Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  Monroe |
  Permit Type: |
  Water - Domestic Wastewater Type II Wastewater Treatment Plant Permit |
  Permit Processor: |
  CODY KURAHARA |
  Application Number: |
  FLA419371-006-DW2P |
  Site Name: |
  City of Layton WWTP |
  Applicant Name: |
  Jay Miller |
  Applicant Company: |
  Florida Keys Aqueduct Authority |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/29/2024 |
  08/29/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  08/29/2024 |
  08/31/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  08/31/2024 |
  09/19/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/19/2024 |
  09/19/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/19/2024 |
  10/08/2024 |
  Applicant must publish a Notice of Application (per Rule 17-104.150(1) F.A.C. ) during the dates provided by the Department. |
  09/19/2024 |
  |
  The Department is waiting for additional information from the permit applicant. |
  10/08/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  Monroe |
  Permit Type: |
  Water - Domestic Wastewater Type II Wastewater Treatment Plant Permit |
  Permit Processor: |
  FRANCO LUCIEN |
  Application Number: |
  FLA642851-014-DW2P |
  Site Name: |
  City of Marathon Area 3 WWTP |
  Applicant Name: |
  Daniel Saus |
  Applicant Company: |
  City of Marathon |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/09/2023 |
  08/09/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  08/09/2023 |
  08/11/2023 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  08/11/2023 |
  08/14/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  08/14/2023 |
  08/17/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  08/14/2023 |
  09/13/2023 |
  The Department is waiting for additional information from the permit applicant. |
  09/13/2023 |
  10/13/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  10/13/2023 |
  11/12/2023 |
  The Department is making an outcome determination regarding the permit application. |
  10/13/2023 |
  |
|