Skip Navigation

Permitting Application with Events Details


This data is current as of: Wednesday, December 6, 2023


Permitting Application Under Review
  FDEP Office:   DADE COUNTY LOCAL PROGRAM
  Florida County:   MIAMI-DADE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ANTHONY RADHAY
  Application Number:   0250022-021-AC
  Site Name:   U S FOUNDRY COMPANY
  Applicant Name:   RICHARD FORTNEY
  Applicant Company:   U.S. FOUNDRY & MANUFACTURING CORP
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/11/2020   12/11/2020
  The permit processor is verifying the permit application fee submitted is correct.   12/11/2020   12/11/2020
  The Department is reviewing the permit application to determine if it contains all required information.   12/11/2020   01/08/2021
  The Department is waiting for additional information from the permit applicant.   01/08/2021   05/05/2021
  The Department is reviewing the permit application to determine if it contains all required information.   05/05/2021   06/04/2021
  The Department is making an outcome determination regarding the permit application.   05/05/2021   07/02/2021
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   07/02/2021   07/02/2021
  The Department's intent regarding the permit application was published.   07/02/2021  


Permitting Application Under Review
  FDEP Office:   DADE COUNTY LOCAL PROGRAM
  Florida County:   MIAMI-DADE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ANTHONY RADHAY
  Application Number:   0250615-027-AC
  Site Name:   MEDLEY LANDFILL
  Applicant Name:   JAMES MOORE
  Applicant Company:   WASTE MANAGEMENT INC. OF FLORIDA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/17/2023   05/17/2023
  The permit processor is verifying the permit application fee submitted is correct.   05/17/2023   05/18/2023
  The Department is reviewing the permit application to determine if it contains all required information.   05/17/2023   06/15/2023
  The Department is waiting for additional information from the permit applicant.   06/15/2023   10/06/2023
  The Department is reviewing the permit application to determine if it contains all required information.   10/06/2023   11/06/2023
  The Department is making an outcome determination regarding the permit application.   10/06/2023  


Permitting Application Under Review
  FDEP Office:   DADE COUNTY LOCAL PROGRAM
  Florida County:   MIAMI-DADE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ANTHONY RADHAY
  Application Number:   0250615-028-AC
  Site Name:   MEDLEY LANDFILL
  Applicant Name:   JAMES MOORE
  Applicant Company:   WASTE MANAGEMENT INC. OF FLORIDA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/20/2023   11/20/2023
  The permit processor is verifying the permit application fee submitted is correct.   11/20/2023   11/22/2023
  The Department is reviewing the permit application to determine if it contains all required information.   11/20/2023  


Permitting Application Under Review
  FDEP Office:   DADE COUNTY LOCAL PROGRAM
  Florida County:   MIAMI-DADE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ANTHONY RADHAY
  Application Number:   0251486-001-AC
  Site Name:   LEAR JET, INC.
  Applicant Name:   AARON DISNEY
  Applicant Company:   LEAR JET, INC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/30/2023   05/30/2023
  The permit processor is verifying the permit application fee submitted is correct.   05/30/2023   06/01/2023
  The Department is waiting for the applicant to submit the requested additional fees.   06/01/2023   06/23/2023
  The permit processor is verifying the permit application fee submitted is correct.   06/23/2023   06/25/2023
  The Department is reviewing the permit application to determine if it contains all required information.   06/23/2023   07/21/2023
  The Department is waiting for additional information from the permit applicant.   07/21/2023   10/17/2023
  The Department is reviewing the permit application to determine if it contains all required information.   10/17/2023   11/16/2023
  The Department is making an outcome determination regarding the permit application.   10/17/2023