  Application Number:   0050009-051-AV
  Site Name:   HOLLINGSHEAD CEMENT FACILITY
  Applicant Name:   DANIELLE PUDVAH
  Applicant Company:   SMYRNA READY MIX CONCRETE, LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/07/2025   03/07/2025
  The Department is performing the initial completeness review.   03/07/2025   03/27/2025
  The Department is making an outcome determination regarding the permit application.   03/07/2025   04/04/2025
  The Department completed the draft permit.   04/04/2025   04/04/2025
  The Department's intent regarding the permit application was published.   04/04/2025   04/09/2025
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   04/09/2025   05/09/2025
  The proposed permit was completed, but is not yet issued.   04/08/2025   04/09/2025
  The Federal Environmental Protection Agency is reviewing the proposed permit.   04/09/2025  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   BAY
  Permit Type:   Air - Title V Operation Permit
  Permit Processor:   DOMINIC A BERTELLI
  Application Number:   0050102-003-AV
  Site Name:   PANAMA CITY PRODUCTION FACILITY
  Applicant Name:   WILLIAM LONG
  Applicant Company:   MOCAMA MARINE LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/01/2025   04/01/2025
  The Department is performing the initial completeness review.   04/01/2025   04/15/2025
  The Department is making an outcome determination regarding the permit application.   04/01/2025   04/17/2025
  The Department completed the draft permit.   04/17/2025   04/17/2025
  The Department's intent regarding the permit application was published.   04/17/2025  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   ESCAMBIA
  Permit Type:   Air - Title V Operation Permit
  Permit Processor:   HOWARD ARD
  Application Number:   0330040-078-AV
  Site Name:   ASCEND PENSACOLA PLANT
  Applicant Name:   KEVIN HEISEL
  Applicant Company:   ASCEND PERFORMANCE MATERIALS OPERATIONS, LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/14/2024   11/14/2024
  The Department is performing the initial completeness review.   11/14/2024   11/20/2024
  The Department is waiting for additional information from the permit applicant.   11/20/2024   03/20/2025
  The Department is reviewing the permit application to determine if it contains all required information.   03/20/2025   03/20/2025
  The Department is making an outcome determination regarding the permit application.   03/20/2025   04/08/2025
  The Department completed the draft permit.   04/08/2025   04/08/2025
  The Department's intent regarding the permit application was published.   04/08/2025   04/21/2025
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   04/21/2025  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   SANTA ROSA
  Permit Type:   Air - Title V Operation Permit
  Permit Processor:   HOWARD ARD
  Application Number:   1130004-046-AV
  Site Name:   TAMINCO PACE SITE
  Applicant Name:   SHANE FOWLER
  Applicant Company:   TAMINCO US LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/24/2025   02/24/2025
  The Department is performing the initial completeness review.   02/24/2025   03/10/2025
  The Department is making an outcome determination regarding the permit application.   02/24/2025   03/17/2025
  The Department completed the draft permit.   03/17/2025   03/17/2025
  The Department's intent regarding the permit application was published.   03/17/2025   03/21/2025
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   03/21/2025   04/20/2025
  The proposed permit was completed, but is not yet issued.   04/20/2025   04/22/2025
  The Federal Environmental Protection Agency is reviewing the proposed permit.   04/22/2025