Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - ERP Modifications
  Permit Processor:   JUNHONG SHI
  Application Number:   0208670-002-EM
  Site Name:   FLORIDA RENEWABLE PARTNERS COLUMBIA COUNTY SOLAR
  Applicant Name:   ANTHONY PEDRONI
  Applicant Company:   FRP COLUMBIA COUNTY SOLAR LLC
  Agency Action:   Pending
  Link to Department’s Application File:   FLORIDA RENEWABLE PARTNERS COLUMBIA COUNTY SOLAR
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/14/2025   03/14/2025
  The Department is reviewing the permit application to determine if it contains all required information.   03/14/2025  
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP).   03/14/2025   03/16/2025
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   03/14/2025   03/28/2025
  The Department is determining if the activity affects State Lands.   03/14/2025   03/16/2025
  The Department is providing notice of application to commenting agencies for review.   03/14/2025   03/18/2025
  The Department is conducting a site investigation, if required   03/14/2025  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Air - Title V Operation Permit
  Permit Processor:   KATIE O O'GARA
  Application Number:   0230046-009-AV
  Site Name:   LAKE CITY
  Applicant Name:   JEFF COKER
  Applicant Company:   NEW MILLENIUM BUILDING SYSTEMS INC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   08/08/2024   08/08/2024
  The Department is performing the initial completeness review.   08/08/2024   09/13/2024
  The Department is waiting for additional information from the permit applicant.   09/13/2024   12/03/2024
  The Department is reviewing the permit application to determine if it contains all required information.   12/03/2024   12/05/2024
  The Department is making an outcome determination regarding the permit application.   12/03/2024   12/18/2024
  The Department completed the draft permit.   12/18/2024   12/18/2024
  The Department's intent regarding the permit application was published.   12/18/2024   01/16/2025
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   01/16/2025   02/15/2025
  The proposed permit was completed, but is not yet issued.   02/15/2025   02/18/2025
  The Federal Environmental Protection Agency is reviewing the proposed permit.   02/18/2025  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   CHASE H STERLING
  Application Number:   0348342-002-SFI
  Site Name:   Campground Improvements
  Applicant Name:  
  Applicant Company:   COLUMBIA COUNTY
  Agency Action:   Pending
  Link to Department’s Application File:   Campground Improvements
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   01/29/2024   01/29/2024
  The Department is reviewing the permit application to determine if it contains all required information.   01/29/2024  
  The Department is conducting a site investigation, if required   01/29/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   MATTHEW BRADEN
  Application Number:   0431148-001-SFI
  Site Name:   COLUMBIA COUNTY SHERRIFF'S OFFICE EVIDENCE BUILDING / KEVIN
  Applicant Name:   KEVIN KIRBY
  Applicant Company:   COLUMBIA COUNTY
  Agency Action:   Pending
  Link to Department’s Application File:   COLUMBIA COUNTY SHERRIFF'S OFFICE EVIDENCE BUILDING / KEVIN
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/02/2023   02/02/2023
  The Department is reviewing the permit application to determine if it contains all required information.   02/02/2023   04/20/2023
  The Department is conducting a site investigation, if required   02/02/2023   05/05/2023
  The Department is waiting for additional information from the permit applicant.   04/20/2023   11/17/2023
  The Department is reviewing the permit application to determine if it contains all required information.   11/17/2023   11/20/2023
  The Department published the public notice of the application after determining it contained all required items.   11/20/2023   11/20/2023
  The Department is waiting for the completion of the required comment period prior to continuing the permit application process.   11/20/2023  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 No Permit Required
  Permit Processor:   SARA HEULER
  Application Number:   0432870-001-NPR
  Site Name:   BELL ROAD COMMERCIAL/ DANIEL CRAPPS
  Applicant Name:   DANIEL CRAPPS
  Applicant Company:   BELL ROAD ENTERPRISES LLC
  Agency Action:   Pending
  Link to Department’s Application File:   BELL ROAD COMMERCIAL/ DANIEL CRAPPS
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/17/2023   03/17/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/17/2023  
  The Department is conducting a site investigation, if required   03/17/2023  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   PAUL M DUFF
  Application Number:   0446098-001-SFI
  Site Name:   HUNTERS CREEK / SW BASCOM NORRIS DRIVE
  Applicant Name:   MICHAEL GREEN
  Applicant Company:   GARDEN STREET COMMUNITIES SOUTHEAST, LLC
  Agency Action:   Pending
  Link to Department’s Application File:   HUNTERS CREEK / SW BASCOM NORRIS DRIVE
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/06/2024   03/06/2024
  The Department is reviewing the permit application to determine if it contains all required information.   03/06/2024  
  The Department is conducting a site investigation, if required   03/06/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   PAUL M DUFF
  Application Number:   0448166-001-SFI
  Site Name:   LEGENDS AT LAKE CITY
  Applicant Name:   JUSTON TRIMBACK
  Applicant Company:   TRIMCOR CONSTRUCTION OF FLORIDA LLC
  Agency Action:   Pending
  Link to Department’s Application File:   LEGENDS AT LAKE CITY
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/17/2024   04/17/2024
  The Department is reviewing the permit application to determine if it contains all required information.   04/17/2024  
  The Department is conducting a site investigation, if required   04/17/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 No Permit Required
  Permit Processor:   PAUL M DUFF
  Application Number:   0448190-001-NPR
  Site Name:   VICTORY HOLDINGS LAKE CITY
  Applicant Name:   KYLE MCLEOD
  Applicant Company:   VICTORY HOLDINGS LLC
  Agency Action:   Pending
  Link to Department’s Application File:   VICTORY HOLDINGS LAKE CITY
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/22/2024   04/22/2024
  The Department is reviewing the permit application to determine if it contains all required information.   04/22/2024  
  The Department is conducting a site investigation, if required   04/22/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - State 404 No Permit Required
  Permit Processor:   PAUL M DUFF
  Application Number:   0448463-001-NPR
  Site Name:   NIBLACK ELEMENTARY SCHOOL BOARD OF COLUMBIA COUNTY
  Applicant Name:   ALEX CARSWELL
  Applicant Company:   SCHOOL BOARD OF COLUMBIA COUNTY
  Agency Action:   Pending
  Link to Department’s Application File:   NIBLACK ELEMENTARY SCHOOL BOARD OF COLUMBIA COUNTY
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/30/2024   04/30/2024
  The Department is reviewing the permit application to determine if it contains all required information.   04/30/2024  
  The Department is conducting a site investigation, if required   04/30/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   COLUMBIA
  Permit Type:   Water - Individual With No Conceptual Approval Permit
  Permit Processor:   MARY AHMAD
  Application Number:   0454785-001-EI
  Site Name:   COLUMBIA CO QUAIL HEIGHTS FLOOD MITIGATION PROJECT
  Applicant Name:   MICHAEL FULLER
  Applicant Company:  
  Agency Action:   Pending
  Link to Department’s Application File:   COLUMBIA CO QUAIL HEIGHTS FLOOD MITIGATION PROJECT
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/08/2024   11/08/2024
  The Department is reviewing the permit application to determine if it contains all required information.   11/08/2024   11/26/2024
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP).   11/08/2024   11/10/2024
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   11/08/2024   11/22/2024
  The Department is determining if the activity affects State Lands.   11/08/2024   11/10/2024
  The Department is providing notice of application to commenting agencies for review.   11/08/2024   11/13/2024
  The Department is conducting a site investigation, if required   11/08/2024   12/16/2024
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands.   11/10/2024   11/15/2024
  The Department is waiting for additional information from the permit applicant.   11/26/2024  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   JUVELENE YDIA
  Application Number:   FLA011394-010-DW4P
  Site Name:   Columbia City Elementary School WWTF
  Applicant Name:   Keith Hatcher
  Applicant Company:   Columbia County School Board
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/15/2024   10/15/2024
  The permit processor is verifying the permit application fee submitted is correct.   10/15/2024   10/17/2024
  The Department is reviewing the permit application to determine if it contains all required information.   10/15/2024   10/15/2024
  The Department is waiting for additional information from the permit applicant.   10/15/2024  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Domestic Wastewater Type III Wastewater Treatment Plant Permit
  Permit Processor:   RODNEY CHRISTENSEN
  Application Number:   FLA011403-008-DW3P
  Site Name:   Super 8 Motel Complex WWTF - Lake City
  Applicant Name:   Deborah Harrell
  Applicant Company:   Manhattan Loan Co DBA Super 8 Motel
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/14/2024   02/14/2024
  The permit processor is verifying the permit application fee submitted is correct.   02/14/2024   02/22/2024
  The Department is reviewing the permit application to determine if it contains all required information.   02/14/2024   02/14/2024
  The Department is waiting for additional information from the permit applicant.   02/14/2024  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   RODNEY CHRISTENSEN
  Application Number:   FLA011412-010-DW4P
  Site Name:   Cannon Creek Mobile Home Park WWTF
  Applicant Name:   Robert Sanchez
  Applicant Company:   Cannon Creek Park, LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/20/2023   11/20/2023
  The permit processor is verifying the permit application fee submitted is correct.   11/20/2023   11/27/2023
  The Department is reviewing the permit application to determine if it contains all required information.   11/20/2023   11/20/2023
  The Department is waiting for additional information from the permit applicant.   11/20/2023  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Domestic Wastewater Type III Wastewater Treatment Plant Permit
  Permit Processor:   RODNEY CHRISTENSEN
  Application Number:   FLA011416-011-DW3P
  Site Name:   FDOT I-10 WB Columbia Co Rest Area WWTF
  Applicant Name:   Travis Humphries
  Applicant Company:   FL Depart Transportation (Marion)
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/26/2025   02/26/2025
  The permit processor is verifying the permit application fee submitted is correct.   02/26/2025   02/26/2025
  The Department is reviewing the permit application to determine if it contains all required information.   02/26/2025   02/26/2025
  The Department is waiting for additional information from the permit applicant.   02/26/2025  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Domestic Wastewater Type I Facility Permit
  Permit Processor:   JUVELENE YDIA
  Application Number:   FLAB07233-002-DW1
  Site Name:   North Florida Mega Industrial Park (NFMIP) WWTF
  Applicant Name:   Chad Williams
  Applicant Company:   Columbia County Board Commissioners
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/31/2025   03/31/2025
  The permit processor is verifying the permit application fee submitted is correct.   03/31/2025  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   Columbia
  Permit Type:   Water - Industrial Wastewater Concrete Batch Plant Permit
  Permit Processor:   STEPHEN SPENCE
  Application Number:   FLG110304-007-IWCB
  Site Name:   Columbia Ready Mix - Lake City
  Applicant Name:   Cameron Hume
  Applicant Company:   Columbia Ready-Mix Concrete, Inc.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/03/2025   02/03/2025
  The permit processor is verifying the permit application fee submitted is correct.   02/03/2025   02/05/2025
  The Department is waiting for the applicant to submit the requested additional fees.   02/05/2025   03/03/2025
  The permit processor is verifying the permit application fee submitted is correct.   03/03/2025   03/03/2025
  The Department is reviewing the permit application to determine if it contains all required information.   03/03/2025   03/14/2025
  The Department is waiting for additional information from the permit applicant.   03/14/2025