Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0373495-004-UC |
  Site Name: |
  TAMPA ELECTRIC COMPANY BIG BEND STATION CLASS I UIC |
  Applicant Name: |
  CARLOS ALDAZABAL |
  Applicant Company: |
  TAMPA ELECTRIC COMPANY |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/16/2022 |
  02/16/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/16/2022 |
  02/17/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/16/2022 |
  01/20/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/20/2023 |
  02/20/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/20/2023 |
  04/18/2023 |
  The Department is making an outcome determination regarding the permit application. |
  02/20/2023 |
  04/18/2023 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  04/18/2023 |
  04/18/2023 |
  The Department published the draft Permit notice. |
  04/18/2023 |
  04/28/2023 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  04/28/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0373495-005-UC |
  Site Name: |
  TAMPA ELECTRIC COMPANY BIG BEND STATION CLASS I UIC |
  Applicant Name: |
  CARLOS ALDAZABAL |
  Applicant Company: |
  TAMPA ELECTRIC COMPANY |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/16/2022 |
  02/16/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/16/2022 |
  02/23/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/16/2022 |
  01/20/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/20/2023 |
  02/20/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/20/2023 |
  04/18/2023 |
  The Department is making an outcome determination regarding the permit application. |
  02/20/2023 |
  04/18/2023 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  04/18/2023 |
  04/18/2023 |
  The Department published the draft Permit notice. |
  04/18/2023 |
  04/28/2023 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  04/28/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0411039-001-UC |
  Site Name: |
  MEADE LAKE AR CLASS V UIC |
  Applicant Name: |
  JAMES HUDOCK |
  Applicant Company: |
  HILLSBOROUGH COUNTY CAPITAL PROGRAMS DEPT |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/10/2021 |
  12/10/2021 |
  The permit processor is verifying the permit application fee submitted is correct. |
  12/10/2021 |
  12/10/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/10/2021 |
  09/15/2022 |
  The Department is waiting for additional information from the permit applicant. |
  09/15/2022 |
  10/17/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/17/2022 |
  01/09/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/09/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0415938-001-UC |
  Site Name: |
  TAMPA TIPPIN WTF CLASS I UIC |
  Applicant Name: |
  CHUCK WEBER |
  Applicant Company: |
  CITY OF TAMPA WATER DEPARTMENT |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/02/2022 |
  02/02/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/02/2022 |
  02/07/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/02/2022 |
  10/24/2022 |
  The Department is waiting for additional information from the permit applicant. |
  10/24/2022 |
  11/22/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/22/2022 |
  04/13/2023 |
  The Department is making an outcome determination regarding the permit application. |
  11/22/2022 |
  04/13/2023 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  04/13/2023 |
  04/13/2023 |
  The Department published the draft Permit notice. |
  04/13/2023 |
  04/25/2023 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  04/25/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0415938-002-UC |
  Site Name: |
  TAMPA TIPPIN WTF CLASS I UIC |
  Applicant Name: |
  CHUCK WEBER |
  Applicant Company: |
  CITY OF TAMPA WATER DEPARTMENT |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/02/2022 |
  02/02/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/02/2022 |
  02/07/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/02/2022 |
  10/24/2022 |
  The Department is waiting for additional information from the permit applicant. |
  10/24/2022 |
  11/22/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/22/2022 |
  04/13/2023 |
  The Department is making an outcome determination regarding the permit application. |
  11/22/2022 |
  04/13/2023 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  04/13/2023 |
  04/13/2023 |
  The Department published the draft Permit notice. |
  04/13/2023 |
  04/25/2023 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  04/25/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  TALLAHASSEE HEADQUARTERS |
  Florida County: |
  HILLSBOROUGH |
  Permit Type: |
  Water - Injection Well Construction Permit |
  Permit Processor: |
  GENE HONEYCUTT |
  Application Number: |
  0415938-003-UC |
  Site Name: |
  TAMPA TIPPIN WTF CLASS I UIC |
  Applicant Name: |
  CHUCK WEBER |
  Applicant Company: |
  CITY OF TAMPA WATER DEPARTMENT |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/02/2022 |
  02/02/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/02/2022 |
  02/07/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/02/2022 |
  10/24/2022 |
  The Department is waiting for additional information from the permit applicant. |
  10/24/2022 |
  11/22/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/22/2022 |
  04/13/2023 |
  The Department is making an outcome determination regarding the permit application. |
  11/22/2022 |
  04/13/2023 |
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others. |
  04/13/2023 |
  04/13/2023 |
  The Department published the draft Permit notice. |
  04/13/2023 |
  04/25/2023 |
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions. |
  04/25/2023 |
  |
|