  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/15/2022 |
  08/15/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  08/15/2022 |
  08/15/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/15/2022 |
  08/15/2022 |
  The Department is making an outcome determination regarding the permit application. |
  08/15/2022 |
  08/19/2022 |
  The Department is preparing the permit revision documents. |
  08/15/2022 |
  08/19/2022 |
  The Department issued a revision to an existing permit and filed the related permit information about the site and the applicant. |
  08/19/2022 |
  08/19/2022 |
  The Department issued the permit and filed the related permit information about the site and the applicant. |
  08/19/2022 |
  08/19/2022 |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 10B - Other Facility Permit |
  Permit Processor: |
  GORDON P D'ABREU |
  Application Number: |
  FL0001589-026-IWB |
  Site Name: |
  Mosaic Fertilizer, LLC - Bartow Chemical Plant |
  Applicant Name: |
  Santino Provenzano |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  02/02/2021 |
  02/02/2021 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/02/2021 |
  02/02/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/02/2021 |
  02/02/2021 |
  The Department is waiting for additional information from the permit applicant. |
  02/02/2021 |
  02/25/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/25/2021 |
  02/25/2021 |
  The Department is waiting for additional information from the permit applicant. |
  02/25/2021 |
  03/25/2021 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/25/2021 |
  03/25/2021 |
  The Department is making an outcome determination regarding the permit application. |
  03/25/2021 |
  03/25/2021 |
  The Department is preparing the permit revision documents. |
  03/25/2021 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 10B - Other Facility Permit |
  Permit Processor: |
  JULIO CABRERA |
  Application Number: |
  FL0037958-027-IWB |
  Site Name: |
  Mosaic Fertilizer, LLC - South Ft Meade Mine |
  Applicant Name: |
  Ben Koplin |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  05/31/2023 |
  05/31/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  05/31/2023 |
  05/31/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/31/2023 |
  06/29/2023 |
  The Department is waiting for additional information from the permit applicant. |
  06/29/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  PHOSPHATE MANAGEMENT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Industrial Wastewater Group 10B - Other Facility Permit |
  Permit Processor: |
  GORDON P D'ABREU |
  Application Number: |
  FL0037958-028-IWB |
  Site Name: |
  Mosaic Fertilizer, LLC - South Ft Meade Mine |
  Applicant Name: |
  |
  Applicant Company: |
  Mosaic Fertilizer LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/05/2023 |
  12/05/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |