Skip Navigation

Permitting Application with Events Details


This data is current as of: Thursday, June 1, 2023


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0148407-014-UC
  Site Name:   D.L. TIPPIN WTP CLASS V UIC
  Applicant Name:   CHARLES WEBER
  Applicant Company:   CITY OF TAMPA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/27/2022   09/27/2022
  The permit processor is verifying the permit application fee submitted is correct.   09/27/2022   09/28/2022
  The Department is reviewing the permit application to determine if it contains all required information.   09/27/2022  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0373495-004-UC
  Site Name:   TAMPA ELECTRIC COMPANY BIG BEND STATION CLASS I UIC
  Applicant Name:   CARLOS ALDAZABAL
  Applicant Company:   TAMPA ELECTRIC COMPANY
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/16/2022   02/16/2022
  The permit processor is verifying the permit application fee submitted is correct.   02/16/2022   02/17/2022
  The Department is reviewing the permit application to determine if it contains all required information.   02/16/2022   01/20/2023
  The Department is waiting for additional information from the permit applicant.   01/20/2023   02/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   02/20/2023   04/18/2023
  The Department is making an outcome determination regarding the permit application.   02/20/2023   04/18/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   04/18/2023   04/18/2023
  The Department published the draft Permit notice.   04/18/2023   04/28/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   04/28/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0373495-005-UC
  Site Name:   TAMPA ELECTRIC COMPANY BIG BEND STATION CLASS I UIC
  Applicant Name:   CARLOS ALDAZABAL
  Applicant Company:   TAMPA ELECTRIC COMPANY
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/16/2022   02/16/2022
  The permit processor is verifying the permit application fee submitted is correct.   02/16/2022   02/23/2022
  The Department is reviewing the permit application to determine if it contains all required information.   02/16/2022   01/20/2023
  The Department is waiting for additional information from the permit applicant.   01/20/2023   02/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   02/20/2023   04/18/2023
  The Department is making an outcome determination regarding the permit application.   02/20/2023   04/18/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   04/18/2023   04/18/2023
  The Department published the draft Permit notice.   04/18/2023   04/28/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   04/28/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0411039-001-UC
  Site Name:   MEADE LAKE AR CLASS V UIC
  Applicant Name:   JAMES HUDOCK
  Applicant Company:   HILLSBOROUGH COUNTY CAPITAL PROGRAMS DEPT
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/10/2021   12/10/2021
  The permit processor is verifying the permit application fee submitted is correct.   12/10/2021   12/10/2021
  The Department is reviewing the permit application to determine if it contains all required information.   12/10/2021   09/15/2022
  The Department is waiting for additional information from the permit applicant.   09/15/2022   10/17/2022
  The Department is reviewing the permit application to determine if it contains all required information.   10/17/2022   01/09/2023
  The Department is waiting for additional information from the permit applicant.   01/09/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0415938-001-UC
  Site Name:   TAMPA TIPPIN WTF CLASS I UIC
  Applicant Name:   CHUCK WEBER
  Applicant Company:   CITY OF TAMPA WATER DEPARTMENT
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/02/2022   02/02/2022
  The permit processor is verifying the permit application fee submitted is correct.   02/02/2022   02/07/2022
  The Department is reviewing the permit application to determine if it contains all required information.   02/02/2022   10/24/2022
  The Department is waiting for additional information from the permit applicant.   10/24/2022   11/22/2022
  The Department is reviewing the permit application to determine if it contains all required information.   11/22/2022   04/13/2023
  The Department is making an outcome determination regarding the permit application.   11/22/2022   04/13/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   04/13/2023   04/13/2023
  The Department published the draft Permit notice.   04/13/2023   04/25/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   04/25/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0415938-002-UC
  Site Name:   TAMPA TIPPIN WTF CLASS I UIC
  Applicant Name:   CHUCK WEBER
  Applicant Company:   CITY OF TAMPA WATER DEPARTMENT
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/02/2022   02/02/2022
  The permit processor is verifying the permit application fee submitted is correct.   02/02/2022   02/07/2022
  The Department is reviewing the permit application to determine if it contains all required information.   02/02/2022   10/24/2022
  The Department is waiting for additional information from the permit applicant.   10/24/2022   11/22/2022
  The Department is reviewing the permit application to determine if it contains all required information.   11/22/2022   04/13/2023
  The Department is making an outcome determination regarding the permit application.   11/22/2022   04/13/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   04/13/2023   04/13/2023
  The Department published the draft Permit notice.   04/13/2023   04/25/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   04/25/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   HILLSBOROUGH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   GENE HONEYCUTT
  Application Number:   0415938-003-UC
  Site Name:   TAMPA TIPPIN WTF CLASS I UIC
  Applicant Name:   CHUCK WEBER
  Applicant Company:   CITY OF TAMPA WATER DEPARTMENT
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/02/2022   02/02/2022
  The permit processor is verifying the permit application fee submitted is correct.   02/02/2022   02/07/2022
  The Department is reviewing the permit application to determine if it contains all required information.   02/02/2022   10/24/2022
  The Department is waiting for additional information from the permit applicant.   10/24/2022   11/22/2022
  The Department is reviewing the permit application to determine if it contains all required information.   11/22/2022   04/13/2023
  The Department is making an outcome determination regarding the permit application.   11/22/2022   04/13/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   04/13/2023   04/13/2023
  The Department published the draft Permit notice.   04/13/2023   04/25/2023
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   04/25/2023