This data is current as of: Monday, April 28, 2025


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Washington
  Permit Type:   Water - Domestic Wastewater Type III Wastewater Treatment Plant Permit
  Permit Processor:   BILL EVANS
  Application Number:   FLA010258-006-DW3P
  Site Name:   Sunny Hills WWTP
  Applicant Name:   Gary Deremer
  Applicant Company:   Sunny Hills Utility Company
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/24/2023   02/24/2023
  The permit processor is verifying the permit application fee submitted is correct.   02/24/2023   02/26/2023
  The Department is waiting for the applicant to submit the requested additional fees.   02/26/2023   03/29/2023
  The permit processor is verifying the permit application fee submitted is correct.   03/29/2023   03/30/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/29/2023   04/28/2023
  The Department is making an outcome determination regarding the permit application.   03/29/2023