Report Run Date: 04/27/2025        Last Data Refresh: 04/26/2025        Report Generated from DOPPLER
 
Facility ID: 9810951
Facility Name: BAHIA HONDA STATE PARK
 
08/08/2023 Enforcement Tracking Activity Dolan, Judy F.
Activity Status: Open
08/08/2023 Enforcement Referral Activity Shanberg, Vincent J
Activity Result: Accepted Activity Status: Closed
Activity Closed Date: 08/08/2023
Events:
Event Type: Activity/Document was acknowledged on this date Date: 08/08/2023
Comment: Acknowledged and Assigned by Judy F. Dolan
Events:
Event Type: Activity has been assigned Date: 08/08/2023
Comment: Assigned to Judy F. Dolan
Events:
Event Type: Activity has been finished Date: 08/08/2023
Comment: Finished
Events:
Event Type: Activity has been submitted for approval Date: 08/08/2023
Comment: Submitted for approval by: Vincent J Shanberg: Submitting facility for enforcement tracking
Events:
Event Type: Activity/Document was accepted on this date Date: 08/08/2023
Comment: Accepted by Judy F. Dolan: Assigning to Vincent Shanberg.
Comments:
Comment Date: 08/08/2023 User: SHANBERG_V
Description: Submitting facility for enforcement tracking
05/24/2023 Editable Letter Activity Shanberg, Vincent J
Activity Title: Compliance Assistance Offer Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 08/08/2023
Comment: Finished
Events:
Event Type: Document has been sent Date: 05/24/2023
Comment: Sent
Attachments:
Attachment Date: 08/08/2023 User: SHANBERG_V
Description: CAOL_BAHIA HONDA STATE PARK_9810951
View Attachment
05/18/2023 Violation Open Shanberg, Vincent J
Significance: Minor Status: Open
Criteria ID: 7043
Rule: 62-762.501(2)(f)2
05/18/2023 Violation Open Shanberg, Vincent J
Significance: Minor Status: Open
Criteria ID: 7041
Rule: 62-762.501(2)(e)3, 62-762.501(2)(e)3.a, 62-762.501(2)(e)3.b, 62-762.501(2)(e)4, 62-762.502(2)(e)4, 62-762.502(2)(e)4.a, 62-762.502(2)(e)4.b, 62-762.502(2)(e)5
05/18/2023 Violation Open Shanberg, Vincent J
Significance: Minor Status: Open
Criteria ID: 7072
Rule: 62-762.601(7), 62-762.602(7)
05/18/2023 Violation Open Shanberg, Vincent J
Significance: SNC-B Status: Open
Criteria ID: 7040
Rule: 62-762.501(2)(e), 62-762.501(2)(e)1, 62-762.501(2)(e)2, 62-762.501(2)(e)2.a, 62-762.501(2)(e)2.b, 62-762.501(2)(e)2.c, 62-762.501(2)(e)2.d, 62-762.502(2)(e), 62-762.502(2)(e)1, 62-762.502(2)(e)2, 62-762.502(2)(e)3, 62-762.502(2)(e)3.a, 62-762.502(2)(e)3.b, 62-762.502(2)(e)3.c, 62-762.502(2)(e)3.d, 62-762.502(2)(e)5
05/04/2023 Site Inspection Activity Closed Shanberg, Vincent J
Activity Result: Major Out of Compliance Activity Status: Closed
On-Site Start Date: 05/04/2023
Activity Closed Date: 05/24/2023 Activity Closed By: SHANBERG_V
Events:
Event Type: Activity has been finished Date: 05/24/2023
Comment: Finished
Comments:
Comment Date: 05/18/2023 User: SHANBERG_V
Description: A Routine Compliance Inspection was conducted on May 4, 2023 with Laura Pardal, Environmental Specialist II , Vincent Shanberg Environmental Specialist III, Elsa Portanyi Environmental Specialist II, with the Florida Department of Environmental Protection, Marathon Office , and Mark Tuschel, Park Services Specialist at Bahia Honda State Park. The facility has one (1) 1000 Compartmented aboveground storage tank storing diesel and gasoline fuel and (2) tank dispensers. Release detections provided by a Kreuger Gauge. Monthly inspection for release detection was conducted on March 2020 to April 2023 The facility has an exemption as a state government entity for Finical reasonability. Three years of monthly inspections are dated from March 2020 to April 2023. The following violation was cited: The facility is missing annual operability testing documentation for overfill protection for 2021, 2022, and 2023. Facility was missing annual operability testing of release detection system for 2021, 2022, and 2023. Failure to install overfill protection. The facility is missing the API color-symbol system on the fill box covers for the AST. A copy of the report will be sent via electronic mail to Mark Tuschel (mark.tuschel@floridadep.gov) and Cassandra Meadows (cassandra.meadows@dep.state.fl.us).
04/29/2020 Editable Letter Activity Winkler, Michael G.
Activity Title: In Compliance Letter Activity Status: Closed
Events:
Event Type: Document has been sent Date: 04/29/2020
Comment: Sent
Events:
Event Type: Activity has been finished Date: 04/29/2020
Comment: Finished
Attachments:
Attachment Date: 04/29/2020 User: WINKLER_MG_1
Description: 2020-04-29 ICL sent to Don Bergeron
View Attachment
04/28/2020 Site Inspection Activity Closed Winkler, Michael G.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 04/28/2020
Activity Closed Date: 04/29/2020 Activity Closed By: WINKLER_MG_1
Events:
Event Type: Activity has been finished Date: 04/29/2020
Comment: Finished
Comments:
Comment Date: 04/29/2020 User: WINKLER_MG_1
Description: NOTE: No signature capture due to CORVID-19. Met with Don Bergeron and Corliss Castro at the facility. This facility has a single 1000 gallon double walled Convault AST compartmented with Diesel and Regular Unleaded for facility equipment and vehicles. The system was inspected. Records were reviewed to include a current registration placard, monthly release detection records, and annual testing of the Krueger gauge interstice monitoring device. Annual testing of the overfill prevention valve was discussed; its testing is identified as an Area of Concern. No violations noted this date.
12/15/2017 Site Inspection Activity Closed Winkler, Michael G.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 12/15/2017
Activity Closed Date: 12/15/2017 Activity Closed By: WINKLER_MG_1
Events:
Event Type: Activity has been finished Date: 12/15/2017
Comment: Finished
Comments:
Comment Date: 12/15/2017 User: WINKLER_MG_1
Description: This is a Double walled AST compartmented with rec90 and diesel, and a single kreuger gauge for the interstice. The shop, AST, and surrounding area had about 3 feet of water from the storm, but Mr. Tuschel was able to secure the records higher up. The AST was checked post Irma and had no water in the tanks. Mr. Tuschel showed me a slight crack in one of the dispensing hoses, and had new hoses onsite ready to for replacement. A reminder of the new Rule. Check the Krueger leak sensor for operability at least once a year, and record the test data on your monthly logbook. No violations noted this date.
12/15/2017 Editable Letter Activity Winkler, Michael G.
Activity Title: In Compliance Letter Activity Status: Closed
Events:
Event Type: Activity has been finished Date: 12/15/2017
Comment: Finished
Comments:
Comment Date: 12/15/2017 User: WINKLER_MG_1
Description: Sent via US mail this date.
Attachments:
Attachment Date: 12/15/2017 User: WINKLER_MG_1
Description: 2017-12-15 Bahia Honda State Park ICL
View Attachment
03/05/2015 Site Inspection Activity Closed Winkler, Michael G.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 03/05/2015
Activity Closed Date: 03/06/2015 Activity Closed By: WINKLER_MG_1
Events:
Event Type: Activity has been finished Date: 03/06/2015
Comment: Finished
Comments:
Comment Date: 03/06/2015 User: WINKLER_MG_1
Description: No violations noted. A slight drip at the gas nozzle has been identified and repairs are in process.
12/18/2012 Attachment Winkler, Michael G.
12/18/2012 Site Inspection Activity Closed Winkler, Michael G.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 12/18/2012
Activity Closed Date: 12/18/2012 Activity Closed By: WINKLER_MG_1
Events:
Event Type: Activity has been finished Date: 12/18/2012
Comment: Finished
Comments:
Comment Date: 12/18/2012 User: WINKLER_MG_1
Description: 1000 gallon DW Convault compartmented 600/400 gas/dsl. No deficiencies noted.
12/20/2011 Site Inspection Activity Closed Winkler, Michael G.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 12/20/2011
Activity Closed Date: 12/20/2011 Activity Closed By: WINKLER_MG_1
Events:
Event Type: Activity has been finished Date: 12/20/2011
Comment: Finished
Comments:
Comment Date: 12/20/2011 User: WINKLER_MG_1
Description: No violations noted this date. Facility is in compliance.
08/06/2010 Editable Letter Activity Lichtler, Gary B.
Activity Title: 1st Non-Compliance Letter Activity Status: Closed
Events:
Event Type: Document has been sent Date: 08/06/2010
Comment: Sent on Fri Aug 06 00:00:00 EDT 2010
Events:
Event Type: Activity has been finished Date: 08/06/2010
Comment: Finished
Attachments:
Attachment Date: 08/06/2010 User: LICHTLER_GB_1
Description: 2010-08-06 NCL
View Attachment
07/29/2010 Violation Closed Lichtler, Gary B.
Significance: Minor Status: Closed
Criteria ID: 2110
Rule: 62-762.701(1)(a)1.a., 62-762.701(1)(a)1.b., 62-762.701(1)(a)1.c., 62-762.701(1)(a)1.d.
07/29/2010 Site Inspection Activity Closed Lichtler, Gary B.
Activity Result: Minor Out of Compliance Activity Status: Closed
On-Site Start Date: 07/29/2010
Activity Closed Date: 08/06/2010 Activity Closed By: LICHTLER_GB_1
Events:
Event Type: Activity has been finished Date: 08/06/2010
Comment: Finished
Comments:
Comment Date: 07/29/2010 User: LICHTLER_GB_1
Description: Email to eric.kiefer@dep.state.fl.us
07/29/2010 Violation Closed Lichtler, Gary B.
Significance: Minor Status: Closed
Criteria ID: 2066
Rule: 62-762.601(1)(a)2.
Comments: Mark this as out of compliance if release detection systems are not functioning or not maintained properly. The inspector will have to know what release detection components have been installed at the facility. Furthermore, develop a library of installation and system operation specifications. These documents will assist you in determining calibration/maintenance as required by the manufacturer. Additional guidance can be found in the Appendix sections of the USEPA "List of Leak Detection Evaluations for Underground Storage Tank Systems" and the DEP Master Equipment List. Installations - have the release detection components been function tested? Just because a piece of equipment is new out of the box does not mean it is fully functional. Have it demonstrated! Calibration/Maintenance - the facility must provide documentation attesting to these operability tests. Operation - The RDRL must be developed, and the facility personnel must be knowledgeable of all the components of the release detection system. Theoretically, they should be able to demonstrate to you how they monitor the release detection system. See rule 62-762.701(1)(c)3
07/29/2010 Violation Closed Lichtler, Gary B.
Significance: Minor Status: Closed
Criteria ID: 2133
Rule: 62-762.711(2)(a), 62-762.711(2)(b), 62-762.711(2)(c), 62-762.711(2)(d), 62-762.711(2)(e), 62-762.711(2)(f), 62-762.711(2)(g), 62-762.711(2)(h)
Comments: If the problem involves failure to perform according to the standards in each of the following areas, then note these items in addition to the paperwork for this rule: a. and g. Inventory - rules 62-762.641(3)(b)1-2, 62-762.641(3)(b)3 and 62-762.701(1)(c)6 b. Repair, operation, and maintenance - rules 62-762.701(1)(a)1, 62-762.701(1)(a)4, 62-762.701(1)(a)6 and 62-762.701(1)(c)3 c. Release detection - rules 62-762.601(1)(e), 62-762.601(2)(g), 62-762.611(2)(b), 62-762.611(3)(b), 62-762.611(3)(d)2, 62-762.641(2)(c) and 62-762.641(2)(e) d. Release detection response level descriptions - rules 62-762.601(1)(b) and 62-762.641(1)(c) e. Tightness, pressure, and breach of integrity tests - rules 62-762.611(3)(a)1 and 62-762.641(1)(a) f. Financial responsibility - rule 62-762.401(3) g. Repairs and replacements - rule 62-762.701(1)(a)6 The following are not issues for this rule: Rules 62-762.451(1)(a)2, 62-762.451(1)(a)3 and 62-762.451(1)(a)4 are verbal notices of activities that may also be written Rule 62-762.451(1)(b) is a registration issue Rules 62-762.451(2)(a), 62-762.451(3)(a) and 62-762.451(3)(b) are INF/DRF reporting issues Rules 62-762.601(1)(a)3 and 62-762.601(1)(f) are covered by 62-762.711(3) Anything with cathodic protection is covered by 62-762.711(3)
07/29/2010 Violation Closed Lichtler, Gary B.
Significance: Minor Status: Closed
Criteria ID: 2003
Rule: 62-762.401(2)(a)6.
Comments: All federal facilities with USTs will have a placard. Federal facilities with only ASTs will not have a placard. Per FS 376.3077, "It is unlawful for any owner, operator, or supplier to pump or otherwise deposit any motor fuel into a tank required to be registered under section 376.303 FS, unless proof of valid registration is displayed on such tank itself or the dispensing or measuring device connected thereto or, where appropriate, in the office or kiosk of the facility where the tank is located." Penalties can be assessed to the facility owner for failure to properly register tank systems. Note that penalties can be assessed to the supplier that delivers motor fuel to an unregistered facility. Check the details on the placard. Do they agree with the location you are inspecting? Owners of multiple facilities may switch placards by mistake. Placards are not always issued or received in a timely manner at the change of year period (June and July). Provide the DEP Tallahassee phone number to the facility so they may resolve problems (850) 487-7077; (850) 488-3935. Check STCM in the registration/placard section for the date that the payment was made and the date that the placard was issued. The location of the placard in plain view can be subjective in interpretation: a. For vehicular fuel facilities, plain view is meant to allow the transport delivery driver to view the placard prior to delivering fuel. b. A legal definition is an exception to the general requirement of a valid search warrant to legitimize a search or seizure; a search implies prying into hidden places, and it is not a search to observe what is open to view.
08/04/2009 Editable Letter Activity Smith, Ryan R.
Activity Title: 1st Non-Compliance Letter Activity Status: Closed
07/31/2009 Violation Closed Smith, Ryan R.
Significance: Minor Status: Closed
Criteria ID: 2133
Rule: 62-762.711(2)(a), 62-762.711(2)(b), 62-762.711(2)(c), 62-762.711(2)(d), 62-762.711(2)(e), 62-762.711(2)(f), 62-762.711(2)(g), 62-762.711(2)(h)
Comments: If the problem involves failure to perform according to the standards in each of the following areas, then note these items in addition to the paperwork for this rule: a. and g. Inventory - rules 62-762.641(3)(b)1-2, 62-762.641(3)(b)3 and 62-762.701(1)(c)6 b. Repair, operation, and maintenance - rules 62-762.701(1)(a)1, 62-762.701(1)(a)4, 62-762.701(1)(a)6 and 62-762.701(1)(c)3 c. Release detection - rules 62-762.601(1)(e), 62-762.601(2)(g), 62-762.611(2)(b), 62-762.611(3)(b), 62-762.611(3)(d)2, 62-762.641(2)(c) and 62-762.641(2)(e) d. Release detection response level descriptions - rules 62-762.601(1)(b) and 62-762.641(1)(c) e. Tightness, pressure, and breach of integrity tests - rules 62-762.611(3)(a)1 and 62-762.641(1)(a) f. Financial responsibility - rule 62-762.401(3) g. Repairs and replacements - rule 62-762.701(1)(a)6 The following are not issues for this rule: Rules 62-762.451(1)(a)2, 62-762.451(1)(a)3 and 62-762.451(1)(a)4 are verbal notices of activities that may also be written Rule 62-762.451(1)(b) is a registration issue Rules 62-762.451(2)(a), 62-762.451(3)(a) and 62-762.451(3)(b) are INF/DRF reporting issues Rules 62-762.601(1)(a)3 and 62-762.601(1)(f) are covered by 62-762.711(3) Anything with cathodic protection is covered by 62-762.711(3)
07/31/2009 Site Inspection Activity Closed Smith, Ryan R.
Activity Result: Minor Out of Compliance Activity Status: Closed
On-Site Start Date: 07/31/2009
Activity Closed Date: 08/04/2009 Activity Closed By: SMITH_RR
07/31/2009 Violation Closed Smith, Ryan R.
Significance: Minor Status: Closed
Criteria ID: 2110
Rule: 62-762.701(1)(a)1.a., 62-762.701(1)(a)1.b., 62-762.701(1)(a)1.c., 62-762.701(1)(a)1.d.
03/09/2009 Site Inspection Activity Closed Smith, Ryan R.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 03/09/2009
Activity Closed Date: 03/10/2009 Activity Closed By: SMITH_RR
Comments:
Comment Date: 03/09/2009 User: SMITH_RR
Description: Original installation inspection deleted by computer error.
Comments:
Comment Date: 03/10/2009 User: SMITH_RR
Description: No fuel in tank yet. Therefor no release detection results necessary
03/09/2009 Site Inspection Activity Closed Smith, Ryan R.
Activity Result: In Compliance Activity Status: Closed
On-Site Start Date: 03/09/2009
Activity Closed Date: 03/10/2009 Activity Closed By: SMITH_RR
Comments:
Comment Date: 03/09/2009 User: SMITH_RR
Description: Original installation inspection deleted by computer error.
Comments:
Comment Date: 03/10/2009 User: SMITH_RR
Description: No fuel in tank yet. Therefor no release detection results necessary