Permitting Application with Events Details


This data is current as of: Sunday, June 16, 2024


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   CALHOUN
  Permit Type:   Water - ERP Modifications
  Permit Processor:   ALYSSA TESSIER
  Application Number:   0395572-002-EM
  Site Name:   CHIPOLA RIVER SOLAR ENERGY CENTER
  Applicant Name:   SARAH TERRELL
  Applicant Company:   FLORIDA POWER & LIGHT COMPANY
  Agency Action:   Pending
  Link to Department’s Application File:   CHIPOLA RIVER SOLAR ENERGY CENTER
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/03/2024   05/03/2024
  The Department is reviewing the permit application to determine if it contains all required information.   05/03/2024   05/17/2024
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP).   05/03/2024   05/05/2024
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   05/03/2024   05/16/2024
  The Department is determining if the activity affects State Lands.   05/03/2024   05/05/2024
  The Department is providing notice of application to commenting agencies for review.   05/03/2024  
  The Department is conducting a site investigation, if required   05/03/2024   05/16/2024
  The Department is waiting for additional information from the permit applicant.   05/17/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   CALHOUN
  Permit Type:   Water - ERP Modifications
  Permit Processor:   ALYSSA TESSIER
  Application Number:   0435280-002-EM
  Site Name:   FPL TENMILE CREEK SOLAR ENERGY CENTER
  Applicant Name:   RYAN DESUTTER
  Applicant Company:   FLORIDA POWER & LIGHT COMPANY
  Agency Action:   Pending
  Link to Department’s Application File:   FPL TENMILE CREEK SOLAR ENERGY CENTER
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/08/2024   05/08/2024
  The Department is reviewing the permit application to determine if it contains all required information.   05/08/2024   05/23/2024
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP).   05/08/2024   05/10/2024
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   05/08/2024   05/22/2024
  The Department is determining if the activity affects State Lands.   05/08/2024   05/10/2024
  The Department is providing notice of application to commenting agencies for review.   05/08/2024  
  The Department is conducting a site investigation, if required   05/08/2024   05/22/2024
  The Department is waiting for additional information from the permit applicant.   05/23/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   CALHOUN
  Permit Type:   Water - ERP Modifications
  Permit Processor:   RICHARD EARLE
  Application Number:   0437483-002-EM
  Site Name:   FPL SAND PINE SOLAR ENERGY CENTER
  Applicant Name:   RYAN DESUTTER
  Applicant Company:   FLORIDA POWER & LIGHT COMPANY
  Agency Action:   Pending
  Link to Department’s Application File:   FPL SAND PINE SOLAR ENERGY CENTER
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/06/2024   05/06/2024
  The Department is reviewing the permit application to determine if it contains all required information.   05/06/2024   05/15/2024
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP).   05/06/2024  
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   05/06/2024  
  The Department is determining if the activity affects State Lands.   05/06/2024   05/08/2024
  The Department is providing notice of application to commenting agencies for review.   05/06/2024   05/07/2024
  The Department is conducting a site investigation, if required   05/06/2024  
  The Department is waiting for additional information from the permit applicant.   05/15/2024  
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands.   05/08/2024   06/04/2024
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)