Skip Navigation

Permitting Application with Events Details


This data is current as of: Wednesday, December 6, 2023


Permitting Application Under Review
  FDEP Office:   ORANGE COUNTY LOCAL PROGRAM
  Florida County:   ORANGE
  Permit Type:   Air - Construction Permit
  Permit Processor:   STEPHEN AMIRAULT
  Application Number:   0950055-011-AC
  Site Name:   ICS-FL DRUM RECONDITIONING FACILITY
  Applicant Name:   MIKE OSBORNE
  Applicant Company:   INDUSTRIAL CONTAINER SERVICES - FL, LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/17/2023   03/17/2023
  The permit processor is verifying the permit application fee submitted is correct.   03/17/2023   03/19/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/17/2023   04/04/2023
  The Department is waiting for additional information from the permit applicant.   04/04/2023   09/05/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/05/2023   10/06/2023
  The Department is making an outcome determination regarding the permit application.   09/05/2023   11/13/2023


Permitting Application Under Review
  FDEP Office:   ORANGE COUNTY LOCAL PROGRAM
  Florida County:   ORANGE
  Permit Type:   Air - Construction Permit
  Permit Processor:   STEPHEN AMIRAULT
  Application Number:   0951247-020-AC
  Site Name:   REV AMBULANCE GROUP ORLANDO, INC.
  Applicant Name:   ERIK STOOR
  Applicant Company:   REV AMBULANCE GROUP, INC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/01/2023   12/01/2023
  The permit processor is verifying the permit application fee submitted is correct.   12/01/2023  


Permitting Application Under Review
  FDEP Office:   ORANGE COUNTY LOCAL PROGRAM
  Florida County:   ORANGE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ROV N CHURAMAN
  Application Number:   0951249-014-AC
  Site Name:   CELLOFOAM NORTH AMERICA INC
  Applicant Name:   TOM LA GRASSA
  Applicant Company:   CELLOFOAM NORTH AMERICA, INC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/05/2023   10/05/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/05/2023   10/07/2023
  The Department is reviewing the permit application to determine if it contains all required information.   10/05/2023   10/05/2023
  The Department is making an outcome determination regarding the permit application.   10/05/2023  


Permitting Application Under Review
  FDEP Office:   ORANGE COUNTY LOCAL PROGRAM
  Florida County:   ORANGE
  Permit Type:   Air - Construction Permit
  Permit Processor:   ROV N CHURAMAN
  Application Number:   0951282-008-AC
  Site Name:   TOUFAYAN BAKERY
  Applicant Name:   GREGORY TOUFAYAN
  Applicant Company:   TOUFAYAN BAKERIES OF FLORIDA, INC.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/26/2023   10/26/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/26/2023   10/27/2023
  The Department is reviewing the permit application to determine if it contains all required information.   10/26/2023   10/26/2023
  The Department is making an outcome determination regarding the permit application.   10/26/2023  


Permitting Application Under Review
  FDEP Office:   ORANGE COUNTY LOCAL PROGRAM
  Florida County:   ORANGE
  Permit Type:   Air - Construction Permit
  Permit Processor:   STEPHEN AMIRAULT
  Application Number:   0951411-001-AC
  Site Name:   AG CARBON SOLUTIONS - YOUNG PINE RD
  Applicant Name:   JAMES MEADE
  Applicant Company:   AG CARBON SOLUTIONS LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/26/2023   04/26/2023
  The permit processor is verifying the permit application fee submitted is correct.   04/26/2023   04/28/2023
  The Department is reviewing the permit application to determine if it contains all required information.   04/26/2023   04/26/2023
  The Department is waiting for additional information from the permit applicant.   05/25/2023   09/14/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/14/2023   10/10/2023
  The Department is waiting for additional information from the permit applicant.   10/10/2023