Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Jackson
  Permit Type:   Water - Industrial Wastewater Concrete Batch Plant Permit
  Permit Processor:   CHARLES HARRELL
  Application Number:   FLG110433-006-IWCB
  Site Name:   Ready Mix USA - Marianna Plant
  Applicant Name:   Ronnie Robinette
  Applicant Company:   Ready Mix USA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   01/30/2024   01/30/2024
  The permit processor is verifying the permit application fee submitted is correct.   01/30/2024   01/30/2024
  The Department is waiting for the applicant to submit the requested additional fees.   01/30/2024   02/01/2024
  The permit processor is verifying the permit application fee submitted is correct.   02/01/2024   02/03/2024
  The Department is reviewing the permit application to determine if it contains all required information.   02/01/2024   02/01/2024
  The Department is making an outcome determination regarding the permit application.   02/01/2024  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Franklin
  Permit Type:   Water - Industrial Wastewater Concrete Batch Plant Permit
  Permit Processor:   CHARLES HARRELL
  Application Number:   FLG110600-008-IWCB
  Site Name:   Smyrna Ready Mix - Plant #106
  Applicant Name:   Jeff Hollingshead
  Applicant Company:   Smyrna Ready Mix Concrete LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/28/2023   07/28/2023
  The permit processor is verifying the permit application fee submitted is correct.   07/28/2023   07/28/2023
  The Department is waiting for the applicant to submit the requested additional fees.   07/28/2023  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Walton
  Permit Type:   Water - Industrial Wastewater Concrete Batch Plant Permit
  Permit Processor:   CHARLES HARRELL
  Application Number:   FLG110639-005-IWCB
  Site Name:   Fort Walton Concrete - Freeport
  Applicant Name:   James Campbell
  Applicant Company:   Fort Walton Concrete, Inc
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/15/2024   03/15/2024
  The permit processor is verifying the permit application fee submitted is correct.   03/15/2024   03/15/2024
  The Department is waiting for the applicant to submit the requested additional fees.   03/15/2024   03/15/2024
  The permit processor is verifying the permit application fee submitted is correct.   03/15/2024   05/09/2024
  The Department is reviewing the permit application to determine if it contains all required information.   03/15/2024   05/09/2024
  The Department is making an outcome determination regarding the permit application.   03/15/2024   05/10/2024
  The permit is effective.   03/15/2024  


Permitting Application Under Review
  FDEP Office:   NORTHWEST DISTRICT
  Florida County:   Walton
  Permit Type:   Water - Industrial Wastewater Concrete Batch Plant Permit
  Permit Processor:   CHARLES HARRELL
  Application Number:   FLG110971-001-IWCB
  Site Name:   Ready Mix USA - Freeport Plant
  Applicant Name:   Ronnie Robinette
  Applicant Company:   Ready Mix USA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/11/2022   05/11/2022
  The permit processor is verifying the permit application fee submitted is correct.   05/11/2022   05/11/2022
  The Department is waiting for the applicant to submit the requested additional fees.   05/11/2022   05/13/2022
  The permit processor is verifying the permit application fee submitted is correct.   05/13/2022   05/13/2022
  The Department is reviewing the permit application to determine if it contains all required information.   05/13/2022   05/13/2022
  The Department is waiting for additional information from the permit applicant.   05/13/2022