Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  LESLIE MAYBIN |
  Application Number: |
  0310071-023-AV |
  Site Name: |
  IFF CHEMICAL HOLDINGS, INC. |
  Applicant Name: |
  RICHARD FRAIN |
  Applicant Company: |
  IFF CHEMICAL HOLDINGS, INC. |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/26/2024 |
  03/26/2024 |
  The Department is performing the initial completeness review. |
  03/26/2024 |
  03/26/2024 |
  The Department is waiting for additional information from the permit applicant. |
  05/20/2024 |
  10/28/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/28/2024 |
  11/22/2024 |
  The Department is making an outcome determination regarding the permit application. |
  10/28/2024 |
  12/02/2024 |
  The Department completed the draft permit. |
  12/02/2024 |
  12/02/2024 |
  The Department's intent regarding the permit application was published. |
  12/02/2024 |
  12/05/2024 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  12/05/2024 |
  01/11/2025 |
  The Department is waiting to see if there is a request for an administrative hearing received from the applicant, the general public or an affected third party. |
  01/14/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  KATIE O O'GARA |
  Application Number: |
  0310157-023-AV |
  Site Name: |
  CMC STEEL FLORIDA |
  Applicant Name: |
  STEVEN HUGHES |
  Applicant Company: |
  CMC STEEL US, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/16/2025 |
  01/16/2025 |
  The Department is performing the initial completeness review. |
  01/16/2025 |
  01/20/2025 |
  The Department is making an outcome determination regarding the permit application. |
  01/16/2025 |
  02/07/2025 |
  The Department completed the draft permit. |
  02/07/2025 |
  02/07/2025 |
  The Department's intent regarding the permit application was published. |
  02/07/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  LESLIE MAYBIN |
  Application Number: |
  0310197-022-AV |
  Site Name: |
  WHITEHOUSE LUMBER OPERATIONS |
  Applicant Name: |
  JAIRUS STEEL |
  Applicant Company: |
  WEST FRASER LAKE BUTLER DIVISION |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/09/2024 |
  12/09/2024 |
  The Department is performing the initial completeness review. |
  12/09/2024 |
  12/09/2024 |
  The Department is making an outcome determination regarding the permit application. |
  12/09/2024 |
  01/27/2025 |
  The Department completed the draft permit. |
  01/27/2025 |
  01/27/2025 |
  The Department's intent regarding the permit application was published. |
  01/27/2025 |
  01/30/2025 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  01/30/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  KATIE O O'GARA |
  Application Number: |
  0310215-074-AV |
  Site Name: |
  NAS-JACKSONVILLE |
  Applicant Name: |
  GREGORY DEWINDT |
  Applicant Company: |
  US NAVY |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/27/2025 |
  01/27/2025 |
  The Department is performing the initial completeness review. |
  01/27/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  KATIE O O'GARA |
  Application Number: |
  0310258-020-AV |
  Site Name: |
  BAE SYSTEMS JACKSONVILLE SHIP REPAIR LLC |
  Applicant Name: |
  TIMOTHY SPRATTO |
  Applicant Company: |
  BAE SYSTEMS JACKSONVILLE SHIP REPAIR |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/12/2025 |
  02/12/2025 |
  The Department is performing the initial completeness review. |
  02/12/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  LESLIE MAYBIN |
  Application Number: |
  0310341-014-AV |
  Site Name: |
  CHANCEY METALS, LLC |
  Applicant Name: |
  STEVE JENKINS |
  Applicant Company: |
  CHANCEY METALS, LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/04/2025 |
  02/04/2025 |
  The Department is performing the initial completeness review. |
  02/04/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  RITA FELTON |
  Application Number: |
  0310358-020-AV |
  Site Name: |
  TRAIL RIDGE LANDFILL |
  Applicant Name: |
  NINA SICKLER |
  Applicant Company: |
  CITY OF JACKSONVILLE |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/10/2024 |
  04/10/2024 |
  The Department is performing the initial completeness review. |
  04/10/2024 |
  06/04/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/05/2024 |
  11/26/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/26/2024 |
  12/09/2024 |
  The Department is making an outcome determination regarding the permit application. |
  11/26/2024 |
  12/10/2024 |
  The Department completed the draft permit. |
  12/10/2024 |
  12/17/2024 |
  The Department's intent regarding the permit application was published. |
  12/17/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  DUVAL |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  RITA FELTON |
  Application Number: |
  0310654-001-AV |
  Site Name: |
  TRAIL RIDGE RNG PROJECT |
  Applicant Name: |
  ROSS GROFFMAN |
  Applicant Company: |
  TRAIL RIDGE ENERGY, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/26/2024 |
  11/26/2024 |
  The Department is performing the initial completeness review. |
  11/26/2024 |
  12/10/2024 |
  The Department is making an outcome determination regarding the permit application. |
  11/26/2024 |
  12/10/2024 |
  The Department completed the draft permit. |
  12/10/2024 |
  12/17/2024 |
  The Department's intent regarding the permit application was published. |
  12/17/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  PUTNAM |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  LESLIE MAYBIN |
  Application Number: |
  1070039-038-AV |
  Site Name: |
  CERTAINTEED GYPSUM PALATKA |
  Applicant Name: |
  DEBBIE MASTER |
  Applicant Company: |
  CERTAINTEED GYPSUM PALATKA, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/12/2024 |
  11/12/2024 |
  The Department is performing the initial completeness review. |
  11/12/2024 |
  11/12/2024 |
  The Department is making an outcome determination regarding the permit application. |
  11/12/2024 |
  01/23/2025 |
  The Department completed the draft permit. |
  01/23/2025 |
  01/23/2025 |
  The Department's intent regarding the permit application was published. |
  01/23/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  NORTHEAST DISTRICT |
  Florida County: |
  SUWANNEE |
  Permit Type: |
  Air - Title V Operation Permit |
  Permit Processor: |
  RITA FELTON |
  Application Number: |
  1210468-011-AV |
  Site Name: |
  SUWANNEE MILL |
  Applicant Name: |
  DANIEL DORFER |
  Applicant Company: |
  BINDERHOLZ LIVE OAK, LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/01/2024 |
  10/01/2024 |
  The Department is performing the initial completeness review. |
  10/01/2024 |
  11/14/2024 |
  The Department is waiting for additional information from the permit applicant. |
  11/14/2024 |
  01/06/2025 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/06/2025 |
  01/21/2025 |
  The Department is making an outcome determination regarding the permit application. |
  01/06/2025 |
  01/28/2025 |
  The Department completed the draft permit. |
  01/28/2025 |
  01/28/2025 |
  The Department's intent regarding the permit application was published. |
  01/28/2025 |
  |
|