases observed.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: SV 10/26/2006 Diesel fuel tank removed. Fiberglass in construction. Tank was crushed and sent to the land fill. All piping associated with tank removed.
09/07/2006 Site Inspection Activity Closed Medicus, Kimberly N.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 09/07/2006
Activity Closed Date: 12/11/2006 Activity Closed By: MEDICUS_KN
Comments:
Comment Date: 09/06/2006 User: MEDICUS_KN
Description: SV - Recieved 30 day notice of upgrade on 8/3/2006 from Dave Spradlin. Recieved 10 day notice of upgrade on 8/23/06 from Blake Bammer. Recieved 48 hour notification on 9/1/2006 from Dave Spradlin. Contractor: Guardian Fuel Technologies 7380 Phillips Hwy #106 Jacksonville, FL 32256 PCC #056681 Environmental: Earth Systems 223 12th Ave. N #2 Jacksonville Beach, FL 32250 CBI was on site cleaning and vacuuming the storage tanks in preparation for removal. All of the dispensers were removed.
Comments:
Comment Date: 09/07/2006 User: MEDICUS_KN
Description: SV - All storage tanks except for the vehicular diesel tank have been removed and crushed for disposal. The fiberglass storage tank pieces are being placed within realco recycling containers.
Comments:
Comment Date: 10/20/2006 User: MEDICUS_KN
Description: SV - A small single-walled steel 'heating oil' tank was discovered while excavating the area area around the diesel tank in preparation for removal on October 17, 2006. The tank did not contain any product, but was instead filled with water. The volume was estimated at 500 gallons. The tank was removed on October 20, 2006 and taken to be recycled at Berman Brothers Inc. in Jacksonville, FL.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: 10/26/2006 - TXI Closure of storage tank systems complete. Facility has 60 days to submit a limited closure assessment report to ERMD/EQD. No new releases observed.
Comments:
Comment Date: 12/11/2006 User: MEDICUS_KN
Description: SV 10/26/2006 Diesel fuel tank removed. Fiberglass in construction. Tank was crushed and sent to the land fill. All piping associated with tank removed.
08/18/2006 Site Inspection Activity Closed Torsanko, Grace
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 08/18/2006
Activity Closed Date: 10/26/2006 Activity Closed By: WILLIAMS_AK_1
Comments:
Comment Date: 10/26/2006 User: WILLIAMS_AK_1
Description: Sumps are dry. Fills are color coded. Spill buckets are dry and no cracks are noticed. Dispenser liners are dry and shear valves are anchored. Tank interstitials are brine filled. Dual point vapor recovery Note: Facility map will be attached when installation inspection is finalized.
10/24/2005 Legacy Activity Allen, Eleanor
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
10/13/2005 Legacy Activity Griffin, Tom
Activity Name: DISCHARGE REPORT FORM RECEIVED Activity Status: Closed
Completion Notes: DRF RECEIVED FOR 9/27/05 ANALYTICAL RESULTS CONFIRMING DISCHARGE AT DIESEL SPILL BUCKET. REPLACEMENT
10/13/2005 Legacy Activity Griffin, Tom
Activity Name: CLEANUP NOTIFICATION LETTER ISSUED Activity Status: Closed
Completion Notes: LETTER TO MCINTOSH FOR SIGNATURE. SURFA LETTER.
10/13/2005 Legacy Activity Griffin, Tom
Activity Name: TECHNICAL REVIEW Activity Status: Closed
Completion Notes: DRF CONFIRM DISCHARGE. NO EVIDENCE OF EXCESSIVE STAINING DURING TXI OF 7/26/05
10/05/2005 Legacy Activity Allen, Eleanor
Activity Name: MONITORING DATA RESULTS REVIEWED Activity Status: Closed
Completion Notes: SPILL BUCKET CLOSURE
09/26/2005 Legacy Activity Griffin, Tom
Activity Name: DISCHARGE CONFIRMED - 770 CU REQUIRED Activity Status: Closed
Completion Notes: DATE OF DISCHARGE CONFIRMATION 9/26/05
08/02/2005 Legacy Activity Allen, Eleanor
Activity Name: TANK INSTALLATION - FINAL INSPECTION Activity Status: Closed
Completion Notes: SPILL CONTAINMENT INSTALL - HYDRO TEST ON CONTAINMENTS, OK.
07/28/2005 Legacy Activity Allen, Eleanor
Activity Name: TANK INSTALLATION - INITIAL INSPECTION Activity Status: Closed
Completion Notes: INSTALLED 4 OPW SPILL CONTAINMENT DUCKETS AROUND FILLS - CONCRETE TO BE POURED.
07/26/2005 Legacy Activity Allen, Eleanor
Activity Name: TANK CLOSURE INSPECTION Activity Status: Closed
Completion Notes: REMOVED 4 EA. SPILL BUCKETS.
07/26/2005 Legacy Activity Griffin, Tom
Activity Name: INCIDENT REPORT FORM RECEIVED Activity Status: Closed
Completion Notes: SPILL BUCKET REPLACEMENT DUE TO FAILED INTEGRITY TESTING.
03/31/2005 Legacy Activity Allen, Eleanor
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
10/17/2004 Legacy Activity Allen, Eleanor
Activity Name: LETTER Activity Status: Closed
Completion Notes: SURFA LTR - CONTAMINATION DISCOVERY.
04/24/2004 Legacy Activity Torsanko, Grace
Activity Name: TANK COMPLIANCE RE-INSPECTION Activity Status: Closed
03/17/2004 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 700(1)(c)3
03/17/2004 Legacy Activity Torsanko, Grace
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
03/05/2004 Legacy Activity Loeffler, Kathe
Activity Name: TELEPHONE CONVERSATION Activity Status: Closed
03/05/2004 Legacy Activity Loeffler, Kathe
Activity Name: RETURN TO COMPLIANCE FROM FORMAL ENFORCEMENT Activity Status: Closed
02/26/2004 Legacy Activity Loeffler, Kathe
Activity Name: INKIND PROJECT COMPLETED Activity Status: Closed
02/24/2004 Legacy Activity Loeffler, Kathe
Activity Name: PENALTY RECEIVED Activity Status: Closed
12/09/2003 Legacy Activity Loeffler, Kathe
Activity Name: SHORT FORM CONSENT ORDER EXECUTED Activity Status: Closed
11/13/2003 Legacy Activity Loeffler, Kathe
Activity Name: DRAFT CONSENT ORDER ISSUED Activity Status: Closed
11/12/2003 Legacy Activity Loeffler, Kathe
Activity Name: INKIND PROJECT PROPOSAL APPROVED Activity Status: Closed
10/30/2003 Legacy Activity Loeffler, Kathe
Activity Name: INKIND PROJECT PROPOSAL RECEIVED Activity Status: Closed
10/08/2003 Legacy Activity Torsanko, Grace
Activity Name: TANK COMPLIANCE RE-INSPECTION Activity Status: Closed
08/26/2003 Legacy Activity Loeffler, Kathe
Activity Name: MEETING Activity Status: Closed
07/21/2003 Legacy Activity Loeffler, Kathe
Activity Name: TELEPHONE CONVERSATION Activity Status: Closed
07/18/2003 Legacy Activity Loeffler, Kathe
Activity Name: TELEPHONE CONVERSATION Activity Status: Closed
06/09/2003 Violation Closed Torsanko, Grace
Significance: SNC-B Status: Closed
Rule: 600(1)(d)
06/09/2003 Legacy Activity Torsanko, Grace
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
06/09/2003 Violation Closed Torsanko, Grace
Significance: SNC-B Status: Closed
Rule: 500(2)(d)2
06/09/2003 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 450(2)(a)
06/09/2003 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 700(1)(c)1
06/09/2003 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 820(2)(c)
06/09/2003 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 710(2)
06/09/2003 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 600(1)(e)
04/25/2002 Legacy Activity Torsanko, Grace
Activity Name: RESPONSE RECEIVED BY DEPARTMENT Activity Status: Closed
03/27/2002 Violation Closed Torsanko, Grace
Significance: Minor Status: Closed
Rule: 640(3)(d)
03/27/2002 Legacy Activity Torsanko, Grace
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
06/14/2001 Legacy Activity Unknown, User
Activity Name: TANK COMPLIANCE RE-INSPECTION Activity Status: Closed
02/22/2001 Legacy Activity Cummings, Constance C.
Activity Name: NON-COMPLIANCE LETTER ISSUED Activity Status: Closed
02/20/2001 Violation Closed Cummings, Constance C.
Significance: Minor Status: Closed
Rule: 510(1)(d)
02/20/2001 Legacy Activity Cummings, Constance C.
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
Completion Notes: SHEAR VALVES NOT PROPERLY ANCHORED
02/24/2000 Legacy Activity Cummings, Constance C.
Activity Name: TANK COMPLIANCE RE-INSPECTION Activity Status: Closed
02/24/2000 Legacy Activity Cummings, Constance C.
Activity Name: COMPLIANCE W/O FORMAL ENFORCEMENT ACTION Activity Status: Closed
02/03/2000 Legacy Activity Cummings, Constance C.
Activity Name: RESPONSE RECEIVED BY DEPARTMENT Activity Status: Closed
01/03/2000 Legacy Activity Cummings, Constance C.
Activity Name: WARNING LETTER ISSUED Activity Status: Closed
11/17/1999 Violation Closed Cummings, Constance C.
Significance: Minor Status: Closed
Rule: 600(1)(b); 640(1)(c)
11/17/1999 Violation Closed Cummings, Constance C.
Significance: SNC-B Status: Closed
Rule: 600(1)(f)
11/17/1999 Legacy Activity Cummings, Constance C.
Activity Name: TANK ANNUAL COMPLIANCE INSPECTION Activity Status: Closed
Completion Notes: NO SITE SUITABILITY OR RDRL
11/17/1999 Legacy Activity Cummings, Constance C.
Activity Name: NON-COMPLIANCE LETTER ISSUED Activity Status: Closed
Completion Notes: .600(1)F .600(1)B