Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  DESOTO |
  Permit Type: |
  Waste - Solid Waste Construction Permit |
  Permit Processor: |
  ALAN WILLET |
  Application Number: |
  0331236-011-SC |
  Site Name: |
  DESOTO RECYCLING & DISPOSAL (DRD) CLASS III LANDFILL 95046 |
  Applicant Name: |
  TONY BISHOP |
  Applicant Company: |
  DESOTO RECYCLING AND DISPOSAL, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/01/2024 |
  03/01/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/01/2024 |
  04/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/01/2024 |
  03/29/2024 |
  The Department is waiting for additional information from the permit applicant. |
  03/29/2024 |
  04/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/30/2024 |
  05/31/2024 |
  The Department is making an outcome determination regarding the permit application. |
  04/30/2024 |
  07/26/2024 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  07/26/2024 |
  07/31/2024 |
  The Department's intent regarding the permit application was published. |
  07/31/2024 |
  08/04/2024 |
  The Office of General Counsel is reviewing petitions received from the applicant or third-parties related to the permit. |
  08/04/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  DESOTO |
  Permit Type: |
  Waste - Solid Waste Operation Permit |
  Permit Processor: |
  ALAN WILLET |
  Application Number: |
  0331236-012-SO |
  Site Name: |
  DESOTO RECYCLING & DISPOSAL (DRD) CLASS III LANDFILL 95046 |
  Applicant Name: |
  TONY BISHOP |
  Applicant Company: |
  DESOTO RECYCLING AND DISPOSAL, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/01/2024 |
  03/01/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/01/2024 |
  03/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/01/2024 |
  03/29/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/05/2024 |
  03/12/2024 |
  The Department is waiting for additional information from the permit applicant. |
  03/29/2024 |
  04/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/30/2024 |
  05/31/2024 |
  The Department is waiting for the applicant to return of the original affidavit of proof of publication of the Notice of Application. |
  03/12/2024 |
  03/12/2024 |
  The Department is making an outcome determination regarding the permit application. |
  04/30/2024 |
  07/26/2024 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  07/26/2024 |
  07/31/2024 |
  The Department's intent regarding the permit application was published. |
  07/31/2024 |
  08/04/2024 |
  The Office of General Counsel is reviewing petitions received from the applicant or third-parties related to the permit. |
  08/04/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0407220-001-SFI |
  Site Name: |
  D. R. HORTON, INC. / 29-39-23-0000-0012-0000 / A |
  Applicant Name: |
  JUSTIN ROBBINS |
  Applicant Company: |
  D.R. HORTON |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  D. R. HORTON, INC. / 29-39-23-0000-0012-0000 / A |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/19/2021 |
  07/19/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/19/2021 |
  08/18/2021 |
  The Department is conducting a site investigation, if required |
  07/19/2021 |
  10/26/2021 |
  The Department is waiting for additional information from the permit applicant. |
  08/18/2021 |
  01/09/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/09/2024 |
  01/17/2024 |
  The Department published the public notice of the application after determining it contained all required items. |
  01/17/2024 |
  01/23/2024 |
  The Department is waiting for the completion of the required comment period prior to continuing the permit application process. |
  01/23/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0419711-004-EE |
  Site Name: |
  FLORIDA POWER & LIGHT / SWEATT TO WHIDDEN SUBSTATIONS |
  Applicant Name: |
  NICK ZWEBER |
  Applicant Company: |
  FLORIDA POWER & LIGHT COMPANY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA POWER & LIGHT / SWEATT TO WHIDDEN SUBSTATIONS |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2025 |
  03/26/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/26/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/26/2025 |
  03/26/2025 |
  The Department is determining if the activity affects State Lands. |
  03/26/2025 |
  03/26/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/26/2025 |
  03/26/2025 |
  The Department is conducting a site investigation, if required |
  03/26/2025 |
  03/26/2025 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0429260-001-SFI |
  Site Name: |
  CHARLOTTE HARBOR LANDING LLC / HARBOUR LAKES / 2 PID'S |
  Applicant Name: |
  |
  Applicant Company: |
  CHARLOTTE HARBOR LANDING LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHARLOTTE HARBOR LANDING LLC / HARBOUR LAKES / 2 PID'S |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/09/2022 |
  12/09/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/09/2022 |
  01/06/2023 |
  The Department is conducting a site investigation, if required |
  12/09/2022 |
  05/19/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/06/2023 |
  04/06/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/06/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 Individual Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0432952-002-SFI |
  Site Name: |
  LLANO RANCHES LP / 33 38 27 0000 0010 0000 |
  Applicant Name: |
  LUCY ABELL |
  Applicant Company: |
  LLANO RANCHES LP |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LLANO RANCHES LP / 33 38 27 0000 0010 0000 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/22/2023 |
  05/22/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/22/2023 |
  06/20/2023 |
  The Department is conducting a site investigation, if required |
  05/22/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/20/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0443327-002-SFG |
  Site Name: |
  F P& L / JOSHUA CREEK SEC / 01 37 25 0000 0010 0000 |
  Applicant Name: |
  KATHARINE MACGREGOR |
  Applicant Company: |
  FPL |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  F P& L / JOSHUA CREEK SEC / 01 37 25 0000 0010 0000 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/19/2023 |
  12/19/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/19/2023 |
  01/17/2024 |
  The Department is conducting a site investigation, if required |
  12/19/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/17/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  JONATHAN GUINN |
  Application Number: |
  0443327-004-SFG |
  Site Name: |
  F P& L / JOSHUA CREEK SEC / 01 37 25 0000 0010 0000 |
  Applicant Name: |
  JODIE ELDRIDGE |
  Applicant Company: |
  FLORIDA POWER & LIGHT COMPANY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  F P& L / JOSHUA CREEK SEC / 01 37 25 0000 0010 0000 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2024 |
  03/27/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/27/2024 |
  |
  The Department is conducting a site investigation, if required |
  03/27/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 General Permit |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0443877-002-SFG |
  Site Name: |
  FLORIDA POWER & LIGHT / SADDLE SOLAR ENERGY CENTER |
  Applicant Name: |
  ROBERT MULLINS |
  Applicant Company: |
  FLORIDA POWER & LIGHT |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA POWER & LIGHT / SADDLE SOLAR ENERGY CENTER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/18/2023 |
  12/18/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/18/2023 |
  01/17/2024 |
  The Department is conducting a site investigation, if required |
  12/18/2023 |
  02/16/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/17/2024 |
  02/16/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/16/2024 |
  02/16/2024 |
  The Department is making an outcome determination regarding the permit application. |
  02/16/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  DANIEL WARMKE |
  Application Number: |
  0444142-001-UC |
  Site Name: |
  ECOSOUTH SERVICES, LLC DESOTO LANDFILL CLASS I UIC |
  Applicant Name: |
  TONY BISHOP |
  Applicant Company: |
  ECOSOUTH SERVICES, LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/12/2024 |
  01/12/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/12/2024 |
  01/18/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/12/2024 |
  04/16/2024 |
  The Department is waiting for additional information from the permit applicant. |
  04/16/2024 |
  05/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/15/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - State 404 No Permit Required |
  Permit Processor: |
  TOBY SCHWETJE |
  Application Number: |
  0447921-001-NPR |
  Site Name: |
  MIKE COATES / 103923000001100000 , 103923032300100010 / (A) |
  Applicant Name: |
  MIKE COATES |
  Applicant Company: |
  PEACE RIVER MANASOTA REGIONAL WATER SUPPLY AUTHORITY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  MIKE COATES / 103923000001100000 , 103923032300100010 / (A) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/22/2024 |
  04/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/22/2024 |
  |
  The Department is conducting a site investigation, if required |
  04/22/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  RUBEN E MARTINEZ |
  Application Number: |
  0449622-001-EE |
  Site Name: |
  CHERRY, WILLIAM / 21 38 25 0000 0200 0420 |
  Applicant Name: |
  WILLIAM CHERRY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CHERRY, WILLIAM / 21 38 25 0000 0200 0420 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/31/2024 |
  05/31/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/31/2024 |
  06/28/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/31/2024 |
  06/02/2024 |
  The Department is determining if the activity affects State Lands. |
  05/31/2024 |
  06/02/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  05/31/2024 |
  06/02/2024 |
  The Department is conducting a site investigation, if required |
  05/31/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/28/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  MATTHEW ERB |
  Application Number: |
  0453356-001-EE |
  Site Name: |
  CITY OF ARCADIA / ROW OF E GIBSON ST |
  Applicant Name: |
  |
  Applicant Company: |
  CITY OF ARCADIA |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CITY OF ARCADIA / ROW OF E GIBSON ST |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/12/2024 |
  09/12/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/12/2024 |
  10/07/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/12/2024 |
  09/14/2024 |
  The Department is determining if the activity affects State Lands. |
  09/12/2024 |
  09/14/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  09/12/2024 |
  09/14/2024 |
  The Department is conducting a site investigation, if required |
  09/12/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  10/07/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0454463-001-EE |
  Site Name: |
  LANCTO CHAD / 07 37 25 0283 00C0 008 |
  Applicant Name: |
  CHAD LANCTO |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LANCTO CHAD / 07 37 25 0283 00C0 008 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/29/2024 |
  10/29/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/29/2024 |
  11/22/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  10/29/2024 |
  10/30/2024 |
  The Department is determining if the activity affects State Lands. |
  10/29/2024 |
  10/30/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  10/29/2024 |
  10/30/2024 |
  The Department is conducting a site investigation, if required |
  10/29/2024 |
  10/30/2024 |
  The Department is waiting for additional information from the permit applicant. |
  11/22/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Noticed General Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0455551-001-EG |
  Site Name: |
  COMCAST / 10-38-25-0000-0050-0000 / JOSHUA CREEK |
  Applicant Name: |
  KATRIN SANTANA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  COMCAST / 10-38-25-0000-0050-0000 / JOSHUA CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/05/2024 |
  12/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/05/2024 |
  01/03/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/05/2024 |
  12/06/2024 |
  The Department is determining if the activity affects State Lands. |
  12/05/2024 |
  12/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/05/2024 |
  12/06/2024 |
  The Department is conducting a site investigation, if required |
  12/05/2024 |
  12/06/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  12/06/2024 |
  12/11/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  POLINA RADINSKY |
  Application Number: |
  0455551-002-EE |
  Site Name: |
  COMCAST / 10-38-25-0000-0050-0000 / JOSHUA CREEK |
  Applicant Name: |
  KATRIN SANTANA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  COMCAST / 10-38-25-0000-0050-0000 / JOSHUA CREEK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/05/2024 |
  12/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/05/2024 |
  01/03/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/05/2024 |
  12/06/2024 |
  The Department is conducting a site investigation, if required |
  12/05/2024 |
  12/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  12/05/2024 |
  12/06/2024 |
  The Department is determining if the activity affects State Lands. |
  12/05/2024 |
  12/06/2024 |
  The Department is waiting for additional information from the permit applicant. |
  01/03/2025 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  12/06/2024 |
  12/11/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  MINING AND MINERALS REGULATION |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JESSIE L MASSEY |
  Application Number: |
  0456333-002-EI |
  Site Name: |
  PIT 17 MINE |
  Applicant Name: |
  DAVID GRETH |
  Applicant Company: |
  GREEN WING REAL ESTATE GROUP LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PIT 17 MINE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/31/2025 |
  03/31/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/31/2025 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/31/2025 |
  03/31/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  03/31/2025 |
  |
  The Department is determining if the activity affects State Lands. |
  03/31/2025 |
  04/02/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/31/2025 |
  04/02/2025 |
  The Department is conducting a site investigation, if required |
  03/31/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  GABRIELLE VIGNET-WILLIAMS |
  Application Number: |
  0457867-001-EI |
  Site Name: |
  CITY OF ARCADIA - LEE SNYDER |
  Applicant Name: |
  LEE SNYDER |
  Applicant Company: |
  CITY OF ARCADIA |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CITY OF ARCADIA - LEE SNYDER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/19/2025 |
  02/19/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/19/2025 |
  03/19/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/19/2025 |
  02/20/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/19/2025 |
  02/20/2025 |
  The Department is determining if the activity affects State Lands. |
  02/19/2025 |
  02/20/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/19/2025 |
  02/20/2025 |
  The Department is conducting a site investigation, if required |
  02/19/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/19/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0457873-001-EI |
  Site Name: |
  FLORIDA POWER & LIGHT |
  Applicant Name: |
  TIM OLIVER |
  Applicant Company: |
  FLORIDA POWER & LIGHT |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FLORIDA POWER & LIGHT |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/19/2025 |
  02/19/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/19/2025 |
  03/21/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/19/2025 |
  02/21/2025 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/19/2025 |
  02/24/2025 |
  The Department is determining if the activity affects State Lands. |
  02/19/2025 |
  02/21/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  02/19/2025 |
  02/21/2025 |
  The Department is conducting a site investigation, if required |
  02/19/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/21/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - ERP Exemption Permit |
  Permit Processor: |
  CASEY N WILLIAMS |
  Application Number: |
  0458323-001-EE |
  Site Name: |
  HATCHER, KRISTINA & CHURCH, GARY / 36 39 23 0000 0190 0000 |
  Applicant Name: |
  KRISTINA HATCHER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  HATCHER, KRISTINA & CHURCH, GARY / 36 39 23 0000 0190 0000 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/04/2025 |
  03/04/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/04/2025 |
  04/03/2025 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  03/04/2025 |
  03/05/2025 |
  The Department is determining if the activity affects State Lands. |
  03/04/2025 |
  03/05/2025 |
  The Department is providing notice of application to commenting agencies for review. |
  03/04/2025 |
  03/05/2025 |
  The Department is conducting a site investigation, if required |
  03/04/2025 |
  |
  The Department is waiting for additional information from the permit applicant. |
  04/03/2025 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  JAMES DODSON |
  Application Number: |
  0459155-001-UC |
  Site Name: |
  DESOTO COUNTY WWTP CLASS I UIC |
  Applicant Name: |
  GREG HARRIS |
  Applicant Company: |
  DESOTO COUNTY UTILITIES |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2025 |
  03/27/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/27/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  DESOTO |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  JAMES DODSON |
  Application Number: |
  0459155-002-UC |
  Site Name: |
  DESOTO COUNTY WWTP CLASS I UIC |
  Applicant Name: |
  GREG HARRIS |
  Applicant Company: |
  DESOTO COUNTY UTILITIES |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/27/2025 |
  03/27/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/27/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DeSoto |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  JESSICA DOUGLAS |
  Application Number: |
  FL0027511-020-DW1P |
  Site Name: |
  William Tyson WWTP |
  Applicant Name: |
  Lee Snyder |
  Applicant Company: |
  Lee County Solid Waste Division |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/28/2025 |
  02/28/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/28/2025 |
  03/06/2025 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/06/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DeSoto |
  Permit Type: |
  Water - Domestic Wastewater Type III Wastewater Treatment Plant Permit |
  Permit Processor: |
  GABRIELA HASHER |
  Application Number: |
  FLA011953-008-DW3P |
  Site Name: |
  Sunrise MHP WWTP |
  Applicant Name: |
  Michael Strand |
  Applicant Company: |
  Sunrise Mobile Home Park |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/03/2025 |
  03/03/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/03/2025 |
  03/03/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/03/2025 |
  03/24/2025 |
  The Department is waiting for additional information from the permit applicant. |
  03/24/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTH DISTRICT |
  Florida County: |
  DeSoto |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Non-surface Water Discharge Permit |
  Permit Processor: |
  RICHARD BOENSCH |
  Application Number: |
  FLA119849-010-IW1N |
  Site Name: |
  Peace River Citrus Products, Inc |
  Applicant Name: |
  Bart Plymale |
  Applicant Company: |
  Bartow Citrus Products, LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/17/2025 |
  01/17/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/17/2025 |
  01/17/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/17/2025 |
  02/10/2025 |
  The Department is waiting for additional information from the permit applicant. |
  02/10/2025 |
  |
|