This data is current as of: Thursday, June 1, 2023


Permitting Application Under Review
  FDEP Office:   SOUTHEAST DISTRICT
  Florida County:   OKEECHOBEE
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   DAVID WHITE
  Application Number:   0138524-004-SFI
  Site Name:   FPL SWEATT SUBSTATION
  Applicant Name:   FRANCK LEBLANC
  Applicant Company:   FLORIDA POWER & LIGHT
  Agency Action:   Pending
  Link to Department’s Application File:   FPL SWEATT SUBSTATION
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/20/2023   03/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/20/2023   04/18/2023
  The Department is conducting a site investigation, if required   03/20/2023  
  The Department is waiting for additional information from the permit applicant.   04/18/2023   04/28/2023
  The Department is reviewing the permit application to determine if it contains all required information.   04/28/2023  
If you would like to comment on the pending application, please go here: Public Comment | DEP Business Portal (fldepportal.com)


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   OKEECHOBEE
  Permit Type:   Water - State 404 Individual Permit
  Permit Processor:   LUCY BRANDENBURG
  Application Number:   0421200-001-SFI
  Site Name:   SR 15 (US 441) AT SW 21ST ST
  Applicant Name:   BRENT SETCHELL
  Applicant Company:   FL DEPT OF TRANSPORTATION
  Agency Action:   Pending
  Link to Department’s Application File:   SR 15 (US 441) AT SW 21ST ST
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/19/2022   05/19/2022
  The Department is conducting a site investigation, if required   05/19/2022   08/31/2022
  The Department is reviewing the permit application to determine if it contains all required information.   05/19/2022   06/15/2022
  The Department is waiting for additional information from the permit applicant.   06/15/2022   03/22/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/22/2023   03/22/2023
  The Department published the public notice of the application after determining it contained all required items.   03/22/2023   04/12/2023
  The Department is waiting for the completion of the required comment period prior to continuing the permit application process.   04/12/2023   05/12/2023
  The Department is making an outcome determination regarding the permit application.   05/12/2023  