Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  Miami-Dade |
  Permit Type: |
  Water - Industrial Wastewater Group 8D, Design Daily Flow of 50,000 or Less GPD Permit |
  Permit Processor: |
  CODY KURAHARA |
  Application Number: |
  FLA016949-005-IW8D |
  Site Name: |
  Hard Rock Stadium - Cooling Tower Facility |
  Applicant Name: |
  Todd Ellzey |
  Applicant Company: |
  South Florida Stadium LLC |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/22/2022 |
  04/22/2022 |
  The permit processor is verifying the permit application fee submitted is correct. |
  04/22/2022 |
  05/09/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/22/2022 |
  05/31/2022 |
  The Department is waiting for additional information from the permit applicant. |
  05/31/2022 |
  07/28/2022 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/28/2022 |
  12/14/2022 |
  The Department is waiting for additional information from the permit applicant. |
  12/14/2022 |
  09/11/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/11/2023 |
  11/13/2023 |
  The Department is making an outcome determination regarding the permit application. |
  09/11/2023 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  Palm Beach |
  Permit Type: |
  Water - Industrial Wastewater Group 8D, Design Daily Flow of 50,000 or Less GPD Permit |
  Permit Processor: |
  CODY KURAHARA |
  Application Number: |
  FLA842923-003-IW8D |
  Site Name: |
  Aerojet Rocketdyne |
  Applicant Name: |
  James Maus |
  Applicant Company: |
  Aerojet Rocketdyne, Inc. |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  08/11/2023 |
  08/11/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  08/11/2023 |
  08/14/2023 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  08/14/2023 |
  09/18/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/18/2023 |
  09/20/2023 |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHEAST DISTRICT |
  Florida County: |
  Palm Beach |
  Permit Type: |
  Water - Industrial Wastewater Group 8D, Design Daily Flow of 50,000 or Less GPD Permit |
  Permit Processor: |
  CODY KURAHARA |
  Application Number: |
  FLA920835-003-IW8D |
  Site Name: |
  Sikorsky Aircraft Corporation |
  Applicant Name: |
  George Mitchell |
  Applicant Company: |
  Sikorsky Aircraft Corporation |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/26/2023 |
  09/26/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/26/2023 |
  09/29/2023 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  09/29/2023 |
  09/29/2023 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/29/2023 |
  09/29/2023 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/29/2023 |
  10/27/2023 |
  The Department is making an outcome determination regarding the permit application. |
  09/29/2023 |
  |
|