Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   DUVAL
  Permit Type:   Waste - Solid Waste Operation Permit
  Permit Processor:   PHIL CIARAVELLA
  Application Number:   0428373-001-SO
  Site Name:   WATER RECOVERY, LLC
  Applicant Name:   EDWARD MAYLON
  Applicant Company:   WATER RECOVERY LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/14/2022   11/14/2022
  The permit processor is verifying the permit application fee submitted is correct.   11/14/2022   11/16/2022
  The Department is reviewing the permit application to determine if it contains all required information.   11/14/2022   11/14/2022
  The Department is making an outcome determination regarding the permit application.   11/14/2022   02/08/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   02/08/2023   02/08/2023
  The Department's intent regarding the permit application was published.   02/08/2023  


Permitting Application Under Review
  FDEP Office:   NORTHEAST DISTRICT
  Florida County:   DUVAL
  Permit Type:   Waste - Solid Waste Operation Permit
  Permit Processor:   MICHAEL B. BOGIN
  Application Number:   0449689-001-SO
  Site Name:   JACKSONVILLE TRANSFER STATION
  Applicant Name:   TODD STRONG
  Applicant Company:   GFL SOLID WASTE SOUTHEAST LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   06/06/2024   06/06/2024
  The permit processor is verifying the permit application fee submitted is correct.   06/06/2024   06/08/2024
  The Department is reviewing the permit application to determine if it contains all required information.   06/06/2024   06/10/2024
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department.   06/08/2024   06/13/2024
  The Department is waiting for additional information from the permit applicant.   06/10/2024   06/13/2024
  The Department is waiting for the applicant to return of the original affidavit of proof of publication of the Notice of Application.   06/13/2024   06/13/2024
  The Department is reviewing the permit application to determine if it contains all required information.   06/13/2024