Permitting Application with Events Details


This data is current as of: Tuesday, March 25, 2025


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   MONROE
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   NOLIN W MOON
  Application Number:   0269177-003-UC
  Site Name:   MARATHON AREA 4 WWTF UIC ONLY (WACS 99325)
  Applicant Name:   DANIEL SAUS
  Applicant Company:   CITY OF MARATHON
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/16/2022   03/16/2022
  The permit processor is verifying the permit application fee submitted is correct.   03/16/2022   03/25/2022
  The Department is waiting for the applicant to submit the requested additional fees.   03/25/2022   03/25/2022
  The permit processor is verifying the permit application fee submitted is correct.   03/25/2022   03/27/2022
  The Department is reviewing the permit application to determine if it contains all required information.   03/25/2022   04/18/2022
  The Department is waiting for additional information from the permit applicant.   04/18/2022   07/27/2022
  The Department is reviewing the permit application to determine if it contains all required information.   07/27/2022   07/27/2022
  The Department is making an outcome determination regarding the permit application.   07/27/2022  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   MONROE
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   NOLIN W MOON
  Application Number:   0277618-213-UC
  Site Name:   MARATHON AREA 3 COLLECTION SYSTEMS (FLA642851)
  Applicant Name:   DANIEL SAUS
  Applicant Company:   CITY OF MARATHON
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/18/2020   09/18/2020
  The permit processor is verifying the permit application fee submitted is correct.   09/18/2020   09/24/2020
  The Department is waiting for the applicant to submit the requested additional fees.   09/24/2020   09/24/2020
  The permit processor is verifying the permit application fee submitted is correct.   09/24/2020   09/24/2020
  The Department is reviewing the permit application to determine if it contains all required information.   09/24/2020   10/20/2020
  The Department is waiting for additional information from the permit applicant.   10/20/2020   08/13/2021
  The Department is reviewing the permit application to determine if it contains all required information.   08/13/2021   09/09/2021
  The Department is waiting for additional information from the permit applicant.   09/09/2021   06/30/2022
  The Department is reviewing the permit application to determine if it contains all required information.   06/30/2022   06/30/2022
  The Department is making an outcome determination regarding the permit application.   06/30/2022   11/21/2022
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   11/21/2022   11/21/2022
  The Department's intent regarding the permit application was published.   11/21/2022   12/10/2022
  The Department's Office of General Counsel received Third Party Petitions related to the permit.   12/10/2022