Skip Navigation

Permitting Application with Events Details


This data is current as of: Friday, February 14, 2025


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Brevard
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   WILLIAM R GILLETT
  Application Number:   FLA010341-006-DW4P
  Site Name:   Holiday Village Travel Park WWTF
  Applicant Name:   Ian Hilpl
  Applicant Company:   Holiday Village RV Park, LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/30/2024   09/30/2024
  The permit processor is verifying the permit application fee submitted is correct.   09/30/2024   09/30/2024
  The Department is reviewing the permit application to determine if it contains all required information.   09/30/2024   10/04/2024
  The Department is waiting for additional information from the permit applicant.   10/04/2024  


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Osceola
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   MARGARITA A HERNANDEZ
  Application Number:   FLA010989-011-DW4P
  Site Name:   Lake Marian Paradise WWTF
  Applicant Name:   HEATH JOHNSON
  Applicant Company:   LAKE MARIAN RESORT, LLC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/03/2024   05/03/2024
  The permit processor is verifying the permit application fee submitted is correct.   05/03/2024   05/03/2024
  The Department is waiting for the applicant to submit the requested additional fees.   05/03/2024   05/06/2024
  The permit processor is verifying the permit application fee submitted is correct.   05/06/2024   05/06/2024
  The Department is reviewing the permit application to determine if it contains all required information.   05/06/2024   05/22/2024
  The Department is waiting for additional information from the permit applicant.   05/22/2024  


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Volusia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   WILLIAM R GILLETT
  Application Number:   FLA011185-006-DW4P
  Site Name:   Madeira Villa Condos North WWTF
  Applicant Name:   Roselle Johnson
  Applicant Company:   Madeira Villa N. Association, INC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   01/23/2025   01/23/2025
  The permit processor is verifying the permit application fee submitted is correct.   01/23/2025   01/25/2025
  The Department is waiting for the applicant to submit the requested additional fees.   01/25/2025   01/27/2025
  The permit processor is verifying the permit application fee submitted is correct.   01/27/2025   01/27/2025
  The Department is reviewing the permit application to determine if it contains all required information.   01/27/2025  


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Volusia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   MARGARITA A HERNANDEZ
  Application Number:   FLA011212-011-DW4P
  Site Name:   Sunny Sands Resort
  Applicant Name:   JOSEPH ARDOLINO
  Applicant Company:   TSTAM, LLC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/19/2023   12/19/2023
  The permit processor is verifying the permit application fee submitted is correct.   12/19/2023   12/19/2023
  The Department is waiting for the applicant to submit the requested additional fees.   12/19/2023   01/23/2024
  The permit processor is verifying the permit application fee submitted is correct.   01/23/2024   01/23/2024
  The Department is reviewing the permit application to determine if it contains all required information.   01/23/2024   02/08/2024
  The Department is waiting for additional information from the permit applicant.   02/08/2024   02/10/2025
  The Department is reviewing the permit application to determine if it contains all required information.   02/10/2025  


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Volusia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   WILLIAM R GILLETT
  Application Number:   FLA011228-007-DW4P
  Site Name:   Camino Real Apartments WWTF
  Applicant Name:   Madhu Parikh
  Applicant Company:   Camino Real Apartments
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/05/2023   09/05/2023
  The permit processor is verifying the permit application fee submitted is correct.   09/05/2023   09/05/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/05/2023   09/18/2023
  The Department is waiting for additional information from the permit applicant.   09/18/2023  


Permitting Application Under Review
  FDEP Office:   CENTRAL DISTRICT
  Florida County:   Volusia
  Permit Type:   Water - Domestic Wastewater Type III (less than 10,000 gpd) Wastewater Treatment Plant Permit
  Permit Processor:   MARGARITA A HERNANDEZ
  Application Number:   FLA011276-008-DW4P
  Site Name:   Hontoon Island State Park
  Applicant Name:   DAVID PACE
  Applicant Company:   FDEP DIVISION OF PARKS & RECREATION
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/16/2024   07/16/2024
  The permit processor is verifying the permit application fee submitted is correct.   07/16/2024   07/16/2024
  The Department is waiting for the applicant to submit the requested additional fees.   07/16/2024   09/03/2024
  The permit processor is verifying the permit application fee submitted is correct.   09/03/2024   09/03/2024
  The Department is reviewing the permit application to determine if it contains all required information.   09/03/2024   09/05/2024
  The Department is waiting for additional information from the permit applicant.   09/05/2024   01/23/2025
  The Department is reviewing the permit application to determine if it contains all required information.   01/23/2025   02/05/2025
  The Department is making an outcome determination regarding the permit application.   01/23/2025