Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  EDGAR GUERRONOREJUELA |
  Application Number: |
  FL0027600-025-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Ft Green Mine Complex |
  Applicant Name: |
  Pat Kane |
  Applicant Company: |
  Mosaic Fertilizer, L.L.C. |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/19/2018 |
  12/19/2018 |
  The permit processor is verifying the permit application fee submitted is correct. |
  12/19/2018 |
  12/19/2018 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/19/2018 |
  01/15/2019 |
  The Department is waiting for additional information from the permit applicant. |
  01/15/2019 |
  02/07/2019 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/07/2019 |
  02/07/2019 |
  The Department is making an outcome determination regarding the permit application. |
  02/07/2019 |
  11/19/2021 |
  The Department is preparing the permit documents. |
  02/07/2019 |
  11/19/2021 |
  The Department published the Notice of Intent to Issue the permit. |
  11/19/2021 |
  12/02/2021 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  11/19/2021 |
  11/19/2021 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  11/19/2021 |
  12/24/2021 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  11/19/2021 |
  12/19/2021 |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DIEGA GRAVE DE PERALTA |
  Application Number: |
  FL0030139-015-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Nichols Concentrates |
  Applicant Name: |
  |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/26/2023 |
  07/26/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  07/26/2023 |
  07/26/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/26/2023 |
  08/24/2023 |
  The Department is waiting for additional information from the permit applicant. |
  08/24/2023 |
  09/20/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/20/2023 |
  10/10/2023 |
  The Department is making an outcome determination regarding the permit application. |
  09/20/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Manatee |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  GORDON P D'ABREU |
  Application Number: |
  FL0032522-014-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Wingate Creek Mine |
  Applicant Name: |
  Santino Provenzano |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/24/2022 |
  05/24/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  05/24/2022 |
  05/26/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/24/2022 |
  06/28/2022 |
  The Department is making an outcome determination regarding the permit application. |
  05/24/2022 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DIEGA GRAVE DE PERALTA |
  Application Number: |
  FL0033332-021-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Lonesome Mine |
  Applicant Name: |
  |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/12/2023 |
  06/12/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  06/12/2023 |
  06/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/12/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hardee |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  JESSICA M PEIN |
  Application Number: |
  FL0035271-010-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Hardee North Pasture Mine |
  Applicant Name: |
  Keith Nadaskay |
  Applicant Company: |
  Mosaic Fertilizer LLC North Pasture |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/04/2022 |
  11/04/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  11/04/2022 |
  11/04/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/04/2022 |
  11/29/2022 |
  The Department is making an outcome determination regarding the permit application. |
  11/04/2022 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  AMAURY P BETANCOURT |
  Application Number: |
  FL0036421-022-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - New Wales Concentrates |
  Applicant Name: |
  Santino Provenzano |
  Applicant Company: |
  Mosaic Fertilizer - Bartow |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/25/2019 |
  10/25/2019 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/25/2019 |
  10/25/2019 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/25/2019 |
  12/02/2019 |
  The Department is waiting for additional information from the permit applicant. |
  12/02/2019 |
  01/29/2020 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/29/2020 |
  03/11/2020 |
  The Department is waiting for additional information from the permit applicant. |
  03/11/2020 |
  12/22/2020 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/22/2020 |
  12/22/2020 |
  The Department is making an outcome determination regarding the permit application. |
  12/22/2020 |
  05/14/2021 |
  The Department is preparing the permit documents. |
  12/22/2020 |
  05/14/2021 |
  The Department published the Notice of Intent to Issue the permit. |
  05/14/2021 |
  05/19/2021 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  05/14/2021 |
  05/14/2021 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  05/14/2021 |
  06/18/2021 |
  The Department published a Notice of Intent to hold a Public Meeting regarding issuing the permit. |
  06/18/2021 |
  07/22/2021 |
  The Department held a Public Meeting related to the permit. |
  07/22/2021 |
  08/25/2021 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  05/14/2021 |
  06/14/2021 |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DIEGA GRAVE DE PERALTA |
  Application Number: |
  FL0036421-023-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - New Wales Concentrates |
  Applicant Name: |
  Santino Provenzano |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/31/2023 |
  01/31/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/31/2023 |
  01/31/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/31/2023 |
  03/02/2023 |
  The Department is waiting for additional information from the permit applicant. |
  03/02/2023 |
  04/10/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/10/2023 |
  05/03/2023 |
  The Department is making an outcome determination regarding the permit application. |
  04/10/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  GORDON P D'ABREU |
  Application Number: |
  FL0037958-023-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - South Ft Meade Mine |
  Applicant Name: |
  Ben Koplin |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/14/2022 |
  10/14/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/14/2022 |
  10/14/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/14/2022 |
  11/14/2022 |
  The Department is waiting for additional information from the permit applicant. |
  11/14/2022 |
  12/14/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/14/2022 |
  12/14/2022 |
  The Department is waiting for additional information from the permit applicant. |
  12/14/2022 |
  01/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  01/12/2023 |
  01/12/2023 |
  The Department is making an outcome determination regarding the permit application. |
  01/12/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DIEGA GRAVE DE PERALTA |
  Application Number: |
  FL0038652-010-IW1S |
  Site Name: |
  Yara North America, Inc. - Port Sutton Ammonia Terminal |
  Applicant Name: |
  Craig King |
  Applicant Company: |
  Yara North America Inc |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/20/2022 |
  09/20/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/20/2022 |
  09/20/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/20/2022 |
  10/13/2022 |
  The Department is waiting for additional information from the permit applicant. |
  10/13/2022 |
  10/28/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/28/2022 |
  11/21/2022 |
  The Department is making an outcome determination regarding the permit application. |
  10/28/2022 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hardee |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DENNIS PIERSON |
  Application Number: |
  FL0040177-033-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Hardee South Pasture Mine |
  Applicant Name: |
  Santino Provenzano |
  Applicant Company: |
  Mosaic Fertilizer - Bartow |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/24/2019 |
  10/24/2019 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/24/2019 |
  10/24/2019 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/24/2019 |
  11/21/2019 |
  The Department is waiting for additional information from the permit applicant. |
  11/21/2019 |
  12/19/2019 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/19/2019 |
  01/15/2020 |
  The Department is making an outcome determination regarding the permit application. |
  12/19/2019 |
  11/22/2021 |
  The Department is preparing the permit documents. |
  12/19/2019 |
  11/22/2021 |
  The Department published the Notice of Intent to Issue the permit. |
  11/22/2021 |
  12/02/2021 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  11/22/2021 |
  11/22/2021 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  11/22/2021 |
  12/22/2021 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  11/22/2021 |
  12/27/2021 |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  EVELYN SARDINAS |
  Application Number: |
  FL0132381-006-IW1S |
  Site Name: |
  Cytec Industries, Inc - Brewster Plant |
  Applicant Name: |
  |
  Applicant Company: |
  Cytec Industries, Inc. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  07/13/2023 |
  07/13/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  07/13/2023 |
  07/13/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/13/2023 |
  07/13/2023 |
  The Department is waiting for additional information from the permit applicant. |
  07/13/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  GORDON P D'ABREU |
  Application Number: |
  FL0160083-005-IW1S |
  Site Name: |
  Estech, Inc - Agricola Plant |
  Applicant Name: |
  John Garlanger |
  Applicant Company: |
  Ardaman & Associates |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/30/2023 |
  10/30/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/30/2023 |
  10/30/2023 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  10/30/2023 |
  11/06/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  11/06/2023 |
  11/06/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/06/2023 |
  11/06/2023 |
  The Department is waiting for additional information from the permit applicant. |
  11/06/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  JESSICA M PEIN |
  Application Number: |
  FL0177130-009-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Riverview Closed Gyp Stack |
  Applicant Name: |
  Kristi Farrell |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/16/2023 |
  11/16/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  11/16/2023 |
  11/16/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/16/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  DIEGA GRAVE DE PERALTA |
  Application Number: |
  FL0178527-009-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - New Wales Gyp Stack Closure |
  Applicant Name: |
  Kristi Farrell |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/03/2023 |
  04/03/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  04/03/2023 |
  04/03/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/03/2023 |
  05/02/2023 |
  The Department is making an outcome determination regarding the permit application. |
  04/03/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  JESSICA M PEIN |
  Application Number: |
  FL0334944-008-IW1S |
  Site Name: |
  Mulberry Phosphogypsum Stack System Closure |
  Applicant Name: |
  Kristi Farrell |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/31/2023 |
  10/31/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/31/2023 |
  11/01/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/31/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  SCOTT ROSE |
  Application Number: |
  FL0757501-004-IW1S |
  Site Name: |
  Mosaic Fertilizer LLC - TMDL Aggregate TN |
  Applicant Name: |
  Kristi Farrell |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  10/11/2022 |
  10/11/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  10/11/2022 |
  10/11/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/11/2022 |
  11/14/2022 |
  The Department is making an outcome determination regarding the permit application. |
  10/11/2022 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  JESSICA M PEIN |
  Application Number: |
  FLA012553-003-IW1S |
  Site Name: |
  Mosaic Fertilizer, L.L.C. - Big Bend Terminal |
  Applicant Name: |
  Kristi Farrell |
  Applicant Company: |
  Mosaic Fertilizer, L.L.C. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/17/2022 |
  11/17/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  11/17/2022 |
  11/17/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  11/17/2022 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Industrial Wastewater Group 1, Surface Water Discharge Permit |
  Permit Processor: |
  JESSICA M PEIN |
  Application Number: |
  FLA177610-010-IW1S |
  Site Name: |
  Mosaic Fertilizer, LLC - Plant City Closed Gypsum Stack |
  Applicant Name: |
  |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  06/12/2023 |
  06/12/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  06/12/2023 |
  06/12/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  06/12/2023 |
  |
|