Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0166215-009-EI |
  Site Name: |
  WINTER GARDEN, CITY OF (ERP) |
  Applicant Name: |
  JON WILLIAMS |
  Applicant Company: |
  CITY OF WINTER GARDEN |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WINTER GARDEN, CITY OF (ERP) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/24/2024 |
  09/24/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/24/2024 |
  09/27/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/24/2024 |
  09/26/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/24/2024 |
  09/27/2024 |
  The Department is determining if the activity affects State Lands. |
  09/24/2024 |
  09/26/2024 |
  The Department is conducting a site investigation, if required |
  09/24/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  09/24/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  09/27/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  09/26/2024 |
  10/04/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0187635-014-EI |
  Site Name: |
  VISTA LF FKA BUTTREY DEV/KEENE RD LF-BORROW PIT (ERP) |
  Applicant Name: |
  DAVID MYHAN |
  Applicant Company: |
  VISTA LANDFILL LLC |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  VISTA LF FKA BUTTREY DEV/KEENE RD LF-BORROW PIT (ERP) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/28/2024 |
  08/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/28/2024 |
  08/30/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/28/2024 |
  08/30/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/28/2024 |
  08/30/2024 |
  The Department is determining if the activity affects State Lands. |
  08/28/2024 |
  08/30/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/28/2024 |
  08/30/2024 |
  The Department is conducting a site investigation, if required |
  08/28/2024 |
  09/27/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/30/2024 |
  11/12/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/12/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  08/30/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0205102-012-EI |
  Site Name: |
  OOCEA SR 408 WIDENING I-4 TO HIAWASSEE ROAD |
  Applicant Name: |
  GLENN PRESSIMONE |
  Applicant Company: |
  CENTRAL FLORIDA EXPRESSWAY AUTHORITY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  OOCEA SR 408 WIDENING I-4 TO HIAWASSEE ROAD |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/15/2024 |
  05/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/15/2024 |
  05/21/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/15/2024 |
  05/17/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  05/15/2024 |
  05/21/2024 |
  The Department is determining if the activity affects State Lands. |
  05/15/2024 |
  05/17/2024 |
  The Department is conducting a site investigation, if required |
  05/15/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  05/15/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  05/21/2024 |
  10/24/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  05/17/2024 |
  05/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/24/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0234306-020-EI |
  Site Name: |
  CFX-OOCEA/SR 417 (SWERP) |
  Applicant Name: |
  GLENN PRESSIMONE |
  Applicant Company: |
  CENTRAL FLORIDA EXPRESSWAY AUTHORITY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CFX-OOCEA/SR 417 (SWERP) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/15/2024 |
  05/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/15/2024 |
  05/21/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/15/2024 |
  05/17/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  05/15/2024 |
  05/21/2024 |
  The Department is determining if the activity affects State Lands. |
  05/15/2024 |
  05/17/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  05/15/2024 |
  |
  The Department is conducting a site investigation, if required |
  05/15/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  05/21/2024 |
  10/24/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  05/17/2024 |
  05/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/24/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JOHANNA PACKER |
  Application Number: |
  0237775-002-EI |
  Site Name: |
  ASHLEY (ERP) |
  Applicant Name: |
  TIMOTHY ASHLEY |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ASHLEY (ERP) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/02/2024 |
  08/02/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/02/2024 |
  08/06/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/02/2024 |
  08/06/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/02/2024 |
  08/06/2024 |
  The Department is determining if the activity affects State Lands. |
  08/02/2024 |
  08/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/02/2024 |
  08/06/2024 |
  The Department is conducting a site investigation, if required |
  08/02/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  08/06/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  MELANIE A WHARTON |
  Application Number: |
  0289412-001-EI |
  Site Name: |
  SHAPIRO, DARIN / KOROTEKEVICH, ALEXANDER AND ORLOV, DIMITRY |
  Applicant Name: |
  KIMBERLY PHAM |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  SHAPIRO, DARIN / KOROTEKEVICH, ALEXANDER AND ORLOV, DIMITRY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/22/2023 |
  11/22/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/22/2023 |
  12/14/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/22/2023 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  11/22/2023 |
  |
  The Department is determining if the activity affects State Lands. |
  11/22/2023 |
  |
  The Department is conducting a site investigation, if required |
  11/22/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  12/14/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0332538-007-EI |
  Site Name: |
  ORANGE COUNTY SOUTH WATER RECLAMATION FACILITY |
  Applicant Name: |
  MARK IKELER |
  Applicant Company: |
  ORANGE COUNTY UTILITIES |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ORANGE COUNTY SOUTH WATER RECLAMATION FACILITY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/06/2024 |
  11/06/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/06/2024 |
  11/13/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  11/06/2024 |
  11/08/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  11/06/2024 |
  11/13/2024 |
  The Department is determining if the activity affects State Lands. |
  11/06/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  11/06/2024 |
  11/07/2024 |
  The Department is conducting a site investigation, if required |
  11/06/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  11/13/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0413592-001-EI |
  Site Name: |
  OBERLY PARKWAY LOT 24 |
  Applicant Name: |
  FELIPE LOPEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  OBERLY PARKWAY LOT 24 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/10/2021 |
  12/10/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/10/2021 |
  01/07/2022 |
  The Department is determining if the activity affects State Lands. |
  12/10/2021 |
  |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/10/2021 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/07/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0420998-001-EI |
  Site Name: |
  BUDRON DALLAS BLVD RESIDENCE |
  Applicant Name: |
  VICTOR BUDRON |
  Applicant Company: |
  AAA CONSTRUCTION COMPANY |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  BUDRON DALLAS BLVD RESIDENCE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/13/2022 |
  05/13/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/13/2022 |
  06/10/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/13/2022 |
  |
  The Department is determining if the activity affects State Lands. |
  05/13/2022 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/10/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0426379-001-EI |
  Site Name: |
  PALMVIEW LOT 3 |
  Applicant Name: |
  LUIS BELLO |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PALMVIEW LOT 3 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/15/2022 |
  09/15/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/15/2022 |
  10/07/2022 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/15/2022 |
  09/17/2022 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/15/2022 |
  09/29/2022 |
  The Department is determining if the activity affects State Lands. |
  09/15/2022 |
  09/17/2022 |
  The Department is conducting a site investigation, if required |
  09/15/2022 |
  09/19/2022 |
  The Department is waiting for additional information from the permit applicant. |
  10/07/2022 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ZOEY C CARR |
  Application Number: |
  0427286-002-EI |
  Site Name: |
  1534 HOFFNER AVE [DOCK] |
  Applicant Name: |
  ALBERTO SANCHEZ DE FUENTES |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  1534 HOFFNER AVE [DOCK] |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/03/2024 |
  07/03/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/03/2024 |
  07/10/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  07/03/2024 |
  07/05/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  07/03/2024 |
  07/10/2024 |
  The Department is determining if the activity affects State Lands. |
  07/03/2024 |
  07/10/2024 |
  The Department is conducting a site investigation, if required |
  07/03/2024 |
  07/10/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  07/03/2024 |
  07/10/2024 |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  07/10/2024 |
  07/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  07/10/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0429692-001-EI |
  Site Name: |
  WEMBLEY AV (ERP / 404) |
  Applicant Name: |
  RANDALL THEVENET |
  Applicant Company: |
  ROB BRENT HOMES |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WEMBLEY AV (ERP / 404) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/21/2022 |
  12/21/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/21/2022 |
  01/19/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  12/21/2022 |
  12/23/2022 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  12/21/2022 |
  01/04/2023 |
  The Department is determining if the activity affects State Lands. |
  12/21/2022 |
  12/23/2022 |
  The Department is conducting a site investigation, if required |
  12/21/2022 |
  03/13/2023 |
  The Department is waiting for additional information from the permit applicant. |
  01/19/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  LEO ANGLERO |
  Application Number: |
  0438503-001-EI |
  Site Name: |
  FWC SPLIT OAK WMA |
  Applicant Name: |
  KATHERINE BURKE |
  Applicant Company: |
  FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FWC SPLIT OAK WMA |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/04/2023 |
  08/04/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/04/2023 |
  08/25/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/04/2023 |
  08/06/2023 |
  The Department is conducting a site investigation, if required |
  08/04/2023 |
  09/03/2023 |
  The Department is determining if the activity affects State Lands. |
  08/04/2023 |
  08/06/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/04/2023 |
  08/18/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/25/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ALEXANDRA K DAVIS |
  Application Number: |
  0438555-001-EI |
  Site Name: |
  VASQUEZ PROPERTY - LOT 09 |
  Applicant Name: |
  JUAN VASQUEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  VASQUEZ PROPERTY - LOT 09 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/07/2023 |
  08/07/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/07/2023 |
  08/24/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/07/2023 |
  08/09/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/07/2023 |
  08/21/2023 |
  The Department is determining if the activity affects State Lands. |
  08/07/2023 |
  08/09/2023 |
  The Department is conducting a site investigation, if required |
  08/07/2023 |
  |
  The Department is waiting for additional information from the permit applicant. |
  08/24/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0438557-001-EI |
  Site Name: |
  VASQUEZ MATA PROPERTY - LOT 10 |
  Applicant Name: |
  JUAN VASQUEZ |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  VASQUEZ MATA PROPERTY - LOT 10 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/07/2023 |
  08/07/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/07/2023 |
  08/31/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/07/2023 |
  08/09/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/07/2023 |
  08/21/2023 |
  The Department is determining if the activity affects State Lands. |
  08/07/2023 |
  08/09/2023 |
  The Department is conducting a site investigation, if required |
  08/07/2023 |
  09/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/31/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ALEXANDRA K DAVIS |
  Application Number: |
  0440389-001-EI |
  Site Name: |
  PALMVIEW STREET LOT 10, BLOCK 29 |
  Applicant Name: |
  LOUIS RAMOS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PALMVIEW STREET LOT 10, BLOCK 29 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/26/2023 |
  09/26/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/26/2023 |
  10/23/2023 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  09/26/2023 |
  09/28/2023 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/26/2023 |
  10/10/2023 |
  The Department is determining if the activity affects State Lands. |
  09/26/2023 |
  09/28/2023 |
  The Department is conducting a site investigation, if required |
  09/26/2023 |
  12/04/2023 |
  The Department is waiting for additional information from the permit applicant. |
  10/23/2023 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0443745-001-EI |
  Site Name: |
  LOT 3 OBERLY PARKWAY |
  Applicant Name: |
  FAISAL SHEIKH |
  Applicant Company: |
  CELEBRATION REAL ESTATE HOLDINGS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LOT 3 OBERLY PARKWAY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/05/2024 |
  01/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/05/2024 |
  01/23/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/05/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  01/05/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  01/05/2024 |
  |
  The Department is conducting a site investigation, if required |
  01/05/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/23/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JOHANNA PACKER |
  Application Number: |
  0443870-001-EI |
  Site Name: |
  LATTIMORE_ODHAMST23-080 |
  Applicant Name: |
  TONYE LATTIMORE |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LATTIMORE_ODHAMST23-080 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/09/2024 |
  01/09/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/09/2024 |
  01/23/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  01/09/2024 |
  01/22/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  01/09/2024 |
  01/22/2024 |
  The Department is determining if the activity affects State Lands. |
  01/09/2024 |
  03/21/2024 |
  The Department is conducting a site investigation, if required |
  01/09/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  01/23/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0444946-001-EI |
  Site Name: |
  LOT 4 CAVALIER STREET |
  Applicant Name: |
  FAISAL SHEIKH |
  Applicant Company: |
  CELEBRATION REAL ESTATE HOLDINGS |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LOT 4 CAVALIER STREET |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/06/2024 |
  02/06/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/06/2024 |
  03/05/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  02/06/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  02/06/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  02/06/2024 |
  |
  The Department is conducting a site investigation, if required |
  02/06/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  03/05/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  KATRINA SCHULTZ |
  Application Number: |
  0448456-001-EI |
  Site Name: |
  14346 ELLERBEE STREET |
  Applicant Name: |
  MICHAEL YOUNG |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  14346 ELLERBEE STREET |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/05/2024 |
  05/05/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/05/2024 |
  05/17/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/05/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  05/05/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  05/05/2024 |
  05/07/2024 |
  The Department is conducting a site investigation, if required |
  05/05/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  05/05/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  05/07/2024 |
  05/22/2024 |
  The Department is waiting for additional information from the permit applicant. |
  05/17/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANGELICA STERNER |
  Application Number: |
  0449302-001-EI |
  Site Name: |
  ZHANG RESIDENCE |
  Applicant Name: |
  CATHERINE BOWMAN |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  ZHANG RESIDENCE |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/28/2024 |
  05/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/28/2024 |
  06/03/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  05/28/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  05/28/2024 |
  06/03/2024 |
  The Department is determining if the activity affects State Lands. |
  05/28/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  05/28/2024 |
  06/03/2024 |
  The Department is conducting a site investigation, if required |
  05/28/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/03/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ALICIA H LOWENSTEIN |
  Application Number: |
  0449614-001-EI |
  Site Name: |
  WHISPERING PINES PLANTATION LLC |
  Applicant Name: |
  BROCK EVANS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  WHISPERING PINES PLANTATION LLC |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/04/2024 |
  06/04/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/04/2024 |
  06/14/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/04/2024 |
  06/06/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/04/2024 |
  06/17/2024 |
  The Department is determining if the activity affects State Lands. |
  06/04/2024 |
  06/06/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  06/04/2024 |
  06/06/2024 |
  The Department is conducting a site investigation, if required |
  06/04/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  06/14/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  06/06/2024 |
  06/20/2024 |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANGELICA STERNER |
  Application Number: |
  0449814-001-EI |
  Site Name: |
  CITY OF BELLE ISLE POLICE DOCK |
  Applicant Name: |
  KATE GRONINGER |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  CITY OF BELLE ISLE POLICE DOCK |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/11/2024 |
  06/11/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/11/2024 |
  06/18/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/11/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/11/2024 |
  06/19/2024 |
  The Department is determining if the activity affects State Lands. |
  06/11/2024 |
  06/13/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  06/11/2024 |
  06/13/2024 |
  The Department is conducting a site investigation, if required |
  06/11/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  06/13/2024 |
  06/20/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/18/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  JOHANNA PACKER |
  Application Number: |
  0450213-001-EI |
  Site Name: |
  STARRY STREET |
  Applicant Name: |
  MICHAEL BONNICK |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  STARRY STREET |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/21/2024 |
  06/21/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/21/2024 |
  06/24/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/21/2024 |
  06/24/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/21/2024 |
  06/24/2024 |
  The Department is determining if the activity affects State Lands. |
  06/21/2024 |
  06/24/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  06/21/2024 |
  06/24/2024 |
  The Department is conducting a site investigation, if required |
  06/21/2024 |
  07/10/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/24/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANGELICA STERNER |
  Application Number: |
  0450316-001-EI |
  Site Name: |
  PALMLAND STREET PROPERTY |
  Applicant Name: |
  CHAD VOLKERTS |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  PALMLAND STREET PROPERTY |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/25/2024 |
  06/25/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/25/2024 |
  07/02/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  06/25/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  06/25/2024 |
  06/28/2024 |
  The Department is determining if the activity affects State Lands. |
  06/25/2024 |
  |
  The Department is conducting a site investigation, if required |
  06/25/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  06/25/2024 |
  06/27/2024 |
  The Department is waiting for additional information from the permit applicant. |
  07/02/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ALEXANDRA K DAVIS |
  Application Number: |
  0452383-001-EI |
  Site Name: |
  DUKE ENERGY BUCK RD DISTRIBUTION LINE HDD |
  Applicant Name: |
  WILLIAM LINTON |
  Applicant Company: |
  DUKE ENERGY FLORIDA |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  DUKE ENERGY BUCK RD DISTRIBUTION LINE HDD |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/22/2024 |
  08/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/22/2024 |
  09/19/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/22/2024 |
  08/24/2024 |
  The Department is conducting a site investigation, if required |
  08/22/2024 |
  10/16/2024 |
  The Department is determining if the activity affects State Lands. |
  08/22/2024 |
  08/24/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/22/2024 |
  10/16/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/22/2024 |
  09/05/2024 |
  The Department is waiting for additional information from the permit applicant. |
  09/19/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  MELANIE A WHARTON |
  Application Number: |
  0452595-001-EI |
  Site Name: |
  FIGUEROA - RALSTON ST. (ERP) |
  Applicant Name: |
  OMAR FIGUEROA |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  FIGUEROA - RALSTON ST. (ERP) |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/26/2024 |
  08/26/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/26/2024 |
  09/09/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/26/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/26/2024 |
  |
  The Department is determining if the activity affects State Lands. |
  08/26/2024 |
  |
  The Department is providing notice of application to commenting agencies for review. |
  08/26/2024 |
  |
  The Department is conducting a site investigation, if required |
  08/26/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  09/09/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  ANGELICA STERNER |
  Application Number: |
  0452679-001-EI |
  Site Name: |
  LAKE SPIER |
  Applicant Name: |
  DONALD MARCOTTE |
  Applicant Company: |
  CITY OF WINTER PARK |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  LAKE SPIER |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/30/2024 |
  08/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/30/2024 |
  09/10/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  08/30/2024 |
  |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  08/30/2024 |
  09/04/2024 |
  The Department is determining if the activity affects State Lands. |
  08/30/2024 |
  09/01/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  08/30/2024 |
  09/01/2024 |
  The Department is conducting a site investigation, if required |
  08/30/2024 |
  |
  The Division of State Lands is conducting a Title determination to determine if the activity affects State Lands. |
  09/01/2024 |
  09/12/2024 |
  The Department is waiting for additional information from the permit applicant. |
  09/10/2024 |
  |
If you would like to comment on the pending application, please go here:
Public Comment | DEP Business Portal (fldepportal.com)
|
Permitting Application Under Review
|
  FDEP Office: |
  CENTRAL DISTRICT |
  Florida County: |
  ORANGE |
  Permit Type: |
  Water - Individual With No Conceptual Approval Permit |
  Permit Processor: |
  IMIRIO PEREZ |
  Application Number: |
  0454164-001-EI |
  Site Name: |
  RABON_OBERLYPKWY00-301 |
  Applicant Name: |
  NICHOLAS RABON |
  Applicant Company: |
  |
  Agency Action: |
  Pending |
  Link to Department’s Application File: |
  RABON_OBERLYPKWY00-301 |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/19/2024 |
  10/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/19/2024 |
  10/25/2024 |
  The Department is determining if the application is eligible for the State Programmatic General Permit (SPGP). |
  10/19/2024 |
  10/21/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  10/19/2024 |
  10/24/2024 |
  The Department is determining if the activity affects State Lands. |
  10/19/2024 |
  10/21/2024 |
  The Department is providing notice of application to commenting agencies for review. |
  10/19/2024 |
  10/21/2024 |
  The Department is conducting a site investigation, if required |
  10/19/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  10/25/2024 |
  |
If you would like to comment on the pending application, please go here: