Skip Navigation

Permitting Application with Events Details


This data is current as of: Wednesday, December 6, 2023


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Collier
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   NOLIN W MOON
  Application Number:   FL0026271-020-DW1P
  Site Name:   City of Naples Water Reclamation Facility
  Applicant Name:   Robert Middleton
  Applicant Company:   City of Naples Public Works Utilities Division
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   12/07/2021   12/07/2021
  The permit processor is verifying the permit application fee submitted is correct.   12/07/2021   12/10/2021
  The Department is waiting for the applicant to submit the requested additional fees.   12/10/2021   12/13/2021
  The permit processor is verifying the permit application fee submitted is correct.   12/13/2021   12/13/2021
  The Department is reviewing the permit application to determine if it contains all required information.   12/13/2021   01/11/2022
  The Department is waiting for additional information from the permit applicant.   01/11/2022   01/19/2022
  The Department is reviewing the permit application to determine if it contains all required information.   01/19/2022   02/18/2022
  The Department is waiting for additional information from the permit applicant.   02/18/2022   06/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   06/20/2023   06/20/2023
  The Department is making an outcome determination regarding the permit application.   06/20/2023   09/18/2023
  The Department is preparing the permit documents.   06/20/2023   09/18/2023
  The Department published the Notice of Intent to Issue the permit.   09/18/2023   09/22/2023
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   09/18/2023   09/18/2023
  The Federal Environmental Protection Agency is reviewing the permit.   09/18/2023   10/23/2023
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   09/18/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Lee
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   BILL D ROBERTSON
  Application Number:   FL0039829-031-DW1P
  Site Name:   Lee County Utilities - Fiesta Village
  Applicant Name:   Pamela Keyes
  Applicant Company:   Lee County Utilities
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   08/21/2023   08/21/2023
  The permit processor is verifying the permit application fee submitted is correct.   09/12/2023   09/12/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/12/2023   10/02/2023
  The Department is waiting for additional information from the permit applicant.   10/02/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Highlands
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   BRIAN EASTHAM
  Application Number:   FLA014311-019-DW1P
  Site Name:   City of Sebring Cemetery Road WWTP
  Applicant Name:   Bob Boggus
  Applicant Company:   CITY OF SEBRING
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/14/2023   07/14/2023
  The permit processor is verifying the permit application fee submitted is correct.   07/14/2023   07/16/2023
  The Department is reviewing the permit application to determine if it contains all required information.   07/14/2023   08/11/2023
  The Department is waiting for additional information from the permit applicant.   08/11/2023   09/28/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/28/2023   10/27/2023
  The Department is waiting for additional information from the permit applicant.   10/27/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Highlands
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   JESSICA DOUGLAS
  Application Number:   FLA014389-015-DW1P
  Site Name:   Sun'N Lake of Sebring Unit 23 WWTP
  Applicant Name:   Roger Polston
  Applicant Company:   Polston Engineering, Inc.
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   06/02/2023   06/02/2023
  The permit processor is verifying the permit application fee submitted is correct.   06/02/2023   06/22/2023
  The Department is reviewing the permit application to determine if it contains all required information.   06/02/2023   06/30/2023
  The Department is waiting for additional information from the permit applicant.   06/30/2023   08/28/2023
  The Department is reviewing the permit application to determine if it contains all required information.   08/28/2023   09/26/2023
  The Department is waiting for additional information from the permit applicant.   09/26/2023   10/05/2023
  The Department is reviewing the permit application to determine if it contains all required information.   10/05/2023   11/01/2023
  The Department is making an outcome determination regarding the permit application.   10/05/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Lee
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   BILL D ROBERTSON
  Application Number:   FLA014565-032-DW1P
  Site Name:   Lehigh Acres WWTF
  Applicant Name:   Sam Cain
  Applicant Company:   Florida Governmental Utility Authority
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/04/2023   10/04/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/04/2023   10/11/2023
  The Department is waiting for the applicant to submit the requested additional fees.   10/11/2023   10/21/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/21/2023   10/23/2023


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Sarasota
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   RICHARD BOENSCH
  Application Number:   FLA043494-019-DW1P
  Site Name:   Venice Gardens Water Reclamation Facility
  Applicant Name:   Michael Mylett
  Applicant Company:   Sarasota County Utilities
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/27/2023   10/27/2023
  The permit processor is verifying the permit application fee submitted is correct.   10/27/2023   11/07/2023
  The Department is waiting for the applicant to submit the requested additional fees.   11/07/2023   11/20/2023
  The permit processor is verifying the permit application fee submitted is correct.   11/20/2023   11/20/2023
  The Department is reviewing the permit application to determine if it contains all required information.   11/20/2023   12/06/2023
  The Department is making an outcome determination regarding the permit application.   11/20/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Collier
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   JESSICA DOUGLAS
  Application Number:   FLA141399-041-DW1P
  Site Name:   Collier County North County WRF
  Applicant Name:   Robert VonHolle
  Applicant Company:   Collier County Water - Sewer District
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/08/2023   03/08/2023
  The permit processor is verifying the permit application fee submitted is correct.   03/08/2023   03/13/2023
  The Department is waiting for the applicant to submit the requested additional fees.   03/13/2023   03/13/2023
  The permit processor is verifying the permit application fee submitted is correct.   03/13/2023   03/13/2023
  The Department is reviewing the permit application to determine if it contains all required information.   03/13/2023   04/07/2023
  The Department is waiting for additional information from the permit applicant.   04/07/2023   07/03/2023
  The Department is reviewing the permit application to determine if it contains all required information.   07/03/2023   07/31/2023
  The Department is waiting for additional information from the permit applicant.   07/31/2023   09/13/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/13/2023   10/13/2023
  The Department is making an outcome determination regarding the permit application.   09/13/2023  


Permitting Application Under Review
  FDEP Office:   SOUTH DISTRICT
  Florida County:   Highlands
  Permit Type:   Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit
  Permit Processor:   RICHARD BOENSCH
  Application Number:   FLA281484-014-DW1P
  Site Name:   North Main Street WWTP
  Applicant Name:  
  Applicant Company:   Town of Lake Placid
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/27/2023   11/27/2023
  The permit processor is verifying the permit application fee submitted is correct.   11/27/2023   12/01/2023
  The Department is waiting for the applicant to submit the requested additional fees.   12/01/2023