Permitting Application with Events Details


This data is current as of: Friday, May 23, 2025


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   JESSICA M PEIN
  Application Number:   FL0000370-019-IW1S
  Site Name:   Mosaic Fertilizer, LLC - South Pierce Concentrates
  Applicant Name:   Kristi Farrell
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/14/2023   02/14/2023
  The permit processor is verifying the permit application fee submitted is correct.   02/14/2023   02/14/2023
  The Department is reviewing the permit application to determine if it contains all required information.   02/14/2023   03/16/2023
  The Department is making an outcome determination regarding the permit application.   02/14/2023  
  The Department is waiting for additional information from the permit applicant.   03/16/2023  
  The Department is reviewing the permit application to determine if it contains all required information.   09/05/2023  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Hillsborough
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   ANTHONY ANNIBALI
  Application Number:   FL0000761-020-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Riverview Chemical Plant
  Applicant Name:   Pat Kane
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/10/2019   05/10/2019
  The permit processor is verifying the permit application fee submitted is correct.   05/10/2019   05/13/2019
  The Department is reviewing the permit application to determine if it contains all required information.   05/10/2019   05/31/2019
  The Department is waiting for additional information from the permit applicant.   05/31/2019   08/19/2019
  The Department is reviewing the permit application to determine if it contains all required information.   08/19/2019   08/19/2019
  The Department is making an outcome determination regarding the permit application.   08/19/2019   08/19/2019
  The Department is preparing the permit documents.   08/19/2019   04/08/2020
  The permit was issued.   04/08/2020  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Hillsborough
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   JESSICA M PEIN
  Application Number:   FL0000761-023-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Riverview Chemical Plant
  Applicant Name:  
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/20/2023   07/20/2023
  The permit processor is verifying the permit application fee submitted is correct.   07/20/2023   07/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   07/20/2023   08/19/2023
  The Department is making an outcome determination regarding the permit application.   07/20/2023  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   JESSICA M PEIN
  Application Number:   FL0001589-028-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Bartow Chemical Plant
  Applicant Name:   Kristi Farrell
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/10/2025   02/10/2025
  The permit processor is verifying the permit application fee submitted is correct.   02/10/2025   02/10/2025
  The Department is reviewing the permit application to determine if it contains all required information.   02/10/2025   03/07/2025
  The Department is waiting for additional information from the permit applicant.   03/07/2025   03/24/2025
  The Department is reviewing the permit application to determine if it contains all required information.   03/24/2025   04/14/2025
  The Department is making an outcome determination regarding the permit application.   03/24/2025  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   DENNIS PIERSON
  Application Number:   FL0001902-020-IW1S
  Site Name:   U S Agri-Chemicals Corporation - Ft Meade Chemical Plant
  Applicant Name:   Susanne Allen
  Applicant Company:   US Agri Chemicals Corp
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/16/2019   12/16/2019
  The permit processor is verifying the permit application fee submitted is correct.   12/16/2019   12/16/2019
  The Department is reviewing the permit application to determine if it contains all required information.   12/16/2019   01/15/2020
  The Department is waiting for additional information from the permit applicant.   01/15/2020   02/18/2020
  The Department is reviewing the permit application to determine if it contains all required information.   02/18/2020   03/18/2020
  The Department is making an outcome determination regarding the permit application.   02/18/2020   03/18/2020
  The Department is preparing the permit documents.   02/18/2020  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   DERRICK S HUDSON
  Application Number:   FL0001961-009-IW1S
  Site Name:   U S Agri-Chemicals Corporation - Bartow Chemical Plant
  Applicant Name:   Susanne Allen
  Applicant Company:   U.S. Agri-Chemicals Corporation
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/16/2021   04/16/2021
  The permit processor is verifying the permit application fee submitted is correct.   04/16/2021   04/16/2021
  The Department is reviewing the permit application to determine if it contains all required information.   04/16/2021   05/13/2021
  The Department is waiting for additional information from the permit applicant.   05/13/2021   06/07/2021
  The Department is reviewing the permit application to determine if it contains all required information.   06/07/2021   10/04/2021
  The Department is making an outcome determination regarding the permit application.   06/07/2021   12/12/2024
  The Department is preparing the permit documents.   06/07/2021   12/12/2024
  The Department published the Notice of Intent to Issue the permit.   12/12/2024   12/26/2024
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   12/12/2024   12/12/2024
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   12/12/2024   01/11/2025
  The Federal Environmental Protection Agency is reviewing the permit.   12/12/2024   01/16/2025
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   01/11/2025   04/18/2025
  The Department's intent regarding the permit application was published.   04/18/2025   04/30/2025
  The permit was issued.   04/30/2025  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Hardee
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   JESSICA M PEIN
  Application Number:   FL0035271-010-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Hardee North Pasture Mine
  Applicant Name:   Keith Nadaskay
  Applicant Company:   Mosaic Fertilizer LLC North Pasture
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/04/2022   11/04/2022
  The permit processor is verifying the permit application fee submitted is correct.   11/04/2022   11/04/2022
  The Department is reviewing the permit application to determine if it contains all required information.   11/04/2022   11/29/2022
  The Department is making an outcome determination regarding the permit application.   11/04/2022  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Manatee
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   DIEGO GRAVE DE PERALTA
  Application Number:   FL0036412-041-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Four Corners Mine
  Applicant Name:   Ryan Thomas
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   05/08/2025   05/08/2025
  The permit processor is verifying the permit application fee submitted is correct.   05/08/2025   05/08/2025
  The Department is reviewing the permit application to determine if it contains all required information.   05/08/2025  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   GORDON P D'ABREU
  Application Number:   FL0037958-023-IW1S
  Site Name:   Mosaic Fertilizer, LLC - South Ft Meade Mine
  Applicant Name:   Ben Koplin
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/14/2022   10/14/2022
  The permit processor is verifying the permit application fee submitted is correct.   10/14/2022   10/14/2022
  The Department is reviewing the permit application to determine if it contains all required information.   10/14/2022   11/14/2022
  The Department is waiting for additional information from the permit applicant.   11/14/2022   12/14/2022
  The Department is reviewing the permit application to determine if it contains all required information.   12/14/2022   12/14/2022
  The Department is waiting for additional information from the permit applicant.   12/14/2022   01/12/2023
  The Department is reviewing the permit application to determine if it contains all required information.   01/12/2023   01/12/2023
  The Department is making an outcome determination regarding the permit application.   01/12/2023  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Hillsborough
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   DIEGO GRAVE DE PERALTA
  Application Number:   FL0038652-010-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Black Point Terminal
  Applicant Name:   Santino Provenzano
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/20/2022   09/20/2022
  The permit processor is verifying the permit application fee submitted is correct.   09/20/2022   09/20/2022
  The Department is reviewing the permit application to determine if it contains all required information.   09/20/2022   10/13/2022
  The Department is waiting for additional information from the permit applicant.   10/13/2022   10/28/2022
  The Department is reviewing the permit application to determine if it contains all required information.   10/28/2022   11/21/2022
  The Department is making an outcome determination regarding the permit application.   10/28/2022  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   EVELYN SARDINAS
  Application Number:   FL0132381-006-IW1S
  Site Name:   Cytec Industries, Inc - Brewster Plant
  Applicant Name:  
  Applicant Company:   Cytec Industries, Inc.
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/13/2023   07/13/2023
  The permit processor is verifying the permit application fee submitted is correct.   07/13/2023   07/13/2023
  The Department is reviewing the permit application to determine if it contains all required information.   07/13/2023   08/10/2023
  The Department is waiting for additional information from the permit applicant.   08/10/2023   09/08/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/08/2023   09/15/2023
  The Department is making an outcome determination regarding the permit application.   09/08/2023   09/15/2023
  The Department is preparing the permit documents.   09/08/2023   12/12/2023
  The Department published the Notice of Intent to Issue the permit.   12/12/2023   01/10/2025
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   12/12/2023   12/12/2023
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   12/12/2023  
  The Federal Environmental Protection Agency is reviewing the permit.   12/12/2023   01/11/2024


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   GORDON P D'ABREU
  Application Number:   FL0160083-005-IW1S
  Site Name:   Estech, Inc - Agricola Plant
  Applicant Name:   John Garlanger
  Applicant Company:   Ardaman & Associates
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/30/2023   10/30/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/30/2023   10/30/2023
  The Department is waiting for the applicant to submit the requested additional fees.   10/30/2023   11/06/2023
  The permit processor is verifying the permit application fee submitted is correct.   11/06/2023   11/06/2023
  The Department is reviewing the permit application to determine if it contains all required information.   11/06/2023   12/05/2023
  The Department is waiting for additional information from the permit applicant.   12/05/2023   01/03/2024
  The Department is reviewing the permit application to determine if it contains all required information.   01/03/2024   01/03/2024
  The Department is making an outcome determination regarding the permit application.   01/03/2024   01/03/2024
  The Department is preparing the permit documents.   01/03/2024  


Permitting Application Under Review
  FDEP Office:   PHOSPHATE MANAGEMENT
  Florida County:   Hillsborough
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   JESSICA M PEIN
  Application Number:   FLA177610-010-IW1S
  Site Name:   Mosaic Fertilizer, LLC - Plant City Closed Gypsum Stack
  Applicant Name:  
  Applicant Company:   Mosaic Fertilizer LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   06/12/2023   06/12/2023
  The permit processor is verifying the permit application fee submitted is correct.   06/12/2023   06/12/2023
  The Department is reviewing the permit application to determine if it contains all required information.   06/12/2023