Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  COLE NOLAN |
  Application Number: |
  FL0028061-025-DW1P |
  Site Name: |
  South County Regional AWWTP |
  Applicant Name: |
  Lisa Rhea |
  Applicant Company: |
  Hillsborough County Public Utilities Department |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/18/2024 |
  01/18/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/18/2024 |
  01/20/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  01/20/2024 |
  02/20/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  02/20/2024 |
  02/22/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  02/20/2024 |
  03/12/2024 |
  The Department is waiting for additional information from the permit applicant. |
  03/12/2024 |
  07/15/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/15/2024 |
  07/15/2024 |
  The Department is making an outcome determination regarding the permit application. |
  07/15/2024 |
  09/18/2024 |
  The Department is preparing the permit documents. |
  07/15/2024 |
  09/18/2024 |
  The Department published the Notice of Intent to Issue the permit. |
  09/18/2024 |
  01/08/2025 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  09/18/2024 |
  09/18/2024 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  09/18/2024 |
  10/23/2024 |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  09/18/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Pinellas |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  BELINDA B OLIVER |
  Application Number: |
  FL0030406-023-DW1P |
  Site Name: |
  Tarpon Springs City of |
  Applicant Name: |
  Thomas Kiger |
  Applicant Company: |
  City of Tarpon Springs |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  12/13/2024 |
  12/13/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  12/13/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Hillsborough |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  KARLA A LOPEZ |
  Application Number: |
  FL0040983-024-DW1P |
  Site Name: |
  Valrico AWWTF |
  Applicant Name: |
  Lisa Rhea |
  Applicant Company: |
  Hillsborough County Public Utilities Department |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/23/2024 |
  04/23/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  04/23/2024 |
  04/25/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  04/25/2024 |
  05/30/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  05/30/2024 |
  05/30/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  05/30/2024 |
  06/05/2024 |
  The Department is waiting for additional information from the permit applicant. |
  06/05/2024 |
  12/13/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/13/2024 |
  12/19/2024 |
  The Department is making an outcome determination regarding the permit application. |
  12/13/2024 |
  12/20/2024 |
  The Department is preparing the permit documents. |
  12/13/2024 |
  12/20/2024 |
  The Department published the Notice of Intent to Issue the permit. |
  12/20/2024 |
  01/12/2025 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  12/20/2024 |
  12/20/2024 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  12/20/2024 |
  |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  12/20/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Pinellas |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  NOAH S CUMMINGS |
  Application Number: |
  FL0128775-014-DW1P |
  Site Name: |
  William E Dunn WRF |
  Applicant Name: |
  Jeremy Waugh |
  Applicant Company: |
  Pinellas County Utilities |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/06/2025 |
  01/06/2025 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/06/2025 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  COLE NOLAN |
  Application Number: |
  FL0A00002-027-DW1P |
  Site Name: |
  Northeast Regional WWTF |
  Applicant Name: |
  Tamara Richardson |
  Applicant Company: |
  Polk County Utilities Division |
  Agency Action: |
  Issue: Pending Final Action |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  04/17/2024 |
  04/17/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  04/17/2024 |
  04/19/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  04/19/2024 |
  04/19/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  04/19/2024 |
  04/21/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  04/19/2024 |
  05/15/2024 |
  The Department is waiting for additional information from the permit applicant. |
  05/15/2024 |
  09/09/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  09/09/2024 |
  09/09/2024 |
  The Department is making an outcome determination regarding the permit application. |
  09/09/2024 |
  11/15/2024 |
  The Department is preparing the permit documents. |
  09/09/2024 |
  11/15/2024 |
  The Department published the Notice of Intent to Issue the permit. |
  11/15/2024 |
  12/11/2024 |
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review. |
  11/15/2024 |
  11/15/2024 |
  The Federal Environmental Protection Agency is reviewing the permit. |
  11/15/2024 |
  |
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application. |
  11/15/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Manatee |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  BELINDA B OLIVER |
  Application Number: |
  FLA012619-023-DW1P |
  Site Name: |
  Manatee County Southwest Regional WWTP |
  Applicant Name: |
  Patrick Shea |
  Applicant Company: |
  Manatee County Utilities |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  09/19/2024 |
  09/19/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  09/19/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Pasco |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  BELINDA B OLIVER |
  Application Number: |
  FLA012737-011-DW1P |
  Site Name: |
  Southeast Pasco Subregional WWTF |
  Applicant Name: |
  David Allen |
  Applicant Company: |
  Pasco County Utilities |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  11/18/2024 |
  11/18/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  11/18/2024 |
  11/20/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  11/20/2024 |
  12/06/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  12/06/2024 |
  12/06/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  12/06/2024 |
  12/06/2024 |
  The Department is waiting for additional information from the permit applicant. |
  12/06/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Polk |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  BELINDA B OLIVER |
  Application Number: |
  FLA012949-013-DW1P |
  Site Name: |
  Sun Ray WWTP |
  Applicant Name: |
  Mark Addison |
  Applicant Company: |
  Polk County Utilities Department |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  01/19/2024 |
  01/19/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  01/19/2024 |
  01/21/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  01/21/2024 |
  03/15/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/15/2024 |
  03/17/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  03/15/2024 |
  03/18/2024 |
  The Department is waiting for additional information from the permit applicant. |
  03/18/2024 |
  |
|
Permitting Application Under Review
|
  FDEP Office: |
  SOUTHWEST DISTRICT |
  Florida County: |
  Hernando |
  Permit Type: |
  Water - Domestic Wastewater Type I Wastewater Treatment Plant Permit |
  Permit Processor: |
  BELINDA B OLIVER |
  Application Number: |
  FLA017223-013-DW1P |
  Site Name: |
  Hernando County Airport WRF |
  Applicant Name: |
  Gordon Onderdonk |
  Applicant Company: |
  Hernando County Utilities |
  Agency Action: |
  Pending |
Permitting Application Events to Date
|
  Permitting Event Description |
  Started |
  Completed |
  Permit application was received by the Department. |
  03/14/2024 |
  03/14/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  03/14/2024 |
  03/16/2024 |
  The Department is waiting for the applicant to submit the requested additional fees. |
  03/16/2024 |
  07/15/2024 |
  The permit processor is verifying the permit application fee submitted is correct. |
  07/15/2024 |
  07/16/2024 |
  The Department is reviewing the permit application to determine if it contains all required information. |
  07/15/2024 |
  08/08/2024 |
  The Department is waiting for additional information from the permit applicant. |
  08/08/2024 |
  |
|