Skip Navigation

Permitting Application with Events Details


This data is current as of: Thursday, June 1, 2023


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   PALM BEACH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   RUFUS L DICKEY
  Application Number:   0079933-011-UC
  Site Name:   WEST PALM BEACH WATER TREATMENT PLANT CLASS V ASR UIC
  Applicant Name:   VICTOR CAROSI
  Applicant Company:   CITY OF WEST PALM BEACH
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/13/2023   03/13/2023
  The permit processor is verifying the permit application fee submitted is correct.   03/13/2023   03/14/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/13/2023   04/11/2023
  The Department is waiting for additional information from the permit applicant.   04/11/2023   05/09/2023
  The Department is reviewing the permit application to determine if it contains all required information.   05/09/2023   05/18/2023
  The Department is waiting for additional information from the permit applicant.   05/18/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   PALM BEACH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   WALSTA JEANBAPTISTE
  Application Number:   0427899-001-UC
  Site Name:   DELRAY BEACH WTP IW UIC
  Applicant Name:   HASSAN HADJIMIRY
  Applicant Company:   CITY OF DELRAY BEACH
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/25/2022   10/25/2022
  The permit processor is verifying the permit application fee submitted is correct.   10/25/2022   10/27/2022
  The Department is reviewing the permit application to determine if it contains all required information.   10/25/2022   02/10/2023
  The Department is waiting for additional information from the permit applicant.   02/10/2023   03/13/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/13/2023   05/23/2023
  The Department is making an outcome determination regarding the permit application.   03/13/2023   05/23/2023
  The Department mailed the Public Notice for the draft Permit to the applicant and interested others.   05/23/2023   05/23/2023
  The Department published the draft Permit notice.   05/23/2023  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   PALM BEACH
  Permit Type:   Water - Injection Well Construction Permit
  Permit Processor:   WALSTA JEANBAPTISTE
  Application Number:   0430575-001-UC
  Site Name:   SUGAR CANE GROWERS COOPERATIVE CLASS I UIC
  Applicant Name:   ANTHONY MICHUDA
  Applicant Company:   SUGAR CANE GROWERS COOPERATIVE OF FLORIDA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   01/20/2023   01/20/2023
  The permit processor is verifying the permit application fee submitted is correct.   01/20/2023   01/22/2023
  The Department is reviewing the permit application to determine if it contains all required information.   01/20/2023   04/19/2023
  The Department is waiting for additional information from the permit applicant.   04/19/2023