Permitting Application with Events Details


This data is current as of: Friday, February 14, 2025


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Citrus
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   FRANK WALL
  Application Number:   FL0000159-028-IW1S
  Site Name:   Citrus Combined Cycle PB1 & PB2
  Applicant Name:   Todd Pigeon
  Applicant Company:   Duke Energy Crystal River
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/09/2024   09/09/2024
  The permit processor is verifying the permit application fee submitted is correct.   09/09/2024   09/09/2024
  The Department is reviewing the permit application to determine if it contains all required information.   09/09/2024   10/09/2024
  The Department is waiting for additional information from the permit applicant.   10/09/2024   01/21/2025
  The Department is reviewing the permit application to determine if it contains all required information.   01/21/2025   01/21/2025
  The Department is making an outcome determination regarding the permit application.   01/21/2025   01/27/2025
  The Department is preparing the permit documents.   01/21/2025   01/27/2025
  The Department published the Notice of Intent to Issue the permit.   01/27/2025   01/31/2025
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   01/27/2025   01/27/2025
  The Federal Environmental Protection Agency is reviewing the permit.   01/27/2025  
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   01/27/2025  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Hillsborough
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   FRANK WALL
  Application Number:   FL0000817-013-IW1S
  Site Name:   Tampa Electric Co Big Bend Power Station
  Applicant Name:   Stanley Kroh
  Applicant Company:   Tampa Electric Company (Teco)
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   07/01/2016   07/01/2016
  The permit processor is verifying the permit application fee submitted is correct.   07/01/2016   07/01/2016
  The Department is reviewing the permit application to determine if it contains all required information.   07/01/2016   07/22/2016
  The Department is waiting for additional information from the permit applicant.   07/22/2016   11/02/2016
  The Department is reviewing the permit application to determine if it contains all required information.   11/02/2016   01/25/2017
  The Department is making an outcome determination regarding the permit application.   11/02/2016   01/25/2017
  The Department is preparing the permit documents.   11/02/2016   01/25/2017
  The Department published the Notice of Intent to Issue the permit.   01/25/2017   02/01/2017
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   01/25/2017   01/25/2017
  The Federal Environmental Protection Agency is reviewing the permit.   01/25/2017  
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   01/25/2017  
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   02/24/2017  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Duval
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   TIEN-SHUENN WU
  Application Number:   FL0001031-014-IW1S
  Site Name:   JEA Northside and St. Johns River Power Park
  Applicant Name:   Paul Steinbrecher
  Applicant Company:   JEA
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   11/09/2016   11/09/2016
  The permit processor is verifying the permit application fee submitted is correct.   11/09/2016   11/09/2016
  The Department is reviewing the permit application to determine if it contains all required information.   11/09/2016   11/22/2016
  The Department is waiting for additional information from the permit applicant.   11/22/2016  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Volusia
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   TIEN-SHUENN WU
  Application Number:   FL0001554-019-IW1S
  Site Name:   FPL Sanford Power Plant
  Applicant Name:   Benjamin Pynes
  Applicant Company:   FPL Sanford
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   03/05/2018   03/05/2018
  The permit processor is verifying the permit application fee submitted is correct.   03/05/2018   03/06/2018
  The Department is reviewing the permit application to determine if it contains all required information.   03/05/2018   03/27/2018
  The Department is waiting for additional information from the permit applicant.   03/27/2018  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   St. Lucie
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   TIEN-SHUENN WU
  Application Number:   FL0002208-022-IW1S
  Site Name:   FPL St. Lucie Power Plant
  Applicant Name:   Carlos Santos
  Applicant Company:   FPL - St Lucie Plant
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/16/2021   04/16/2021
  The permit processor is verifying the permit application fee submitted is correct.   04/16/2021   04/18/2021
  The Department is reviewing the permit application to determine if it contains all required information.   04/16/2021   11/18/2021
  The Department is waiting for additional information from the permit applicant.   11/18/2021   10/04/2024
  The Department is reviewing the permit application to determine if it contains all required information.   10/04/2024   10/04/2024
  The Department is making an outcome determination regarding the permit application.   10/04/2024   12/04/2024
  The Department is preparing the permit documents.   10/04/2024   12/04/2024
  The Department published the Notice of Intent to Issue the permit.   12/04/2024   12/17/2024
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   12/04/2024   12/04/2024
  The Federal Environmental Protection Agency is reviewing the permit.   12/04/2024   01/20/2025
  The Department is waiting the required period of time for public comment prior to continuing to process the permit application.   12/04/2024   01/20/2025
  The Department is mailing the permit applicant and other affected or interested parties a certified copy of the Department's intended actions.   01/20/2025   02/06/2025
  The Department's intent regarding the permit application was published.   02/06/2025  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Escambia
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   FRANK WALL
  Application Number:   FL0002275-022-IW1S
  Site Name:   Gulf Clean Energy Center
  Applicant Name:   James Fowler
  Applicant Company:   Florida Power & Light Company
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   09/27/2023   09/27/2023
  The permit processor is verifying the permit application fee submitted is correct.   09/27/2023   09/27/2023
  The Department is reviewing the permit application to determine if it contains all required information.   09/27/2023   12/19/2023
  The Department is waiting for additional information from the permit applicant.   12/19/2023   03/18/2024
  The Department is reviewing the permit application to determine if it contains all required information.   03/18/2024   06/14/2024
  The Department is waiting for additional information from the permit applicant.   06/14/2024   09/12/2024
  The Department is reviewing the permit application to determine if it contains all required information.   09/12/2024  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Martin
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   TIEN-SHUENN WU
  Application Number:   FL0030988-018-IW1S
  Site Name:   FPL - Martin Power Plant
  Applicant Name:   Russell Peters
  Applicant Company:   Florida Power & Light
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   04/20/2018   04/20/2018
  The permit processor is verifying the permit application fee submitted is correct.   04/20/2018   04/22/2018
  The Department is reviewing the permit application to determine if it contains all required information.   04/20/2018   04/27/2018
  The Department is waiting for additional information from the permit applicant.   04/27/2018  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Putnam
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   TIEN-SHUENN WU
  Application Number:   FL0036498-027-IW1S
  Site Name:   Seminole Electric Coop WWTF
  Applicant Name:   David Ferrentino
  Applicant Company:   Seminole Electric
  Agency Action:   Issue: Pending Final Action
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   02/07/2023   02/07/2023
  The permit processor is verifying the permit application fee submitted is correct.   02/07/2023   02/13/2023
  The Department is reviewing the permit application to determine if it contains all required information.   02/07/2023   03/28/2023
  The Department is waiting for additional information from the permit applicant.   03/28/2023   01/27/2025
  The Department is reviewing the permit application to determine if it contains all required information.   01/27/2025   01/27/2025
  The Department is making an outcome determination regarding the permit application.   01/27/2025   02/05/2025
  The Department is preparing the permit documents.   01/27/2025   02/05/2025
  The Department published the Notice of Intent to Issue the permit.   02/05/2025  
  The Department mailed the draft permit to the Federal Environmental Protection Agency for their review.   02/05/2025  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Polk
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   FRANK WALL
  Application Number:   FL0043869-015-IW1S
  Site Name:   Tampa Electric Polk Power Station
  Applicant Name:   Stanley Kroh
  Applicant Company:   Tampa Electric Company
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   10/01/2018   10/01/2018
  The permit processor is verifying the permit application fee submitted is correct.   10/01/2018   10/01/2018
  The Department is reviewing the permit application to determine if it contains all required information.   10/01/2018   10/26/2018
  The Department is waiting for additional information from the permit applicant.   10/26/2018  


Permitting Application Under Review
  FDEP Office:   TALLAHASSEE HEADQUARTERS
  Florida County:   Citrus
  Permit Type:   Water - Industrial Wastewater Group 1, Surface Water Discharge Permit
  Permit Processor:   FRANK WALL
  Application Number:   FL0A00004-006-IW1S
  Site Name:   Crystal River Unit 3
  Applicant Name:   John Jernigan
  Applicant Company:   Accelerated Decommissioning Partners(ADP-CR3) LLC
  Agency Action:   Pending
Permitting Application Events to Date
  Permitting Event Description   Started   Completed
  Permit application was received by the Department.   08/15/2024   08/15/2024
  The permit processor is verifying the permit application fee submitted is correct.   08/15/2024   08/15/2024
  The Department is reviewing the permit application to determine if it contains all required information.   08/15/2024   08/23/2024
  The Department is waiting for additional information from the permit applicant.   08/23/2024