Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Escambia
  Permit Type:   Water - Industrial Wastewater Facility Permit
  Permit Processor:   BILL EVANS
  Application Number:   FL0002526-013-IWF
  Site Name:   International Paper Company - Pensacola Mill
  Applicant Name:   Gregory Munson
  Applicant Company:   Gunster - Tallahassee Office
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/24/2020   02/24/2020
  The permit processor is verifying the permit application fee submitted is correct.   02/24/2020   02/25/2020
  The Department is reviewing the permit application to determine if it contains all required information.   02/24/2020   04/24/2020
  The Department is waiting for additional information from the permit applicant.   04/24/2020   05/22/2020
  The Department is reviewing the permit application to determine if it contains all required information.   05/22/2020   07/21/2020
  The Department is making an outcome determination regarding the permit application.   05/22/2020