Permitting Application Under Review
|
  FDEP Office: |
  MINING AND MINERALS REGULATION |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Modifications |
  Permit Processor: |
  JESSIE L MASSEY |
  Application Number: |
  0269764-010-EM |
  Site Name: |
  FARABEE MINE & SHELL, LLC |
  Applicant Name: |
  JAMES WEEK |
  Applicant Company: |
  FARABEE MINE & SHELL LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FARABEE MINE & SHELL, LLC |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/03/2024 |
  12/03/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/03/2024 |
  01/07/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/03/2024 |
  12/03/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  12/03/2024 |
  01/14/2025 |
  The Department is determining if the activity affects State Lands. |
  12/03/2024 |
  12/05/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/03/2024 |
  12/04/2024 |
  The Department is conducting a site investigation, if required |
  12/03/2024 |
  12/03/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/07/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Injection Well Operation Permit |
  Permit Processor: |
  DANIEL WARMKE |
  Application Number: |
  0271367-009-UO |
  Site Name: |
  CHARLOTTE CO. BURNT STORE WWTP & WTP CLASS I UIC |
  Applicant Name: |
  DAVE WATSON |
  Applicant Company: |
  CHARLOTTE COUNTY UTILITIES DEPARTMENT |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/26/2024 |
  01/26/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/26/2024 |
  01/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/26/2024 |
  02/03/2025 |
  The Department is making an outcome determination regarding the permit application. |
  01/26/2024 |
  02/03/2025 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  02/03/2025 |
  02/03/2025 |
  The Department published the draft Permit notice. |
  02/03/2025 |
  02/10/2025 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  02/10/2025 |
  03/13/2025 |
  The Department's intent regarding the permit application was published. |
  03/13/2025 |
  03/16/2025 |
  The permit was issued. |
  03/16/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  LINDSAY FURR |
  Application Number: |
  0273798-009-SFI |
  Site Name: |
  FLORIDA DEPT OF TRANSPORTATION / SR 31 & CR 74 |
  Applicant Name: |
  NICOLE MONIES |
  Applicant Company: |
  FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT) |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA DEPT OF TRANSPORTATION / SR 31 & CR 74 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/15/2023 |
  02/15/2023 |
  The Department is conducting a site investigation, if required |
  02/15/2023 |
  05/09/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/15/2023 |
  03/28/2023 |
  The Department is waiting for additional information from the permit applicant. |
  03/28/2023 |
  01/03/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/03/2024 |
  01/03/2024 |
  The Department published the public notice of the application after determining it contained all required items. |
  01/03/2024 |
  01/05/2024 |
  The Department is waiting for the completion of the required comment period prior to continuing the permit application process. |
  01/05/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0284434-010-EI |
  Site Name: |
  GULF & PALMS ESTATES ASSO / 411912429001 / 080343085 / (R) |
  Applicant Name: |
  DANIEL LYNCH |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GULF & PALMS ESTATES ASSO / 411912429001 / 080343085 / (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/22/2023 |
  02/22/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/22/2023 |
  03/22/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/22/2023 |
  02/23/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/22/2023 |
  02/23/2023 |
  The Department is determining if the activity affects State Lands. |
  02/22/2023 |
  02/23/2023 |
  The Department is conducting a site investigation, if required |
  02/22/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/22/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0285091-007-EE |
  Site Name: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
  Applicant Name: |
  MARY DEWITT |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/11/2022 |
  05/11/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/11/2022 |
  06/10/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/11/2022 |
  05/13/2022 |
  The Department is determining if the activity affects State Lands. |
  05/11/2022 |
  05/13/2022 |
  The Department is waiting for additional information from the permit applicant. |
  06/10/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0285091-009-EG |
  Site Name: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
  Applicant Name: |
  KAREN MEEUWSEN |
  Applicant Company: |
  KAREN E MEEUWSEN TRUSTEE |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/02/2025 |
  01/02/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/02/2025 |
  01/29/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/02/2025 |
  01/02/2025 |
  The Department is determining if the activity affects State Lands. |
  01/02/2025 |
  01/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/02/2025 |
  01/02/2025 |
  The Department is conducting a site investigation, if required |
  01/02/2025 |
  01/02/2025 |
  The Department is waiting for additional information from the permit applicant. |
  01/29/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0285091-010-EE |
  Site Name: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
  Applicant Name: |
  MARYANN SANFORD |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ENGLEWOOD BEACH CONDO ASSN / 411912653000 / BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/13/2025 |
  03/13/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/13/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/13/2025 |
  03/14/2025 |
  The Department is determining if the activity affects State Lands. |
  03/13/2025 |
  03/14/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/13/2025 |
  03/14/2025 |
  The Department is conducting a site investigation, if required |
  03/13/2025 |
  03/14/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0286673-005-NPR |
  Site Name: |
  CHARLOTTE CO UTILITIES / EAST PORT WTP / 402319100001 / UPLD |
  Applicant Name: |
  |
  Applicant Company: |
  CHARLOTTE CO UTILITIES |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE CO UTILITIES / EAST PORT WTP / 402319100001 / UPLD |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/30/2024 |
  01/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/30/2024 |
  02/15/2024 |
  The Department is conducting a site investigation, if required |
  01/30/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  02/15/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Mangrove Exemptions |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0293231-003-ME |
  Site Name: |
  PALM HARBOR MARINA (SOUTH) / 412033203002 /412033205001 |
  Applicant Name: |
  DONALD BUTLER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PALM HARBOR MARINA (SOUTH) / 412033203002 /412033205001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/26/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0293231-004-EE |
  Site Name: |
  PALM HARBOR MARINA (SOUTH) / 412033203002 /412033205001 |
  Applicant Name: |
  MEGAN NICHOLS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PALM HARBOR MARINA (SOUTH) / 412033203002 /412033205001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/01/2025 |
  04/01/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/01/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/01/2025 |
  04/03/2025 |
  The Department is determining if the activity affects State Lands. |
  04/01/2025 |
  04/03/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  04/01/2025 |
  04/03/2025 |
  The Department is conducting a site investigation, if required |
  04/01/2025 |
  04/03/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  JAMES DODSON |
  Application Number: |
  0294077-002-UC |
  Site Name: |
  TOWN & COUNTRY UTILITIES UIC |
  Applicant Name: |
  WILLIAM VANDER MAY |
  Applicant Company: |
  TOWN AND COUNTRY UTILITIES |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/03/2024 |
  09/03/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/03/2024 |
  09/24/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/03/2024 |
  10/23/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/23/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Drinking Water Distribution System General Permit |
  Permit Processor: |
  RACHEL BROWN |
  Application Number: |
  0294514-077-DSGP |
  Site Name: |
  TOWN & COUNTRY UTILITY (AKA BABCOCK RANCH) - PWS 5084116 |
  Applicant Name: |
  John Broderick |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/24/2025 |
  03/24/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/24/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0294849-002-EE |
  Site Name: |
  HESS, DOUGLAS /412005383016/CANAL |
  Applicant Name: |
  DOUG HESS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HESS, DOUGLAS /412005383016/CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/01/2025 |
  04/01/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/01/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/01/2025 |
  04/03/2025 |
  The Department is determining if the activity affects State Lands. |
  04/01/2025 |
  04/03/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  04/01/2025 |
  04/03/2025 |
  The Department is conducting a site investigation, if required |
  04/01/2025 |
  04/03/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0298329-012-EE |
  Site Name: |
  WINDWARD STUMP PASS OWNER LLC / 080345225 |
  Applicant Name: |
  JOHANNA SHIFFLETTE |
  Applicant Company: |
  HANS WILSON & ASSOCIATES, INC. |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WINDWARD STUMP PASS OWNER LLC / 080345225 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/24/2022 |
  05/24/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/24/2022 |
  05/24/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/24/2022 |
  05/26/2022 |
  The Department is determining if the activity affects State Lands. |
  05/24/2022 |
  05/26/2022 |
  The Department is conducting a site investigation, if required |
  05/24/2022 |
  06/23/2022 |
  The Department is waiting for additional information from the permit applicant. |
  05/24/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0298894-013-EE |
  Site Name: |
  LEGACY HARBOR BELLE LLC / 412319234001 / (R) |
  Applicant Name: |
  |
  Applicant Company: |
  LEGACY HARBOR BELLE LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LEGACY HARBOR BELLE LLC / 412319234001 / (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/01/2023 |
  12/01/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/01/2023 |
  12/27/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/01/2023 |
  12/03/2023 |
  The Department is determining if the activity affects State Lands. |
  12/01/2023 |
  12/03/2023 |
  The Department is conducting a site investigation, if required |
  12/01/2023 |
  12/06/2023 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  12/03/2023 |
  12/08/2023 |
  The Department is waiting for additional information from the permit applicant. |
  12/27/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0299212-001-EI |
  Site Name: |
  SHORT, RODNEY / 412028379003 / |
  Applicant Name: |
  RODNEY SHORT |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SHORT, RODNEY / 412028379003 / |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/04/2023 |
  12/04/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/04/2023 |
  12/20/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/04/2023 |
  12/05/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  12/04/2023 |
  12/05/2023 |
  The Department is determining if the activity affects State Lands. |
  12/04/2023 |
  12/05/2023 |
  The Department is conducting a site investigation, if required |
  12/04/2023 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  12/05/2023 |
  12/07/2023 |
  The Department is waiting for additional information from the permit applicant. |
  12/20/2023 |
  01/17/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/17/2024 |
  02/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  02/15/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0299739-006-EE |
  Site Name: |
  POTTER, EMMET / CRAVEN, DAN / 412017455003 / LEMON BAY (R) |
  Applicant Name: |
  EMMET POTTER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  POTTER, EMMET / CRAVEN, DAN / 412017455003 / LEMON BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/09/2021 |
  06/09/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/09/2021 |
  06/09/2021 |
  The Department is conducting a site investigation, if required |
  06/09/2021 |
  07/09/2021 |
  The Department is determining if the activity affects State Lands. |
  06/09/2021 |
  06/11/2021 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/09/2021 |
  06/11/2021 |
  The Department is waiting for additional information from the permit applicant. |
  06/09/2021 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0299765-003-EE |
  Site Name: |
  PLACIDA HARBOUR CLUB INC / 081387965 / LGI DOCK 61 |
  Applicant Name: |
  RON COGHLIN |
  Applicant Company: |
  PLACIDA HARBOUR CLUB |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PLACIDA HARBOUR CLUB INC / 081387965 / LGI DOCK 61 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/03/2025 |
  01/03/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/03/2025 |
  01/31/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/03/2025 |
  01/05/2025 |
  The Department is determining if the activity affects State Lands. |
  01/03/2025 |
  01/05/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/03/2025 |
  01/05/2025 |
  The Department is conducting a site investigation, if required |
  01/03/2025 |
  01/07/2025 |
  The Department is waiting for additional information from the permit applicant. |
  01/31/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0300951-003-EE |
  Site Name: |
  WALKER, EVERETT/ 412006451012 / LEMON BAY |
  Applicant Name: |
  EVERETT WALKER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WALKER, EVERETT/ 412006451012 / LEMON BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/10/2025 |
  03/10/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/10/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/10/2025 |
  03/11/2025 |
  The Department is determining if the activity affects State Lands. |
  03/10/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  03/10/2025 |
  03/11/2025 |
  The Department is conducting a site investigation, if required |
  03/10/2025 |
  03/11/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0304187-002-EI |
  Site Name: |
  1937 BEACH ROAD PROPERTIES LLC / DRINNEN / 411912254007 (R) |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  1937 BEACH ROAD PROPERTIES LLC / DRINNEN / 411912254007 (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/30/2021 |
  11/30/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/30/2021 |
  12/22/2021 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/30/2021 |
  12/02/2021 |
  The Department is determining if the activity affects State Lands. |
  11/30/2021 |
  12/02/2021 |
  The Department is waiting for additional information from the permit applicant. |
  12/22/2021 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0304187-003-EE |
  Site Name: |
  1937 BEACH ROAD PROPERTIES LLC / DRINNEN / 411912254007 (R) |
  Applicant Name: |
  MICHAEL STIPP |
  Applicant Company: |
  1937 BEACH ROAD PROPERTIES LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  1937 BEACH ROAD PROPERTIES LLC / DRINNEN / 411912254007 (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/02/2025 |
  04/02/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/02/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/02/2025 |
  04/03/2025 |
  The Department is determining if the activity affects State Lands. |
  04/02/2025 |
  04/03/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  04/02/2025 |
  04/03/2025 |
  The Department is conducting a site investigation, if required |
  04/02/2025 |
  04/03/2025 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  04/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0304722-004-EE |
  Site Name: |
  KF & LF PROPERTIES / FARLOWS / 080346955 / 412005332001 (R) |
  Applicant Name: |
  MATTHEW KELLY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KF & LF PROPERTIES / FARLOWS / 080346955 / 412005332001 (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/08/2024 |
  01/08/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/08/2024 |
  01/11/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/08/2024 |
  01/10/2024 |
  The Department is conducting a site investigation, if required |
  01/08/2024 |
  03/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  01/08/2024 |
  01/10/2024 |
  The Department is determining if the activity affects State Lands. |
  01/08/2024 |
  01/10/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/11/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Modifications |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0307231-007-EM |
  Site Name: |
  DIAZ, AARON / 422002351003 / LEMON BAY |
  Applicant Name: |
  AARON DIAZ |
  Applicant Company: |
  450 ANCHOR ROW LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  DIAZ, AARON / 422002351003 / LEMON BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/12/2025 |
  02/12/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/12/2025 |
  03/14/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/12/2025 |
  02/13/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/12/2025 |
  02/13/2025 |
  The Department is determining if the activity affects State Lands. |
  02/12/2025 |
  02/13/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/12/2025 |
  02/13/2025 |
  The Department is conducting a site investigation, if required |
  02/12/2025 |
  02/13/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/14/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0307232-003-EE |
  Site Name: |
  BAWEL, ZACH / 412028352012 / LEMON BAY |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BAWEL, ZACH / 412028352012 / LEMON BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/28/2025 |
  01/28/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/28/2025 |
  02/27/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/28/2025 |
  01/28/2025 |
  The Department is determining if the activity affects State Lands. |
  01/28/2025 |
  01/28/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/28/2025 |
  01/28/2025 |
  The Department is conducting a site investigation, if required |
  01/28/2025 |
  01/28/2025 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  01/28/2025 |
  01/31/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/27/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0310941-002-EE |
  Site Name: |
  BEALL, ROBERT J / 412006326001/LEMON BAY |
  Applicant Name: |
  CODY COLLE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BEALL, ROBERT J / 412006326001/LEMON BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/06/2025 |
  02/06/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/06/2025 |
  03/07/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/06/2025 |
  02/07/2025 |
  The Department is determining if the activity affects State Lands. |
  02/06/2025 |
  02/07/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/06/2025 |
  02/07/2025 |
  The Department is conducting a site investigation, if required |
  02/06/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/07/2025 |
  03/25/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2025 |
  03/25/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/25/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0311982-003-EI |
  Site Name: |
  SANDPIPER SHORES POA / 412033176002 / BOCILLA LAGOON (R) |
  Applicant Name: |
  LEW FRIEDLAND |
  Applicant Company: |
  HEMMINGWAYS RETREAT LLP |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SANDPIPER SHORES POA / 412033176002 / BOCILLA LAGOON (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/22/2024 |
  01/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/22/2024 |
  02/16/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/22/2024 |
  01/24/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  01/22/2024 |
  01/24/2024 |
  The Department is determining if the activity affects State Lands. |
  01/22/2024 |
  01/24/2024 |
  The Department is conducting a site investigation, if required |
  01/22/2024 |
  02/21/2024 |
  The Department is waiting for additional information from the permit applicant. |
  02/16/2024 |
  05/08/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/08/2024 |
  06/07/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/07/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Modifications |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0313110-005-EM |
  Site Name: |
  GRIBBIN, MARTIN / 412319127003 / CANAL (R) |
  Applicant Name: |
  MARTIN GRIBBIN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GRIBBIN, MARTIN / 412319127003 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/18/2025 |
  03/18/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/18/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/18/2025 |
  03/19/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/18/2025 |
  03/19/2025 |
  The Department is determining if the activity affects State Lands. |
  03/18/2025 |
  03/19/2025 |
  The Department is conducting a site investigation, if required |
  03/18/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  03/18/2025 |
  03/19/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0314308-005-EE |
  Site Name: |
  1330 BEACH ROAD INC/ CBC AFFIL/ 411901476001 / 080351965 (R) |
  Applicant Name: |
  THOMAS LESTER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  1330 BEACH ROAD INC/ CBC AFFIL/ 411901476001 / 080351965 (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/30/2021 |
  11/30/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/30/2021 |
  11/30/2021 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/30/2021 |
  12/02/2021 |
  The Department is determining if the activity affects State Lands. |
  11/30/2021 |
  12/02/2021 |
  The Department is conducting a site investigation, if required |
  11/30/2021 |
  12/30/2021 |
  The Department is waiting for additional information from the permit applicant. |
  11/30/2021 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JO SANTOS |
  Application Number: |
  0315709-004-EI |
  Site Name: |
  HOOKER, BENJAMIN & VICTORIA / 402325178001 / CREEK |
  Applicant Name: |
  GEORGE GROVES |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HOOKER, BENJAMIN & VICTORIA / 402325178001 / CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/13/2025 |
  03/13/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/13/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/13/2025 |
  03/14/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/13/2025 |
  03/14/2025 |
  The Department is determining if the activity affects State Lands. |
  03/13/2025 |
  03/14/2025 |
  The Department is conducting a site investigation, if required |
  03/13/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  03/13/2025 |
  03/14/2025 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  03/14/2025 |
  03/18/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Formal Determination |
  Permit Processor: |
  TIM J THIBAULT |
  Application Number: |
  0315828-003-FD |
  Site Name: |
  T&M MINING LLC - HALL BERMONT PIT |
  Applicant Name: |
  MILES HALL |
  Applicant Company: |
  HALL FAMILY RANCH LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  T&M MINING LLC - HALL BERMONT PIT |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2025 |
  03/25/2025 |
  The Department is conducting a site investigation, if required |
  03/25/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/25/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0317522-004-EE |
  Site Name: |
  SUNWIND PROPERTIES INC/422016428006/PLACIDA HRBR/DOCK 14 |
  Applicant Name: |
  JAMIE PUERTO |
  Applicant Company: |
  SUNWIND PROPERTIES INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SUNWIND PROPERTIES INC/422016428006/PLACIDA HRBR/DOCK 14 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/31/2025 |
  03/31/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/31/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/31/2025 |
  04/02/2025 |
  The Department is determining if the activity affects State Lands. |
  03/31/2025 |
  04/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/31/2025 |
  04/02/2025 |
  The Department is conducting a site investigation, if required |
  03/31/2025 |
  04/02/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0322319-002-EI |
  Site Name: |
  KEIFER, DANIELA / 4022002352007 |
  Applicant Name: |
  DANIEL KEIFER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KEIFER, DANIELA / 4022002352007 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/08/2024 |
  11/08/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/08/2024 |
  12/06/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/08/2024 |
  11/10/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  11/08/2024 |
  11/12/2024 |
  The Department is determining if the activity affects State Lands. |
  11/08/2024 |
  11/10/2024 |
  The Department is conducting a site investigation, if required |
  11/08/2024 |
  11/12/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/08/2024 |
  11/10/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/06/2024 |
  12/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/30/2024 |
  01/29/2025 |
  The Department is waiting for additional information from the permit applicant. |
  01/29/2025 |
  02/18/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/18/2025 |
  03/11/2025 |
  The Department is making an outcome determination regarding the permit application. |
  02/18/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0326265-006-EE |
  Site Name: |
  HARBOUR VILLAGE POA / 402127701000 / CANAL SIDE (R) |
  Applicant Name: |
  |
  Applicant Company: |
  HARBOUR VILLAGE POA |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HARBOUR VILLAGE POA / 402127701000 / CANAL SIDE (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/03/2024 |
  12/03/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/03/2024 |
  01/02/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/03/2024 |
  12/03/2024 |
  The Department is determining if the activity affects State Lands. |
  12/03/2024 |
  12/03/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/03/2024 |
  12/03/2024 |
  The Department is conducting a site investigation, if required |
  12/03/2024 |
  12/03/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/02/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0328847-002-EE |
  Site Name: |
  ESSAY, JEREMY / 412006451009 / LEMON BAY |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ESSAY, JEREMY / 412006451009 / LEMON BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/06/2025 |
  02/06/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/06/2025 |
  03/06/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/06/2025 |
  02/07/2025 |
  The Department is determining if the activity affects State Lands. |
  02/06/2025 |
  02/07/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/06/2025 |
  02/07/2025 |
  The Department is conducting a site investigation, if required |
  02/06/2025 |
  02/07/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/06/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0329662-002-EE |
  Site Name: |
  CORAL CREEK ANGLERS CLUB OWNER ASSN INC / 422012426002 |
  Applicant Name: |
  PETE CASSARA |
  Applicant Company: |
  CORAL CREEK ANGLERS CLUB OWNERS ASSOCIATION, INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CORAL CREEK ANGLERS CLUB OWNER ASSN INC / 422012426002 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/10/2025 |
  03/10/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/10/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/10/2025 |
  03/17/2025 |
  The Department is determining if the activity affects State Lands. |
  03/10/2025 |
  03/17/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/10/2025 |
  03/17/2025 |
  The Department is conducting a site investigation, if required |
  03/10/2025 |
  03/17/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0331872-006-EE |
  Site Name: |
  ZUSMAN, NEIL / 402227353011 / ALLIGATOR BAY |
  Applicant Name: |
  CLAYTON CROCKER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ZUSMAN, NEIL / 402227353011 / ALLIGATOR BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/30/2025 |
  01/30/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/30/2025 |
  02/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/30/2025 |
  02/01/2025 |
  The Department is determining if the activity affects State Lands. |
  01/30/2025 |
  02/01/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/30/2025 |
  02/01/2025 |
  The Department is conducting a site investigation, if required |
  01/30/2025 |
  02/03/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0331872-007-EE |
  Site Name: |
  ZUSMAN, NEIL / 402227353011 / ALLIGATOR BAY |
  Applicant Name: |
  CLAYTON CROCKER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ZUSMAN, NEIL / 402227353011 / ALLIGATOR BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/30/2025 |
  01/30/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/30/2025 |
  02/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/30/2025 |
  02/01/2025 |
  The Department is determining if the activity affects State Lands. |
  01/30/2025 |
  02/01/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/30/2025 |
  02/01/2025 |
  The Department is conducting a site investigation, if required |
  01/30/2025 |
  02/03/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Domestic Wastewater Collection/Transmission System |
  Permit Processor: |
  RODNEY EUGENE |
  Application Number: |
  0337010-088-DWC |
  Site Name: |
  TOWN AND COUNTRY UTILITY FLA665495 |
  Applicant Name: |
  JOHN BRODERICK |
  Applicant Company: |
  BABCOCK PROPERTY HOLDINGS, LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/21/2025 |
  03/21/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/21/2025 |
  03/26/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/26/2025 |
  03/26/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/26/2025 |
  03/26/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/26/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0337583-003-EI |
  Site Name: |
  MAGNOLIAS MARKET ON THE BAY /OCEANAIRE/ 080353675 / BAY (R) |
  Applicant Name: |
  |
  Applicant Company: |
  MAGNOLIAS MARKET ON THE BAY LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MAGNOLIAS MARKET ON THE BAY /OCEANAIRE/ 080353675 / BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/14/2023 |
  08/14/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/14/2023 |
  09/11/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/14/2023 |
  08/16/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/14/2023 |
  08/18/2023 |
  The Department is determining if the activity affects State Lands. |
  08/14/2023 |
  08/16/2023 |
  The Department is conducting a site investigation, if required |
  08/14/2023 |
  08/18/2023 |
  The Department is waiting for additional information from the permit applicant. |
  09/11/2023 |
  09/13/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/13/2023 |
  10/13/2023 |
  The Department is waiting for additional information from the permit applicant. |
  10/13/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0342210-005-EE |
  Site Name: |
  CRAVEN, DANIEL / 412028326002 / BAY |
  Applicant Name: |
  DANIEL CRAVEN |
  Applicant Company: |
  DRC HOLDING CO LLC TRUSTEE |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CRAVEN, DANIEL / 412028326002 / BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/08/2022 |
  07/08/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/08/2022 |
  07/08/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/08/2022 |
  07/08/2022 |
  The Department is determining if the activity affects State Lands. |
  07/08/2022 |
  07/08/2022 |
  The Department is conducting a site investigation, if required |
  07/08/2022 |
  07/08/2022 |
  The Department is waiting for additional information from the permit applicant. |
  07/08/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Drinking Water Distribution System General Permit |
  Permit Processor: |
  RACHEL BROWN |
  Application Number: |
  0344279-117-DSGP |
  Site Name: |
  CHARLOTTE COUNTY UTILITIES (PWS 5084100) |
  Applicant Name: |
  DAVID WATSON |
  Applicant Company: |
  CHARLOTTE COUNTY UTILITIES |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/25/2025 |
  03/26/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/26/2025 |
  03/26/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/26/2025 |
  03/26/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/26/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0355018-006-EG |
  Site Name: |
  SARDINAS, GIEZY / 402229455001 / SPDR WWAY |
  Applicant Name: |
  GIEZY SARDINAS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SARDINAS, GIEZY / 402229455001 / SPDR WWAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/04/2025 |
  02/04/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/04/2025 |
  03/05/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/04/2025 |
  02/05/2025 |
  The Department is determining if the activity affects State Lands. |
  02/04/2025 |
  02/05/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/04/2025 |
  02/05/2025 |
  The Department is conducting a site investigation, if required |
  02/04/2025 |
  02/05/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/05/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0355691-002-EI |
  Site Name: |
  BREIDENBACH, WILLIAM / 412008126006 / ROCK CREEK |
  Applicant Name: |
  WILLIAM BREIDENBACH |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BREIDENBACH, WILLIAM / 412008126006 / ROCK CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/19/2024 |
  07/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/19/2024 |
  08/16/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/19/2024 |
  07/21/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  07/19/2024 |
  07/25/2024 |
  The Department is determining if the activity affects State Lands. |
  07/19/2024 |
  07/21/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/19/2024 |
  07/21/2024 |
  The Department is conducting a site investigation, if required |
  07/19/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  07/21/2024 |
  07/30/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/16/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0360601-003-EG |
  Site Name: |
  LEBLANC, TRENTON FKA BLEWETT, DANA / 402315232003 / PEACE R |
  Applicant Name: |
  TRENTON LEBLANC |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LEBLANC, TRENTON FKA BLEWETT, DANA / 402315232003 / PEACE R |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/20/2025 |
  03/20/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/20/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/20/2025 |
  03/22/2025 |
  The Department is determining if the activity affects State Lands. |
  03/20/2025 |
  03/22/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/20/2025 |
  03/22/2025 |
  The Department is conducting a site investigation, if required |
  03/20/2025 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  03/22/2025 |
  03/26/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Injection Well Operation Permit |
  Permit Processor: |
  DANIEL WARMKE |
  Application Number: |
  0364951-002-UO |
  Site Name: |
  ENGLEWOOD ASR CLASS V UIC |
  Applicant Name: |
  RAYMOND BURROUGHS |
  Applicant Company: |
  ENGLEWOOD WATER DISTRICT |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/09/2024 |
  02/09/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/09/2024 |
  02/11/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/09/2024 |
  03/20/2025 |
  The Department is making an outcome determination regarding the permit application. |
  02/09/2024 |
  03/20/2025 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  03/20/2025 |
  03/20/2025 |
  The Department published the draft Permit notice. |
  03/20/2025 |
  03/24/2025 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  03/24/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0368261-002-EG |
  Site Name: |
  KROMPETZ, EDWARD / 412115254015 |
  Applicant Name: |
  EDWARD KROMPETZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KROMPETZ, EDWARD / 412115254015 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/06/2025 |
  02/06/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/06/2025 |
  03/07/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/06/2025 |
  02/07/2025 |
  The Department is determining if the activity affects State Lands. |
  02/06/2025 |
  02/07/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/06/2025 |
  02/07/2025 |
  The Department is conducting a site investigation, if required |
  02/06/2025 |
  02/07/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/07/2025 |
  03/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/17/2025 |
  03/17/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/17/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0370237-007-EE |
  Site Name: |
  BECKMAN, CHRISTOPHER / KUEPPER / 411901380006 / BAY |
  Applicant Name: |
  CHRISTOPHER BECKMAN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BECKMAN, CHRISTOPHER / KUEPPER / 411901380006 / BAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/05/2024 |
  08/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/05/2024 |
  09/03/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/05/2024 |
  08/06/2024 |
  The Department is determining if the activity affects State Lands. |
  08/05/2024 |
  08/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/05/2024 |
  08/06/2024 |
  The Department is conducting a site investigation, if required |
  08/05/2024 |
  08/06/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  08/06/2024 |
  08/07/2024 |
  The Department is waiting for additional information from the permit applicant. |
  09/03/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0370771-003-EI |
  Site Name: |
  BROWN, JAMES / 402130228006 / CANAL (R) |
  Applicant Name: |
  JONATHAN BENNETT |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BROWN, JAMES / 402130228006 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/15/2023 |
  08/15/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/15/2023 |
  09/14/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/15/2023 |
  08/17/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/15/2023 |
  08/17/2023 |
  The Department is determining if the activity affects State Lands. |
  08/15/2023 |
  08/17/2023 |
  The Department is conducting a site investigation, if required |
  08/15/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  09/14/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  SWERP ONLINE PERMIT PROCESSOR |
  Application Number: |
  0374771-002-EE |
  Site Name: |
  4471 BAYVIEW ST [BOAT LIFT] |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  4471 BAYVIEW ST [BOAT LIFT] |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/03/2025 |
  04/03/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/03/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/03/2025 |
  |
  The Department is determining if the activity affects State Lands. |
  04/03/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  04/03/2025 |
  |
  The Department is conducting a site investigation, if required |
  04/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Drinking Water Distribution System General Permit |
  Permit Processor: |
  RODNEY EUGENE |
  Application Number: |
  0374803-013-DSGP |
  Site Name: |
  BURNT STORE REVERSE OSMOSIS WTP (PWS 6080318) |
  Applicant Name: |
  SCOTT EDWARDS |
  Applicant Company: |
  LENNAR HOMES, INC. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/25/2025 |
  03/31/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/31/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Modifications |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0375475-007-EM |
  Site Name: |
  FFWCC & SFWMD / BOND FARM HYDROLOGICAL ENHANCEMENT |
  Applicant Name: |
  KATHERINE BURKE |
  Applicant Company: |
  FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FFWCC & SFWMD / BOND FARM HYDROLOGICAL ENHANCEMENT |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/14/2025 |
  03/14/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/14/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/14/2025 |
  03/17/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/14/2025 |
  03/17/2025 |
  The Department is determining if the activity affects State Lands. |
  03/14/2025 |
  03/17/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/14/2025 |
  03/17/2025 |
  The Department is conducting a site investigation, if required |
  03/14/2025 |
  03/17/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0378355-001-EE |
  Site Name: |
  CLEMANS, CHARLES J / 412017130013 / CANAL |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CLEMANS, CHARLES J / 412017130013 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/01/2025 |
  04/01/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/01/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/01/2025 |
  04/03/2025 |
  The Department is determining if the activity affects State Lands. |
  04/01/2025 |
  04/03/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  04/01/2025 |
  04/03/2025 |
  The Department is conducting a site investigation, if required |
  04/01/2025 |
  04/03/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0380525-003-EI |
  Site Name: |
  MADISON, MARC & ANNETTE / 402128330005 / MYAKKA RIVER (R) |
  Applicant Name: |
  ANNETTE MADISON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MADISON, MARC & ANNETTE / 402128330005 / MYAKKA RIVER (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/01/2022 |
  06/01/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/01/2022 |
  07/01/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/01/2022 |
  06/03/2022 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/01/2022 |
  06/15/2022 |
  The Department is determining if the activity affects State Lands. |
  06/01/2022 |
  06/03/2022 |
  The Department is conducting a site investigation, if required |
  06/01/2022 |
  09/09/2022 |
  The Department is waiting for additional information from the permit applicant. |
  07/01/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0380525-005-EI |
  Site Name: |
  MADISON, MARC & ANNETTE / 402128330005 / MYAKKA RIVER (R) |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MADISON, MARC & ANNETTE / 402128330005 / MYAKKA RIVER (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/11/2024 |
  09/11/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/11/2024 |
  11/07/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/11/2024 |
  09/13/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/11/2024 |
  09/16/2024 |
  The Department is determining if the activity affects State Lands. |
  09/11/2024 |
  09/13/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/11/2024 |
  09/13/2024 |
  The Department is conducting a site investigation, if required |
  09/11/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  09/13/2024 |
  09/18/2024 |
  The Department is waiting for additional information from the permit applicant. |
  11/07/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0382197-002-EE |
  Site Name: |
  WATERVIEW PROPERTY OWNERS ASSN |
  Applicant Name: |
  ROBERT MEIER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WATERVIEW PROPERTY OWNERS ASSN |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/20/2024 |
  11/20/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/20/2024 |
  12/19/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/20/2024 |
  11/21/2024 |
  The Department is determining if the activity affects State Lands. |
  11/20/2024 |
  11/21/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/20/2024 |
  11/21/2024 |
  The Department is conducting a site investigation, if required |
  11/20/2024 |
  12/19/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/19/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JO SANTOS |
  Application Number: |
  0387164-001-EI |
  Site Name: |
  KOZMINSKE, MICHELE /402232128004 / CANAL |
  Applicant Name: |
  GEORGE GROVES |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KOZMINSKE, MICHELE /402232128004 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/07/2025 |
  03/07/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/07/2025 |
  04/03/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/07/2025 |
  03/09/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/07/2025 |
  03/10/2025 |
  The Department is determining if the activity affects State Lands. |
  03/07/2025 |
  03/09/2025 |
  The Department is conducting a site investigation, if required |
  03/07/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  03/07/2025 |
  03/09/2025 |
  The Department is waiting for additional information from the permit applicant. |
  04/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0401943-003-NPR |
  Site Name: |
  CHARLOTTE COUNTY AIRPORT AUTHORITY / 412310300001 / |
  Applicant Name: |
  JAMES PARISH |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE COUNTY AIRPORT AUTHORITY / 412310300001 / |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/06/2023 |
  07/06/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/06/2023 |
  08/04/2023 |
  The Department is conducting a site investigation, if required |
  07/06/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  08/04/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - WOTUS Determination with WMD Formal |
  Permit Processor: |
  MATT CZAHOR |
  Application Number: |
  0405357-001-WD |
  Site Name: |
  FLORIDA POWER & LIGHT / PARTRIDGE SUBSTATION |
  Applicant Name: |
  DAN DOYLE |
  Applicant Company: |
  PASTORE DOYLE DEVELOPERS LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA POWER & LIGHT / PARTRIDGE SUBSTATION |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/11/2021 |
  06/11/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/11/2021 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - WOTUS Determination with WMD Formal |
  Permit Processor: |
  MATT CZAHOR |
  Application Number: |
  0405426-001-WD |
  Site Name: |
  HOPE ETERNAL GARDENS / VARIOUS PID / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  HOPE ETERNAL GARDENS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HOPE ETERNAL GARDENS / VARIOUS PID / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/11/2021 |
  06/11/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/11/2021 |
  07/11/2021 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - WOTUS Determination with WMD Formal |
  Permit Processor: |
  MATT CZAHOR |
  Application Number: |
  0407096-001-WD |
  Site Name: |
  MANCINI PACKING CO / 422321100001 / (A) |
  Applicant Name: |
  SCOTT HOWARD |
  Applicant Company: |
  MARONDA HOMES |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MANCINI PACKING CO / 422321100001 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/19/2021 |
  07/19/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/19/2021 |
  08/18/2021 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0407096-002-NPR |
  Site Name: |
  MANCINI PACKING CO / 422321100001 / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  ZEMEL LAND PARTNERS LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MANCINI PACKING CO / 422321100001 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/12/2023 |
  07/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/12/2023 |
  08/07/2023 |
  The Department is conducting a site investigation, if required |
  07/12/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  08/07/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0407915-002-EI |
  Site Name: |
  HEWITT, ERIC & ROXANNE & DAVID / 402322185006 / CANAL |
  Applicant Name: |
  ERIC HEWITT |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HEWITT, ERIC & ROXANNE & DAVID / 402322185006 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/13/2022 |
  06/13/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/13/2022 |
  07/13/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/13/2022 |
  06/15/2022 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/13/2022 |
  06/22/2022 |
  The Department is determining if the activity affects State Lands. |
  06/13/2022 |
  06/15/2022 |
  The Department is conducting a site investigation, if required |
  06/13/2022 |
  |
  The Department is waiting for additional information from the permit applicant. |
  07/13/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  DANIEL SENSI |
  Application Number: |
  0408275-003-NPR |
  Site Name: |
  CHARLOTTE CO PUBLIC WORKS / KINGS HWY SHARED PATH /362773482 |
  Applicant Name: |
  JOANNE VERNON |
  Applicant Company: |
  CHARLOTTE COUNTY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE CO PUBLIC WORKS / KINGS HWY SHARED PATH /362773482 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/28/2024 |
  05/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/28/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/28/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0408403-003-EI |
  Site Name: |
  SMITH, THOMAS / 412017486001 / CANAL (R) |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SMITH, THOMAS / 412017486001 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/17/2021 |
  11/17/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/17/2021 |
  12/16/2021 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/17/2021 |
  11/19/2021 |
  The Department is determining if the activity affects State Lands. |
  11/17/2021 |
  11/19/2021 |
  The Department is waiting for additional information from the permit applicant. |
  12/16/2021 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0408848-002-EE |
  Site Name: |
  JLM TAMPA INC / 080361515 / 412033128007 / PASS (R) |
  Applicant Name: |
  |
  Applicant Company: |
  JLM TAMPA INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  JLM TAMPA INC / 080361515 / 412033128007 / PASS (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/26/2025 |
  03/27/2025 |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/27/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/26/2025 |
  03/27/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  03/27/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0408851-002-EE |
  Site Name: |
  110 GASPARILLA LLC / 080361525 / 412033128008 / PASS (R) |
  Applicant Name: |
  |
  Applicant Company: |
  110 GASPARILLA LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  110 GASPARILLA LLC / 080361525 / 412033128008 / PASS (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/26/2025 |
  03/28/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  03/28/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/26/2025 |
  03/28/2025 |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/28/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0409542-003-EE |
  Site Name: |
  ESSAY, RICHARD / 412006451010 / LEMON BAY (R) |
  Applicant Name: |
  BRICE FLOWER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ESSAY, RICHARD / 412006451010 / LEMON BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/06/2025 |
  02/06/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/06/2025 |
  03/07/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/06/2025 |
  02/07/2025 |
  The Department is determining if the activity affects State Lands. |
  02/06/2025 |
  02/07/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/06/2025 |
  02/07/2025 |
  The Department is conducting a site investigation, if required |
  02/06/2025 |
  02/07/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/07/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0410603-006-EI |
  Site Name: |
  SANYET, FELICITA / 422319384011 / CANAL (R) |
  Applicant Name: |
  FELICITA SANYET |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SANYET, FELICITA / 422319384011 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/26/2023 |
  09/26/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/26/2023 |
  10/24/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/26/2023 |
  09/26/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/26/2023 |
  09/26/2023 |
  The Department is determining if the activity affects State Lands. |
  09/26/2023 |
  09/26/2023 |
  The Department is conducting a site investigation, if required |
  09/26/2023 |
  09/26/2023 |
  The Department is waiting for additional information from the permit applicant. |
  10/24/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0412632-002-EI |
  Site Name: |
  POLLOCK, JAMES / 422015356009 / HARBOR |
  Applicant Name: |
  JAMES POLLOCK |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  POLLOCK, JAMES / 422015356009 / HARBOR |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/06/2024 |
  09/06/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/06/2024 |
  10/04/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/06/2024 |
  09/08/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/06/2024 |
  09/10/2024 |
  The Department is determining if the activity affects State Lands. |
  09/06/2024 |
  09/08/2024 |
  The Department is conducting a site investigation, if required |
  09/06/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  09/06/2024 |
  09/08/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/04/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  RYAN HETRICK |
  Application Number: |
  0413222-004-SFI |
  Site Name: |
  HERNANDEZ, SILVIO / 422429226010 / |
  Applicant Name: |
  SILVIO HERNANDEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HERNANDEZ, SILVIO / 422429226010 / |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/05/2022 |
  01/05/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/05/2022 |
  02/04/2022 |
  The Department is waiting for additional information from the permit applicant. |
  02/04/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0414858-002-EG |
  Site Name: |
  JOURNET, JONATHAN / 412126102005 / CANAL |
  Applicant Name: |
  JONATHAN JOURNET |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  JOURNET, JONATHAN / 412126102005 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/31/2023 |
  08/31/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/31/2023 |
  09/27/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/31/2023 |
  09/02/2023 |
  The Department is determining if the activity affects State Lands. |
  08/31/2023 |
  09/02/2023 |
  The Department is conducting a site investigation, if required |
  08/31/2023 |
  09/05/2023 |
  The Department is waiting for additional information from the permit applicant. |
  09/27/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  RYAN HETRICK |
  Application Number: |
  0415227-002-NPR |
  Site Name: |
  PERIUT, DAVID / 402112384006 / CANAL |
  Applicant Name: |
  DAVIE PERIUT |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PERIUT, DAVID / 402112384006 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/18/2022 |
  01/18/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/18/2022 |
  02/17/2022 |
  The Department is waiting for additional information from the permit applicant. |
  02/17/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0416693-002-SFI |
  Site Name: |
  BOARDWALK VILLAGE LLC - BOARDWALK EXCAVATION |
  Applicant Name: |
  JOHN ROWLAND |
  Applicant Company: |
  S2A MODULAR 36 LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BOARDWALK VILLAGE LLC - BOARDWALK EXCAVATION |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/28/2022 |
  10/28/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/28/2022 |
  11/22/2022 |
  The Department is conducting a site investigation, if required |
  10/28/2022 |
  |
  The Department is waiting for additional information from the permit applicant. |
  11/22/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JEFFREY PASSERELLO |
  Application Number: |
  0418363-001-NPR |
  Site Name: |
  FROLAN INVESTMENT, LLC / 412317278016 / A |
  Applicant Name: |
  FRANK SHULMAN |
  Applicant Company: |
  SADDLE LIGHT INVESTMENTS LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FROLAN INVESTMENT, LLC / 412317278016 / A |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/22/2022 |
  03/22/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/22/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JEFFREY PASSERELLO |
  Application Number: |
  0419107-002-NPR |
  Site Name: |
  KILLORAN, ANITA / 422422177006 / |
  Applicant Name: |
  ANITA KILORAN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KILLORAN, ANITA / 422422177006 / |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/06/2022 |
  04/06/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/06/2022 |
  05/05/2022 |
  The Department is waiting for additional information from the permit applicant. |
  05/05/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0419311-004-EE |
  Site Name: |
  ABRUZZESE, ROBERT / 412129181003 / CANAL (R) |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ABRUZZESE, ROBERT / 412129181003 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2025 |
  03/27/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/27/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/27/2025 |
  03/31/2025 |
  The Department is determining if the activity affects State Lands. |
  03/27/2025 |
  03/31/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/27/2025 |
  03/31/2025 |
  The Department is conducting a site investigation, if required |
  03/27/2025 |
  03/31/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0419860-001-SFI |
  Site Name: |
  HARPER PROPERTY HOLDINGS LLC & ETAL / MCNEW RANCH |
  Applicant Name: |
  RON INGE |
  Applicant Company: |
  MCNEW PROPERTY HOLDINGS, LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HARPER PROPERTY HOLDINGS LLC & ETAL / MCNEW RANCH |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/21/2022 |
  04/21/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/21/2022 |
  05/20/2022 |
  The Department is waiting for additional information from the permit applicant. |
  05/20/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0420859-001-NPR |
  Site Name: |
  PC RESIDENTIAL LAND LLC / 412106404002 / |
  Applicant Name: |
  VANESSA VELEZ |
  Applicant Company: |
  PASSARELLA & ASSOCIATES INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PC RESIDENTIAL LAND LLC / 412106404002 / |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/10/2022 |
  05/10/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/10/2022 |
  06/09/2022 |
  The Department is waiting for additional information from the permit applicant. |
  06/09/2022 |
  07/13/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/13/2022 |
  07/13/2022 |
  The Department is making an outcome determination regarding the permit application. |
  07/13/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0421003-002-SFI |
  Site Name: |
  BARSTOOL PROP LLC & CHARLOTTE HARBOR CON / PG STORAGE VAULT |
  Applicant Name: |
  GARY BAYNE |
  Applicant Company: |
  BARSTOOL PROPERTIES LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BARSTOOL PROP LLC & CHARLOTTE HARBOR CON / PG STORAGE VAULT |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/30/2023 |
  05/30/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/30/2023 |
  06/28/2023 |
  The Department is conducting a site investigation, if required |
  05/30/2023 |
  09/08/2023 |
  The Department is waiting for additional information from the permit applicant. |
  06/28/2023 |
  09/08/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/08/2023 |
  10/05/2023 |
  The Department is waiting for additional information from the permit applicant. |
  10/05/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0423764-001-EI |
  Site Name: |
  BECKMAN, ROBERT / 412319156007 / CANAL (R) |
  Applicant Name: |
  GEORGE GROVES |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BECKMAN, ROBERT / 412319156007 / CANAL (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/14/2022 |
  07/14/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/14/2022 |
  08/12/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/14/2022 |
  07/16/2022 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  07/14/2022 |
  07/22/2022 |
  The Department is determining if the activity affects State Lands. |
  07/14/2022 |
  07/16/2022 |
  The Department is conducting a site investigation, if required |
  07/14/2022 |
  08/11/2022 |
  The Department is waiting for additional information from the permit applicant. |
  08/12/2022 |
  05/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/12/2023 |
  05/12/2023 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0424972-003-SFI |
  Site Name: |
  PIEDRA, JULIO / 422429101003 |
  Applicant Name: |
  JULIO PIEDRA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PIEDRA, JULIO / 422429101003 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/14/2023 |
  03/14/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/14/2023 |
  04/13/2023 |
  The Department is conducting a site investigation, if required |
  03/14/2023 |
  04/13/2023 |
  The Department is waiting for additional information from the permit applicant. |
  04/13/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0429052-001-SFI |
  Site Name: |
  26 VILLAS DEL SOL LLC / SHELL OAKS / 3 PID'S |
  Applicant Name: |
  |
  Applicant Company: |
  26 VILLAS DEL SOL LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  26 VILLAS DEL SOL LLC / SHELL OAKS / 3 PID'S |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/05/2022 |
  12/05/2022 |
  The Department is conducting a site investigation, if required |
  12/05/2022 |
  11/16/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/05/2022 |
  01/04/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/04/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0429521-004-EG |
  Site Name: |
  PEREZ, VICTOR / 402309105003 |
  Applicant Name: |
  VICTOR PEREZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PEREZ, VICTOR / 402309105003 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/28/2025 |
  02/28/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/28/2025 |
  03/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/28/2025 |
  03/02/2025 |
  The Department is determining if the activity affects State Lands. |
  02/28/2025 |
  03/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/28/2025 |
  03/02/2025 |
  The Department is conducting a site investigation, if required |
  02/28/2025 |
  03/03/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0429979-003-SFI |
  Site Name: |
  BURNT STORE ROAD-RET / MULTIPLE PID / (A) |
  Applicant Name: |
  RANDY THIBAUT |
  Applicant Company: |
  BURNT STORE ROAD-RET |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BURNT STORE ROAD-RET / MULTIPLE PID / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/16/2023 |
  10/16/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/16/2023 |
  11/06/2023 |
  The Department is conducting a site investigation, if required |
  10/16/2023 |
  10/16/2023 |
  The Department is waiting for additional information from the permit applicant. |
  11/06/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0430007-002-NPR |
  Site Name: |
  BABCOCK RANCH BOAT RAMP / 422629201001 , 422630100001 / (A) |
  Applicant Name: |
  JOHN BRODERICK |
  Applicant Company: |
  BABCOCK PROPERTY HOLDINGS LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BABCOCK RANCH BOAT RAMP / 422629201001 , 422630100001 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/19/2023 |
  05/19/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/19/2023 |
  06/16/2023 |
  The Department is conducting a site investigation, if required |
  05/19/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/16/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  DANIEL SENSI |
  Application Number: |
  0430914-001-EE |
  Site Name: |
  HEALEY, MARK & TAMI / 412028303007 / CANAL |
  Applicant Name: |
  MARK HEALEY |
  Applicant Company: |
  |
  Agency Action: |
  Issue: Pending Final Action |
  Link to Department’s Application File: |
  HEALEY, MARK & TAMI / 412028303007 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/30/2023 |
  01/30/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/30/2023 |
  02/16/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/30/2023 |
  01/31/2023 |
  The Department is determining if the activity affects State Lands. |
  01/30/2023 |
  01/31/2023 |
  The Department is conducting a site investigation, if required |
  01/30/2023 |
  01/31/2023 |
  The Department is making an outcome determination regarding the permit application. |
  01/30/2023 |
  02/16/2023 |
  The final permit application status was determined by the Department. |
  02/16/2023 |
  02/16/2023 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0431214-002-EE |
  Site Name: |
  BALOGH, WILLIAM / 412006326002 / LEMON BAY (R) |
  Applicant Name: |
  CODY COLLE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BALOGH, WILLIAM / 412006326002 / LEMON BAY (R) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/11/2025 |
  02/11/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/11/2025 |
  03/13/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/11/2025 |
  02/12/2025 |
  The Department is determining if the activity affects State Lands. |
  02/11/2025 |
  02/12/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/11/2025 |
  02/12/2025 |
  The Department is conducting a site investigation, if required |
  02/11/2025 |
  02/12/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/13/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Modifications |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0433129-003-EM |
  Site Name: |
  FLORIDA POWER & LIGHT / GREEN PASTURE SOLAR ENERGY CENTER |
  Applicant Name: |
  TIM OLIVER |
  Applicant Company: |
  FLORIDA POWER & LIGHT |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA POWER & LIGHT / GREEN PASTURE SOLAR ENERGY CENTER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/03/2025 |
  02/03/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/03/2025 |
  03/04/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/03/2025 |
  02/04/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/03/2025 |
  02/04/2025 |
  The Department is determining if the activity affects State Lands. |
  02/03/2025 |
  02/04/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/03/2025 |
  02/04/2025 |
  The Department is conducting a site investigation, if required |
  02/03/2025 |
  03/04/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/04/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0434162-001-EI |
  Site Name: |
  CITY OF PUNTA GORDA / COLONY POINT DR DMMA CHANNEL |
  Applicant Name: |
  GREGORY MURRAY |
  Applicant Company: |
  CITY OF PUNTA GORDA |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CITY OF PUNTA GORDA / COLONY POINT DR DMMA CHANNEL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/19/2023 |
  04/19/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/19/2023 |
  05/20/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/19/2023 |
  04/21/2023 |
  The Department is conducting a site investigation, if required |
  04/19/2023 |
  05/11/2023 |
  The Department is determining if the activity affects State Lands. |
  04/19/2023 |
  04/28/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  04/19/2023 |
  04/24/2023 |
  The Department is waiting for additional information from the permit applicant. |
  05/20/2023 |
  07/18/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/18/2024 |
  08/16/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/16/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0434225-002-EI |
  Site Name: |
  RODRIGUEZ, MAIRA / 402728400008 |
  Applicant Name: |
  MAIRA RODRIGUEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  RODRIGUEZ, MAIRA / 402728400008 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/30/2023 |
  05/30/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/30/2023 |
  06/27/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/30/2023 |
  06/01/2023 |
  The Department is conducting a site investigation, if required |
  05/30/2023 |
  06/19/2023 |
  The Department is determining if the activity affects State Lands. |
  05/30/2023 |
  06/01/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  05/30/2023 |
  06/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  06/27/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  ERIN M REED |
  Application Number: |
  0434225-003-NPR |
  Site Name: |
  RODRIGUEZ, MAIRA / 402728400008 |
  Applicant Name: |
  MAIRA RODRIGUEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  RODRIGUEZ, MAIRA / 402728400008 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/30/2023 |
  05/30/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/30/2023 |
  06/27/2023 |
  The Department is conducting a site investigation, if required |
  05/30/2023 |
  06/19/2023 |
  The Department is waiting for additional information from the permit applicant. |
  06/27/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0434642-003-SFG |
  Site Name: |
  TECO PEOPLES GAS / ALONG BURNT STORE RD & ZEMEL RD |
  Applicant Name: |
  QUOC MAI |
  Applicant Company: |
  MAI ENGINEERING |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  TECO PEOPLES GAS / ALONG BURNT STORE RD & ZEMEL RD |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/26/2023 |
  07/26/2023 |
  The Department is conducting a site investigation, if required |
  07/26/2023 |
  07/26/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/26/2023 |
  08/24/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/24/2023 |
  12/19/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/19/2023 |
  12/19/2023 |
  The Department is making an outcome determination regarding the permit application. |
  12/19/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0434907-004-NPR |
  Site Name: |
  PUNTA GORDA PROPERTIES LLC / 412301477005 |
  Applicant Name: |
  JAMES RALLO |
  Applicant Company: |
  PUNTA GORDA PROPERTIES LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PUNTA GORDA PROPERTIES LLC / 412301477005 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/06/2023 |
  12/06/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/06/2023 |
  01/04/2024 |
  The Department is conducting a site investigation, if required |
  12/06/2023 |
  12/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/04/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0435033-004-NPR |
  Site Name: |
  PUNTA GORDA PROPERTIES LLC / 412301477004 |
  Applicant Name: |
  JAMES RALLO |
  Applicant Company: |
  PUNTA GORDA PROPERTIES LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PUNTA GORDA PROPERTIES LLC / 412301477004 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/06/2023 |
  12/06/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/06/2023 |
  01/04/2024 |
  The Department is conducting a site investigation, if required |
  12/06/2023 |
  12/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/04/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0436057-002-SFG |
  Site Name: |
  GRAND, BRIAN / 402110380017 / A |
  Applicant Name: |
  BRIAN GRAND |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GRAND, BRIAN / 402110380017 / A |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/06/2023 |
  06/06/2023 |
  The Department is conducting a site investigation, if required |
  06/06/2023 |
  10/02/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/06/2023 |
  07/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  07/06/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0436587-003-EI |
  Site Name: |
  CASSELLS, CHAD / 412127226018 / CANAL / R |
  Applicant Name: |
  CHAD CASSELLS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CASSELLS, CHAD / 412127226018 / CANAL / R |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/02/2023 |
  08/02/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/02/2023 |
  08/24/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/02/2023 |
  08/04/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/02/2023 |
  08/07/2023 |
  The Department is determining if the activity affects State Lands. |
  08/02/2023 |
  08/04/2023 |
  The Department is conducting a site investigation, if required |
  08/02/2023 |
  08/18/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/24/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0436749-001-NPR |
  Site Name: |
  RIVER COMMONS / 402215376004 |
  Applicant Name: |
  |
  Applicant Company: |
  RIVER COMMONS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  RIVER COMMONS / 402215376004 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/15/2023 |
  06/15/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/15/2023 |
  07/12/2023 |
  The Department is conducting a site investigation, if required |
  06/15/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  07/12/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0437447-002-SFG |
  Site Name: |
  MURDOCK VILLAGE COMM REDEV AGENCY / 402112251001 |
  Applicant Name: |
  JAMES HARVEY |
  Applicant Company: |
  KL WEST PORT EXPANSION LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MURDOCK VILLAGE COMM REDEV AGENCY / 402112251001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/02/2024 |
  02/02/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/02/2024 |
  |
  The Department is conducting a site investigation, if required |
  02/02/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0438068-002-NPR |
  Site Name: |
  SYNERGY HOMES LLC / 23508 CEDARTON AVENUE / 402224278028 |
  Applicant Name: |
  DYLAN CURRY |
  Applicant Company: |
  SYNERGY HOMES LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SYNERGY HOMES LLC / 23508 CEDARTON AVENUE / 402224278028 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/25/2023 |
  07/25/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/25/2023 |
  08/22/2023 |
  The Department is conducting a site investigation, if required |
  07/25/2023 |
  08/23/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/22/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0438810-001-EI |
  Site Name: |
  SMERECZYNSKY, BLAKE / 422004229005 / R |
  Applicant Name: |
  BLAKE SMERECZYNSKY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SMERECZYNSKY, BLAKE / 422004229005 / R |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/14/2023 |
  08/14/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/14/2023 |
  09/11/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/14/2023 |
  08/16/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/14/2023 |
  08/16/2023 |
  The Department is determining if the activity affects State Lands. |
  08/14/2023 |
  08/16/2023 |
  The Department is conducting a site investigation, if required |
  08/14/2023 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  08/16/2023 |
  08/18/2023 |
  The Department is waiting for additional information from the permit applicant. |
  09/11/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0439112-002-EE |
  Site Name: |
  GARCIA, MICHAEL / 402315404006 / R |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  COASTLINE BOAT LIFT COVERS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GARCIA, MICHAEL / 402315404006 / R |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/22/2023 |
  12/22/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/22/2023 |
  01/22/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/22/2023 |
  12/22/2023 |
  The Department is determining if the activity affects State Lands. |
  12/22/2023 |
  12/22/2023 |
  The Department is conducting a site investigation, if required |
  12/22/2023 |
  12/22/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/22/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0440933-001-NPR |
  Site Name: |
  STOR NOW FLORIDA LLC / 412105353003 , 412105353002 / (A) |
  Applicant Name: |
  CRAIG SHOEMAKER |
  Applicant Company: |
  STOR NOW FLORIDA LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  STOR NOW FLORIDA LLC / 412105353003 , 412105353002 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/09/2023 |
  10/09/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/09/2023 |
  11/07/2023 |
  The Department is conducting a site investigation, if required |
  10/09/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  11/07/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0441313-002-EE |
  Site Name: |
  MARONEY, GREG / 412126476004 |
  Applicant Name: |
  CREG MARONEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MARONEY, GREG / 412126476004 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/17/2024 |
  05/17/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/17/2024 |
  06/06/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/17/2024 |
  05/19/2024 |
  The Department is determining if the activity affects State Lands. |
  05/17/2024 |
  05/19/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  05/17/2024 |
  05/19/2024 |
  The Department is conducting a site investigation, if required |
  05/17/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/06/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0441436-001-SFI |
  Site Name: |
  ANITA RUSSEL / MULTIPLE PID / (A) |
  Applicant Name: |
  ANITA RUSSELL |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ANITA RUSSEL / MULTIPLE PID / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/23/2023 |
  10/23/2023 |
  The Department is conducting a site investigation, if required |
  10/23/2023 |
  02/14/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/23/2023 |
  11/01/2023 |
  The Department is waiting for additional information from the permit applicant. |
  11/01/2023 |
  02/14/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/14/2024 |
  02/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  02/15/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  JEFFREY PASSERELLO |
  Application Number: |
  0441705-002-SFI |
  Site Name: |
  DAILYN RAMOS / 422419201007 / (A) |
  Applicant Name: |
  DAILYN RAMOS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  DAILYN RAMOS / 422419201007 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/05/2024 |
  02/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/05/2024 |
  |
  The Department is conducting a site investigation, if required |
  02/05/2024 |
  03/06/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  KATARINA GLUECK |
  Application Number: |
  0442670-003-EE |
  Site Name: |
  MORINVILLE, JOSEPH / 422319334001 / CANAL |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  COASTLINE BOATLIFT COVERS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MORINVILLE, JOSEPH / 422319334001 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/15/2024 |
  08/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/15/2024 |
  09/13/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/15/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  08/15/2024 |
  08/17/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/15/2024 |
  08/17/2024 |
  The Department is conducting a site investigation, if required |
  08/15/2024 |
  08/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  09/13/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  ERIN M REED |
  Application Number: |
  0442791-001-EE |
  Site Name: |
  ZUS, SERGE / 412003407003 |
  Applicant Name: |
  SERGE ZUS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ZUS, SERGE / 412003407003 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/05/2023 |
  12/05/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/05/2023 |
  01/04/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/05/2023 |
  12/06/2023 |
  The Department is determining if the activity affects State Lands. |
  12/05/2023 |
  12/06/2023 |
  The Department is conducting a site investigation, if required |
  12/05/2023 |
  01/19/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0442988-001-EI |
  Site Name: |
  DEMPSEY, JESS / 422429126015 |
  Applicant Name: |
  JESS DEMPSEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  DEMPSEY, JESS / 422429126015 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/11/2023 |
  12/11/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/11/2023 |
  01/10/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/11/2023 |
  12/12/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  12/11/2023 |
  12/12/2023 |
  The Department is determining if the activity affects State Lands. |
  12/11/2023 |
  12/12/2023 |
  The Department is conducting a site investigation, if required |
  12/11/2023 |
  01/26/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/10/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0442988-002-SFI |
  Site Name: |
  DEMPSEY, JESS / 422429126015 |
  Applicant Name: |
  JESS DEMPSEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  DEMPSEY, JESS / 422429126015 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/11/2023 |
  12/11/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/11/2023 |
  01/10/2024 |
  The Department is conducting a site investigation, if required |
  12/11/2023 |
  01/26/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/10/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0443030-002-SFG |
  Site Name: |
  CACCIAPAGLIA, ANTHONY / 402213356013 / CANAL |
  Applicant Name: |
  ANTHONY CACCIAPAGLIO |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CACCIAPAGLIA, ANTHONY / 402213356013 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/12/2023 |
  12/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/12/2023 |
  01/11/2024 |
  The Department is conducting a site investigation, if required |
  12/12/2023 |
  01/05/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/11/2024 |
  02/12/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/12/2024 |
  02/12/2024 |
  The Department is making an outcome determination regarding the permit application. |
  02/12/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0443405-001-NPR |
  Site Name: |
  TEG DEVELOPERS LLC / 412105326001 / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  TEG DEVELOPERS LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  TEG DEVELOPERS LLC / 412105326001 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/20/2023 |
  12/20/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/20/2023 |
  01/11/2024 |
  The Department is conducting a site investigation, if required |
  12/20/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/11/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0445433-001-EI |
  Site Name: |
  HILL, ROBERT / 422022181009 / R |
  Applicant Name: |
  MIKE HETTINGER |
  Applicant Company: |
  LGI TRANSIT LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HILL, ROBERT / 422022181009 / R |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/19/2024 |
  02/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/19/2024 |
  03/20/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/19/2024 |
  02/20/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/19/2024 |
  02/20/2024 |
  The Department is determining if the activity affects State Lands. |
  02/19/2024 |
  02/20/2024 |
  The Department is conducting a site investigation, if required |
  02/19/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  02/20/2024 |
  02/23/2024 |
  The Department is waiting for additional information from the permit applicant. |
  03/20/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0445720-001-EE |
  Site Name: |
  CHAPMAN, BRUCE / 402325234005 |
  Applicant Name: |
  BRUCE CHAPMAN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHAPMAN, BRUCE / 402325234005 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/26/2024 |
  02/26/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/26/2024 |
  03/04/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/26/2024 |
  03/04/2024 |
  The Department is determining if the activity affects State Lands. |
  02/26/2024 |
  03/04/2024 |
  The Department is conducting a site investigation, if required |
  02/26/2024 |
  02/27/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  SHANELL BOSCH |
  Application Number: |
  0445827-001-NPR |
  Site Name: |
  SORESI DEVELOPMENT LLC / 422329152003 / (A) |
  Applicant Name: |
  NATALIE SORESI |
  Applicant Company: |
  SORESI DEVELOPMENT LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SORESI DEVELOPMENT LLC / 422329152003 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/28/2024 |
  02/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/28/2024 |
  |
  The Department is conducting a site investigation, if required |
  02/28/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  SHANELL BOSCH |
  Application Number: |
  0445830-001-NPR |
  Site Name: |
  SORESI DEVELOPMENT LLC / 422329152002 / (A) |
  Applicant Name: |
  NATALIE SORESI |
  Applicant Company: |
  SORESI DEVELOPMENT LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SORESI DEVELOPMENT LLC / 422329152002 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/28/2024 |
  02/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/28/2024 |
  |
  The Department is conducting a site investigation, if required |
  02/28/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  SHANELL BOSCH |
  Application Number: |
  0446831-001-NPR |
  Site Name: |
  GRANDE STORAGE CONDOS II, LLC / 412117202001 / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  GRANDE STORAGE CONDOS II, LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GRANDE STORAGE CONDOS II, LLC / 412117202001 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2024 |
  03/25/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2024 |
  |
  The Department is conducting a site investigation, if required |
  03/25/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0446832-001-NPR |
  Site Name: |
  BLOOM ACADEMY PUNTA GORDA LLC / 412307477005 / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  BLOOM ACADEMY PUNTA GORDA LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BLOOM ACADEMY PUNTA GORDA LLC / 412307477005 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2024 |
  03/25/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2024 |
  |
  The Department is conducting a site investigation, if required |
  03/25/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0446871-001-NPR |
  Site Name: |
  ANDREW SALOMON / 412321151011 / (A) |
  Applicant Name: |
  ANDREW SALOMON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ANDREW SALOMON / 412321151011 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2024 |
  03/26/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2024 |
  |
  The Department is conducting a site investigation, if required |
  03/26/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0447379-001-NPR |
  Site Name: |
  FLORIDA PANTHER LOADING SERVICE LLC / ONE PID / (A) |
  Applicant Name: |
  JONAS LUNA |
  Applicant Company: |
  FLORIDA PANTHER LOADING SERVICE LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA PANTHER LOADING SERVICE LLC / ONE PID / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/08/2024 |
  04/08/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/08/2024 |
  |
  The Department is conducting a site investigation, if required |
  04/08/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0448163-003-EG |
  Site Name: |
  PCCI GROUP / OHARA DRIVE XING |
  Applicant Name: |
  NORMA BRANSCUM |
  Applicant Company: |
  PRODESIGN ENGINEERING |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PCCI GROUP / OHARA DRIVE XING |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/07/2024 |
  11/07/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/07/2024 |
  12/05/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/07/2024 |
  11/08/2024 |
  The Department is determining if the activity affects State Lands. |
  11/07/2024 |
  11/08/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/07/2024 |
  11/08/2024 |
  The Department is conducting a site investigation, if required |
  11/07/2024 |
  11/08/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/05/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0448273-001-NPR |
  Site Name: |
  BURNT STORE LAKES PROPERTY OWNER'S ASSOCIATION, INC (A) |
  Applicant Name: |
  SANDRA FUNK |
  Applicant Company: |
  BURNT STORE LAKES PROPERTY OWNER'S ASSOCIATION, INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BURNT STORE LAKES PROPERTY OWNER'S ASSOCIATION, INC (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/30/2024 |
  04/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/30/2024 |
  |
  The Department is conducting a site investigation, if required |
  04/30/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0448496-001-NPR |
  Site Name: |
  BENDERSON DEVELOPMENT COMPANY, INC. / 402307751055 / (A) |
  Applicant Name: |
  |
  Applicant Company: |
  BENDERSON DEVELOPMENT CO INC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BENDERSON DEVELOPMENT COMPANY, INC. / 402307751055 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/06/2024 |
  05/06/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/06/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/06/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0448856-001-NPR |
  Site Name: |
  TAYLOR PRIME PROPERTIES LLC / HB RV GP!, LP / 412327352001 |
  Applicant Name: |
  |
  Applicant Company: |
  HB RV GP!, LP |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  TAYLOR PRIME PROPERTIES LLC / HB RV GP!, LP / 412327352001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/14/2024 |
  05/14/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/14/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/14/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0448914-001-NPR |
  Site Name: |
  CHARLOTTE COUNTY BOCC / 412013110001 / ROTUNDA BRIDGES 4 & 5 |
  Applicant Name: |
  JOANNE VERNON |
  Applicant Company: |
  CHARLOTTE COUNTY BOCC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE COUNTY BOCC / 412013110001 / ROTUNDA BRIDGES 4 & 5 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/15/2024 |
  05/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/15/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/15/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0448978-001-NPR |
  Site Name: |
  CHARLOTTE CO / OYSTER CREEK LITTORAL SHELF / 412008226001 |
  Applicant Name: |
  |
  Applicant Company: |
  CHARLOTTE COUNTY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE CO / OYSTER CREEK LITTORAL SHELF / 412008226001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/17/2024 |
  05/17/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/17/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/17/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0449085-001-EE |
  Site Name: |
  MISSANT, JON / 412225229004 / CREEK |
  Applicant Name: |
  JON MISSANT |
  Applicant Company: |
  JON E MISSANT TRUSTEE |
  Agency Action: |
  Issue: Pending Final Action |
  Link to Department’s Application File: |
  MISSANT, JON / 412225229004 / CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/21/2024 |
  05/21/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/21/2024 |
  06/20/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/21/2024 |
  05/22/2024 |
  The Department is determining if the activity affects State Lands. |
  05/21/2024 |
  05/22/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  05/21/2024 |
  05/22/2024 |
  The Department is conducting a site investigation, if required |
  05/21/2024 |
  05/22/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  05/22/2024 |
  05/23/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/20/2024 |
  09/11/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/11/2024 |
  09/11/2024 |
  The Department is making an outcome determination regarding the permit application. |
  09/11/2024 |
  10/15/2024 |
  The final permit application status was determined by the Department. |
  10/15/2024 |
  10/15/2024 |
  The Department issued the permit and filed the related permit information about the site and the applicant. |
  10/15/2024 |
  10/15/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0449491-006-EE |
  Site Name: |
  LAMMERTIN, JASON / 402234227002 |
  Applicant Name: |
  JASON LAMMERTIN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LAMMERTIN, JASON / 402234227002 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/11/2024 |
  09/11/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/11/2024 |
  02/27/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/11/2024 |
  09/13/2024 |
  The Department is conducting a site investigation, if required |
  09/11/2024 |
  10/11/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/11/2024 |
  09/13/2024 |
  The Department is determining if the activity affects State Lands. |
  09/11/2024 |
  09/13/2024 |
  The Department is waiting for additional information from the permit applicant. |
  02/27/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0450553-001-EE |
  Site Name: |
  GARCIA, YENIS / 422415401010 |
  Applicant Name: |
  YENIS GARCIA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GARCIA, YENIS / 422415401010 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/01/2024 |
  07/01/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/01/2024 |
  07/31/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/01/2024 |
  07/03/2024 |
  The Department is determining if the activity affects State Lands. |
  07/01/2024 |
  07/03/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/01/2024 |
  07/03/2024 |
  The Department is conducting a site investigation, if required |
  07/01/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  07/31/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0451045-003-EE |
  Site Name: |
  GERMAN, JONI / 402301307003 / CANAL |
  Applicant Name: |
  CLAYTON CROCKER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GERMAN, JONI / 402301307003 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/17/2025 |
  03/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/17/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/17/2025 |
  03/18/2025 |
  The Department is determining if the activity affects State Lands. |
  03/17/2025 |
  03/18/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/17/2025 |
  03/18/2025 |
  The Department is conducting a site investigation, if required |
  03/17/2025 |
  03/18/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0451464-001-EE |
  Site Name: |
  EHLEITER, JAMES / 412126456008 |
  Applicant Name: |
  JAMES EHLEITER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  EHLEITER, JAMES / 412126456008 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/25/2024 |
  07/25/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/25/2024 |
  08/20/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/25/2024 |
  07/27/2024 |
  The Department is determining if the activity affects State Lands. |
  07/25/2024 |
  07/27/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/25/2024 |
  07/27/2024 |
  The Department is conducting a site investigation, if required |
  07/25/2024 |
  09/18/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/20/2024 |
  08/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/22/2024 |
  09/20/2024 |
  The Department is waiting for additional information from the permit applicant. |
  09/20/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0451496-001-EE |
  Site Name: |
  SHEA, NATALIA / 402109304020 + REAR LOT FKA 402109304008 |
  Applicant Name: |
  NATALIA SHEA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SHEA, NATALIA / 402109304020 + REAR LOT FKA 402109304008 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/26/2024 |
  07/26/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/26/2024 |
  08/20/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/26/2024 |
  07/28/2024 |
  The Department is determining if the activity affects State Lands. |
  07/26/2024 |
  07/28/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/26/2024 |
  07/28/2024 |
  The Department is conducting a site investigation, if required |
  07/26/2024 |
  09/16/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/20/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JO SANTOS |
  Application Number: |
  0451569-003-EI |
  Site Name: |
  YOUNKMAN-REYNOLDS, ASHLEY / 402303201003 / DEEP CREEK |
  Applicant Name: |
  ASHLEY YOUNKMAN-REYNOLDS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  YOUNKMAN-REYNOLDS, ASHLEY / 402303201003 / DEEP CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/16/2024 |
  09/16/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/16/2024 |
  10/15/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/16/2024 |
  09/18/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/16/2024 |
  09/18/2024 |
  The Department is determining if the activity affects State Lands. |
  09/16/2024 |
  09/18/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/16/2024 |
  09/18/2024 |
  The Department is conducting a site investigation, if required |
  09/16/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  09/18/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  10/15/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0452049-001-EE |
  Site Name: |
  BRADLEY, JOYCE / 412334280005 / CANAL |
  Applicant Name: |
  JOYCE BRADLEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BRADLEY, JOYCE / 412334280005 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/23/2024 |
  07/23/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/23/2024 |
  08/21/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/23/2024 |
  07/25/2024 |
  The Department is determining if the activity affects State Lands. |
  07/23/2024 |
  07/25/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/23/2024 |
  07/25/2024 |
  The Department is conducting a site investigation, if required |
  07/23/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  08/21/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  MINING AND MINERALS REGULATION |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JESSIE L MASSEY |
  Application Number: |
  0452371-001-EI |
  Site Name: |
  LAKE LONLEY MINE |
  Applicant Name: |
  JOEL BOBROW |
  Applicant Company: |
  R&D CATTLE RANCH, LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LAKE LONLEY MINE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/12/2024 |
  11/12/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/12/2024 |
  12/10/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/12/2024 |
  11/14/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  11/12/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  11/12/2024 |
  11/15/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/12/2024 |
  11/15/2024 |
  The Department is conducting a site investigation, if required |
  11/12/2024 |
  12/10/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/10/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  MINING AND MINERALS REGULATION |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JESSIE L MASSEY |
  Application Number: |
  0452374-001-EI |
  Site Name: |
  BISHOP EXCAVATION |
  Applicant Name: |
  GARY BAYNE |
  Applicant Company: |
  SOUTHWEST ENGINEERING AND DESIGN |
  Agency Action: |
  No State Lands |
  Link to Department’s Application File: |
  BISHOP EXCAVATION |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/20/2024 |
  09/20/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/20/2024 |
  10/15/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/20/2024 |
  09/22/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/20/2024 |
  09/30/2024 |
  The Department is determining if the activity affects State Lands. |
  09/20/2024 |
  09/24/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/20/2024 |
  09/24/2024 |
  The Department is conducting a site investigation, if required |
  09/20/2024 |
  10/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/15/2024 |
  12/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/19/2024 |
  01/16/2025 |
  The Department is waiting for additional information from the permit applicant. |
  01/16/2025 |
  01/24/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/24/2025 |
  02/03/2025 |
  The Department is making an outcome determination regarding the permit application. |
  01/24/2025 |
  02/03/2025 |
  The Environmental Resource Program decision regarding the permit application was made. |
  01/24/2025 |
  03/25/2025 |
  The Department is awaiting proof of publication from the applicant following the issuance of a Notice of Intent to Issue a permit. |
  03/25/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0452407-002-EG |
  Site Name: |
  AZARI, RAFAEL / 412308302003 |
  Applicant Name: |
  KAREN AZARI |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  AZARI, RAFAEL / 412308302003 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/19/2024 |
  09/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/19/2024 |
  10/18/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/19/2024 |
  09/21/2024 |
  The Department is determining if the activity affects State Lands. |
  09/19/2024 |
  09/21/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/19/2024 |
  09/21/2024 |
  The Department is conducting a site investigation, if required |
  09/19/2024 |
  09/19/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/18/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0452852-001-EE |
  Site Name: |
  KRAMER, ANTHONY / 422310431009 |
  Applicant Name: |
  ANTHONY KRAMER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KRAMER, ANTHONY / 422310431009 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/05/2024 |
  09/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/05/2024 |
  10/04/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/05/2024 |
  09/07/2024 |
  The Department is determining if the activity affects State Lands. |
  09/05/2024 |
  09/07/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/05/2024 |
  09/07/2024 |
  The Department is conducting a site investigation, if required |
  09/05/2024 |
  10/24/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/04/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  MINING AND MINERALS REGULATION |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JESSIE L MASSEY |
  Application Number: |
  0452990-001-EI |
  Site Name: |
  WATERSIDE RESTORATION |
  Applicant Name: |
  TOM FLOOD |
  Applicant Company: |
  TMV PROPERTIES |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WATERSIDE RESTORATION |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/10/2024 |
  09/10/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/10/2024 |
  10/24/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/10/2024 |
  09/10/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/10/2024 |
  09/16/2024 |
  The Department is determining if the activity affects State Lands. |
  09/10/2024 |
  09/20/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/10/2024 |
  09/11/2024 |
  The Department is conducting a site investigation, if required |
  09/10/2024 |
  01/08/2025 |
  The Department is waiting for additional information from the permit applicant. |
  10/24/2024 |
  01/24/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/24/2025 |
  02/21/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/21/2025 |
  03/31/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/31/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KRYSTEN WOOD |
  Application Number: |
  0453046-003-EI |
  Site Name: |
  TC INVESTMENT GROUP LLC / 402225479009 / PEACE RIVER |
  Applicant Name: |
  JAMES WILLIAMSON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  TC INVESTMENT GROUP LLC / 402225479009 / PEACE RIVER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/31/2025 |
  01/31/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/31/2025 |
  02/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/31/2025 |
  02/02/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  01/31/2025 |
  02/03/2025 |
  The Department is determining if the activity affects State Lands. |
  01/31/2025 |
  02/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/31/2025 |
  02/02/2025 |
  The Department is conducting a site investigation, if required |
  01/31/2025 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  02/02/2025 |
  02/04/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0453350-002-EG |
  Site Name: |
  HOLIDAY BUILDERS / 412012430012 |
  Applicant Name: |
  MICHAEL LILLY |
  Applicant Company: |
  HOLIDAY BUILDERS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HOLIDAY BUILDERS / 412012430012 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/15/2024 |
  11/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/15/2024 |
  12/13/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/15/2024 |
  11/17/2024 |
  The Department is determining if the activity affects State Lands. |
  11/15/2024 |
  11/17/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/15/2024 |
  11/17/2024 |
  The Department is conducting a site investigation, if required |
  11/15/2024 |
  12/05/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/13/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0453800-008-EI |
  Site Name: |
  ZEROLO, FERNANDO & ROJAS, LIBIA / 412705151007 |
  Applicant Name: |
  FERNANDO & LIBIA ZEROLO & ROJAS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ZEROLO, FERNANDO & ROJAS, LIBIA / 412705151007 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/25/2025 |
  03/27/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/25/2025 |
  03/28/2025 |
  The Department is determining if the activity affects State Lands. |
  03/25/2025 |
  03/27/2025 |
  The Department is conducting a site investigation, if required |
  03/25/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  03/25/2025 |
  03/27/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  JO SANTOS |
  Application Number: |
  0454252-001-EG |
  Site Name: |
  PRODESIGN ENGINEERING |
  Applicant Name: |
  NORMA BRANSCUM |
  Applicant Company: |
  PRODESIGN ENGINEERING |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PRODESIGN ENGINEERING |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/22/2024 |
  10/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/22/2024 |
  11/21/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  10/22/2024 |
  10/24/2024 |
  The Department is determining if the activity affects State Lands. |
  10/22/2024 |
  10/24/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  10/22/2024 |
  10/24/2024 |
  The Department is conducting a site investigation, if required |
  10/22/2024 |
  10/24/2024 |
  The Department is waiting for additional information from the permit applicant. |
  11/21/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  JAMES DODSON |
  Application Number: |
  0454303-001-UC |
  Site Name: |
  SLD RECYCLING AND DISPOSAL FACILITY |
  Applicant Name: |
  DON GRIGG |
  Applicant Company: |
  SLD LANDFILL |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/24/2024 |
  10/24/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/24/2024 |
  10/31/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/24/2024 |
  11/18/2024 |
  The Department is waiting for additional information from the permit applicant. |
  11/18/2024 |
  12/18/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/18/2024 |
  03/27/2025 |
  The Department is making an outcome determination regarding the permit application. |
  12/18/2024 |
  03/27/2025 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  03/27/2025 |
  03/27/2025 |
  The Department published the draft Permit notice. |
  03/27/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0454876-001-EE |
  Site Name: |
  STOLL, DARIN L / 412126377007 |
  Applicant Name: |
  DARIN STOLL |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  STOLL, DARIN L / 412126377007 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/13/2024 |
  11/13/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/13/2024 |
  12/13/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/13/2024 |
  11/13/2024 |
  The Department is determining if the activity affects State Lands. |
  11/13/2024 |
  11/13/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/13/2024 |
  11/13/2024 |
  The Department is conducting a site investigation, if required |
  11/13/2024 |
  11/13/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/13/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0455086-001-EE |
  Site Name: |
  LEPAGE, ERIC / 412313251003 |
  Applicant Name: |
  ERIC LEPAGE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LEPAGE, ERIC / 412313251003 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/19/2024 |
  11/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/19/2024 |
  12/18/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/19/2024 |
  11/20/2024 |
  The Department is determining if the activity affects State Lands. |
  11/19/2024 |
  11/20/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  11/19/2024 |
  11/20/2024 |
  The Department is conducting a site investigation, if required |
  11/19/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  12/18/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0455719-001-EE |
  Site Name: |
  HURD, JEREMY / 402427201002 |
  Applicant Name: |
  JEREMY HURD |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HURD, JEREMY / 402427201002 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/10/2024 |
  12/10/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/10/2024 |
  01/07/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/10/2024 |
  12/11/2024 |
  The Department is determining if the activity affects State Lands. |
  12/10/2024 |
  12/11/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/10/2024 |
  12/11/2024 |
  The Department is conducting a site investigation, if required |
  12/10/2024 |
  12/11/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/07/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0455978-001-EE |
  Site Name: |
  VLASENKO, SIMON / 402116228001 |
  Applicant Name: |
  SIMON VLASENKO |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  VLASENKO, SIMON / 402116228001 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/18/2024 |
  12/18/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/18/2024 |
  01/09/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/18/2024 |
  12/19/2024 |
  The Department is determining if the activity affects State Lands. |
  12/18/2024 |
  12/19/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/18/2024 |
  12/19/2024 |
  The Department is conducting a site investigation, if required |
  12/18/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/09/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0456034-001-EE |
  Site Name: |
  ASC GLOBAL INC / 402130258006 |
  Applicant Name: |
  CLAYTON CROCKER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ASC GLOBAL INC / 402130258006 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/20/2024 |
  12/20/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/20/2024 |
  01/15/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/20/2024 |
  12/20/2024 |
  The Department is determining if the activity affects State Lands. |
  12/20/2024 |
  12/20/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/20/2024 |
  12/20/2024 |
  The Department is conducting a site investigation, if required |
  12/20/2024 |
  12/20/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/15/2025 |
  03/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/17/2025 |
  03/17/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/17/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0457166-001-EE |
  Site Name: |
  ECO LUNA LLC/ 422416301016 |
  Applicant Name: |
  ALAIN NOGUERAS |
  Applicant Company: |
  ECO LUNA LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ECO LUNA LLC/ 422416301016 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/30/2025 |
  01/30/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/30/2025 |
  02/25/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/30/2025 |
  01/31/2025 |
  The Department is determining if the activity affects State Lands. |
  01/30/2025 |
  01/31/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  01/30/2025 |
  01/31/2025 |
  The Department is conducting a site investigation, if required |
  01/30/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  02/25/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0457605-001-EE |
  Site Name: |
  VALERA, JORGE / 412333356021 |
  Applicant Name: |
  JORGE VALERA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  VALERA, JORGE / 412333356021 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/12/2025 |
  02/12/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/12/2025 |
  03/13/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/12/2025 |
  02/13/2025 |
  The Department is determining if the activity affects State Lands. |
  02/12/2025 |
  02/13/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/12/2025 |
  02/13/2025 |
  The Department is conducting a site investigation, if required |
  02/12/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/13/2025 |
  03/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/17/2025 |
  03/17/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/17/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANDREW HEMMELGARN |
  Application Number: |
  0457874-001-EI |
  Site Name: |
  ECOSPHERE RESORATION INSTITUTE |
  Applicant Name: |
  TOM RIES |
  Applicant Company: |
  ECOSPHERE RESTORATION INSTITUTE |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ECOSPHERE RESORATION INSTITUTE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/19/2025 |
  02/19/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/19/2025 |
  03/21/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/19/2025 |
  02/21/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/19/2025 |
  02/21/2025 |
  The Department is determining if the activity affects State Lands. |
  02/19/2025 |
  02/21/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/19/2025 |
  02/21/2025 |
  The Department is conducting a site investigation, if required |
  02/19/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/21/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0458166-001-EI |
  Site Name: |
  GULF SHELLFISH INSTITUTE |
  Applicant Name: |
  STEPHEN HESTERBERG |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GULF SHELLFISH INSTITUTE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/27/2025 |
  02/27/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/27/2025 |
  03/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/27/2025 |
  02/28/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/27/2025 |
  02/28/2025 |
  The Department is determining if the activity affects State Lands. |
  02/27/2025 |
  02/28/2025 |
  The Department is conducting a site investigation, if required |
  02/27/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  02/27/2025 |
  02/28/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0458177-001-EI |
  Site Name: |
  GULF SHELLFISH INSTITUTE / CHARLOTTE HARBOR |
  Applicant Name: |
  MALLORY SEA |
  Applicant Company: |
  GULF SHELLFISH INSTITUTE |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  GULF SHELLFISH INSTITUTE / CHARLOTTE HARBOR |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/27/2025 |
  02/27/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/27/2025 |
  03/28/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/27/2025 |
  02/28/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/27/2025 |
  02/28/2025 |
  The Department is determining if the activity affects State Lands. |
  02/27/2025 |
  02/28/2025 |
  The Department is conducting a site investigation, if required |
  02/27/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  02/27/2025 |
  02/28/2025 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  02/28/2025 |
  03/19/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0458365-001-EE |
  Site Name: |
  FLORES, GEORGE / 402107109003 / CANAL |
  Applicant Name: |
  GEORGE FLORES |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORES, GEORGE / 402107109003 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/05/2025 |
  03/05/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/05/2025 |
  04/01/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/05/2025 |
  03/06/2025 |
  The Department is determining if the activity affects State Lands. |
  03/05/2025 |
  03/06/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/05/2025 |
  03/06/2025 |
  The Department is conducting a site investigation, if required |
  03/05/2025 |
  03/06/2025 |
  The Department is waiting for additional information from the permit applicant. |
  04/01/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0458985-001-EE |
  Site Name: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
  Applicant Name: |
  JAMES WILLIAMSON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/24/2025 |
  03/24/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/24/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/24/2025 |
  03/25/2025 |
  The Department is determining if the activity affects State Lands. |
  03/24/2025 |
  03/25/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/24/2025 |
  03/25/2025 |
  The Department is conducting a site investigation, if required |
  03/24/2025 |
  03/25/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0458985-002-EE |
  Site Name: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
  Applicant Name: |
  JAMES WILLIAMSON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/24/2025 |
  03/24/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/24/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/24/2025 |
  03/25/2025 |
  The Department is determining if the activity affects State Lands. |
  03/24/2025 |
  03/25/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/24/2025 |
  03/25/2025 |
  The Department is conducting a site investigation, if required |
  03/24/2025 |
  03/25/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0458985-003-EE |
  Site Name: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
  Applicant Name: |
  JAMES WILLIAMSON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/26/2025 |
  03/27/2025 |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/27/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/26/2025 |
  03/27/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  03/27/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BUNKE |
  Application Number: |
  0458985-004-EE |
  Site Name: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
  Applicant Name: |
  JAMES WILLIAMSON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BLACK WATER CAPITAL FUND LLC / 412128279019 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/26/2025 |
  03/27/2025 |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/27/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/26/2025 |
  03/27/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  03/27/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  JULIA DAVIS |
  Application Number: |
  0459063-001-EG |
  Site Name: |
  HELLMAN, ALYSON / 422035326012 / GROUPER HOLE |
  Applicant Name: |
  MITCHELL SMITH |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HELLMAN, ALYSON / 422035326012 / GROUPER HOLE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/25/2025 |
  03/25/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/25/2025 |
  03/26/2025 |
  The Department is determining if the activity affects State Lands. |
  03/25/2025 |
  03/26/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/25/2025 |
  03/26/2025 |
  The Department is conducting a site investigation, if required |
  03/25/2025 |
  03/26/2025 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  03/26/2025 |
  03/28/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0459144-002-EE |
  Site Name: |
  BAILEY, MARK / 402227430001 / CANAL |
  Applicant Name: |
  MARK BAILEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BAILEY, MARK / 402227430001 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2025 |
  03/27/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/27/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/27/2025 |
  03/31/2025 |
  The Department is determining if the activity affects State Lands. |
  03/27/2025 |
  03/31/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/27/2025 |
  03/31/2025 |
  The Department is conducting a site investigation, if required |
  03/27/2025 |
  03/31/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JO SANTOS |
  Application Number: |
  0459153-001-EI |
  Site Name: |
  MCQUEEN, PAULA / 402333351002 / PEACE RIVER |
  Applicant Name: |
  MICHAEL RUSSELL |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MCQUEEN, PAULA / 402333351002 / PEACE RIVER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2025 |
  03/27/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/27/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/27/2025 |
  03/31/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/27/2025 |
  03/31/2025 |
  The Department is determining if the activity affects State Lands. |
  03/27/2025 |
  03/31/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/27/2025 |
  03/31/2025 |
  The Department is conducting a site investigation, if required |
  03/27/2025 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  03/31/2025 |
  04/01/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0459194-001-EE |
  Site Name: |
  LEE, MEYLIN / 412312376005 |
  Applicant Name: |
  MEYLIN LEE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LEE, MEYLIN / 412312376005 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/28/2025 |
  03/28/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/28/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/28/2025 |
  03/30/2025 |
  The Department is determining if the activity affects State Lands. |
  03/28/2025 |
  03/30/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/28/2025 |
  03/30/2025 |
  The Department is conducting a site investigation, if required |
  03/28/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  SAVANAH CEILLEY |
  Application Number: |
  0459256-001-EG |
  Site Name: |
  KRCEK, ROBERT / 412126456006 / CANAL |
  Applicant Name: |
  ROBERT KRCEK |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  KRCEK, ROBERT / 412126456006 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/31/2025 |
  03/31/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/31/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/31/2025 |
  04/01/2025 |
  The Department is determining if the activity affects State Lands. |
  03/31/2025 |
  04/01/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/31/2025 |
  04/01/2025 |
  The Department is conducting a site investigation, if required |
  03/31/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RYAN BENNETT SNYDER |
  Application Number: |
  0459327-001-EE |
  Site Name: |
  HOLSTEAD, SUE M & STEVEN M / 402125454006 / CANAL |
  Applicant Name: |
  STEVEN & SUE HOLSTEAD |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HOLSTEAD, SUE M & STEVEN M / 402125454006 / CANAL |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/01/2025 |
  04/01/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/01/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/01/2025 |
  04/02/2025 |
  The Department is determining if the activity affects State Lands. |
  04/01/2025 |
  04/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  04/01/2025 |
  04/02/2025 |
  The Department is conducting a site investigation, if required |
  04/01/2025 |
  04/02/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  SWERP ONLINE PERMIT PROCESSOR |
  Application Number: |
  0459409-001-EE |
  Site Name: |
  CHARLIE MACE |
  Applicant Name: |
  KEEGAN WEEKS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLIE MACE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/03/2025 |
  04/03/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/03/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  04/03/2025 |
  |
  The Department is determining if the activity affects State Lands. |
  04/03/2025 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  04/03/2025 |
  |
  The Department is conducting a site investigation, if required |
  04/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  ROLANDO GOMEZ |
  Application Number: |
  CH000683 M1 |
  Site Name: |
  CH R-014 S0057/N0043 |
  Applicant Name: |
  GARY L. & LORRAINE K. MCBRIDE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  DEREK D BELLAMY |
  Application Number: |
  CH000725 AR |
  Site Name: |
  CH R-001 |
  Applicant Name: |
  CHARLES & MARGARET SCARL |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  ROLANDO GOMEZ |
  Application Number: |
  CH000727 |
  Site Name: |
  CH R-055 S0438/S0493 |
  Applicant Name: |
  SUZANNE M. LINDSEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  ROLANDO GOMEZ |
  Application Number: |
  CH000730 |
  Site Name: |
  CH R-008 N0002/S0086 |
  Applicant Name: |
  |
  Applicant Company: |
  BOARDWALK OF MANASOTA KEY |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  ROLANDO GOMEZ |
  Application Number: |
  CH000731 |
  Site Name: |
  CH R-052 N0447/N0563 |
  Applicant Name: |
  MICHAEL & JENNIFER STRASHINSKY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  DEREK D BELLAMY |
  Application Number: |
  CH000733 AR |
  Site Name: |
  CH R-001 |
  Applicant Name: |
  MATT LOGSDON |
  Applicant Company: |
  MNA LIGHTHOUSE LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  CHARLOTTE |
  Permit Type: |
  Water - Beaches Construction Individual Permit |
  Permit Processor: |
  ROLANDO GOMEZ |
  Application Number: |
  CH000734 |
  Site Name: |
  CH R-001 |
  Applicant Name: |
  |
  Applicant Company: |
  MNA LIGHTHOUSE LLC, INC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  |
  |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  Charlotte |
  Permit Type: |
  Water - Domestic Wastewater Type II Facility Permit |
  Permit Processor: |
  ROBERT E REID |
  Application Number: |
  FLA014060-017-DW2 |
  Site Name: |
  Riverwoods Utilities WWTP |
  Applicant Name: |
  Cameron McKee |
  Applicant Company: |
  Riverwood CDD |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/20/2025 |
  03/20/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/20/2025 |
  03/26/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/26/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  Charlotte |
  Permit Type: |
  Water - Domestic Wastewater Type I Facility Permit |
  Permit Processor: |
  RACHEL BROWN |
  Application Number: |
  FLA014098-017-DW1 |
  Site Name: |
  Rotonda WRF |
  Applicant Name: |
  Dave Watson |
  Applicant Company: |
  Charlotte County Utilities-Rotunda West WWTP |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/12/2025 |
  03/12/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/12/2025 |
  03/19/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/19/2025 |
  03/19/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/19/2025 |
  03/19/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/19/2025 |
  03/31/2025 |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  Charlotte |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  RICHARD BOENSCH |
  Application Number: |
  FLA118371-017-DW1P |
  Site Name: |
  City of Punta Gorda WWTP |
  Applicant Name: |
  Thomas Spencer |
  Applicant Company: |
  City Of Punta Gorda |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/04/2024 |
  09/04/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/04/2024 |
  09/10/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  09/10/2024 |
  09/12/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/12/2024 |
  09/12/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/12/2024 |
  10/16/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/16/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  Charlotte |
  Permit Type: |
  Water - Industrial Wastewater Facility Permit |
  Permit Processor: |
  RICHARD BOENSCH |
  Application Number: |
  FLAB07511-001-IWF |
  Site Name: |
  Taylor Road Punta Gorda RV LP |
  Applicant Name: |
  Mark Davies |
  Applicant Company: |
  Kimley-Horn and Associates, Inc. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/10/2025 |
  03/10/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/10/2025 |
  03/20/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/10/2025 |
  03/27/2025 |
  The Department is making an outcome determination regarding the permit application. |
  03/10/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  Charlotte |
  Permit Type: |
  Water - Industrial Wastewater Concrete Batch Plant Permit |
  Permit Processor: |
  GABRIELLE VIGNET-WILLIAMS |
  Application Number: |
  FLG110778-006-IWCB |
  Site Name: |
  Coast Concrete Company, LLC |
  Applicant Name: |
  Rick Cripe |
  Applicant Company: |
  Coast Concrete Company, LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/27/2025 |
  01/27/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/27/2025 |
  02/04/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  02/04/2025 |
  02/04/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/04/2025 |
  02/04/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/04/2025 |
  03/06/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/06/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE NPDES STORMWATER |
  Florida County: |
  Charlotte |
  Permit Type: |
  MS2, > 10-50K |
  Permit Processor: |
  ALEXANDER C WEEKS |
  Application Number: |
  FLR04E039-005-MS2B |
  Site Name: |
  Punta Gorda, City of |
  Applicant Name: |
  Alvin Clemons |
  Applicant Company: |
  City of Punta Gorda |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/05/2022 |
  07/05/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  07/05/2022 |
  07/12/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/05/2022 |
  10/21/2024 |
  The Department is waiting for additional information from the permit applicant. |
  10/21/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE NPDES STORMWATER |
  Florida County: |
  Charlotte |
  Permit Type: |
  Construction Generic Dewatering Small |
  Permit Processor: |
  KRISHNA BARAL |
  Application Number: |
  FLR20HZ68-001-CGDS |
  Site Name: |
  Elevated Storage Tank Replacement |
  Applicant Name: |
  Mark Selph |
  Applicant Company: |
  Tlc Diversified, Inc. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/17/2025 |
  02/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/17/2025 |
  02/28/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/28/2025 |
  |
|