2025.04.11 |
INSPECTION RELATED IN COMPLIANCE LETTER CEI - CEMEX MIAMI CEMENT PLANT & SCL QUARRY (EPAID FLD981758485) |
 |
2025.04.03 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2025.03.20 |
INSPECTION RELATED EXIT INTERVIEW |
 |
2025.03.18 |
SITE PHOTOS SITE PHOTOS |
 |
2023.12.06 |
INSPECTION RELATED RETURN TO COMPLIANCE LETTER CEI - CEMEX MIAMI CEMENT PLANT & SCL QUARRY (FLD981758485) |
 |
2023.12.06 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2023.11.20 |
INSPECTION RELATED SUBMITTALS |
 |
2023.11.06 |
INSPECTION RELATED STATUS REPORT - EXIT INTERVIEW |
 |
2023.11.02 |
SITE PHOTOS SITE PHOTOS 1 |
 |
2023.11.02 |
SITE PHOTOS SITE PHOTOS 3 |
 |
2023.11.02 |
SITE PHOTOS SITE PHOTOS 2 |
 |
2022.08.16 |
INSPECTION RELATED CEMEX MIAMI CEMENT PLANT & SCL QUARRY RETURN TO COMPLIANCE LETTER CEI DATED 06-21-2022 |
 |
2022.08.12 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT - FINAL SUBMITTAL - HW MANIFEST AND PROFILE |
 |
2022.08.09 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2022.07.25 |
INSPECTION RELATED USED OIL ACCEPTANCE AND DELIVERY RECORDS AND SPILL/LEAK LOGS |
 |
2022.07.25 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT - CORRECTIVE ACTIONS - CONTINGENCY PLAN UPDATES AND SOLVENT SDS |
 |
2022.07.01 |
INSPECTION RELATED STATUS REPORT - EXIT INTERVIEW |
 |
2022.06.21 |
INSPECTION RELATED SITE PHOTOS 3 |
 |
2022.06.21 |
INSPECTION RELATED SITE PHOTOS 2 |
 |
2022.06.21 |
INSPECTION RELATED SITE PHOTOS 1 |
 |
2021.01.15 |
REQUEST FOR ADDITIONAL INFORMATION |
 |
2021.01.13 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2021.01.12 |
INSPECTION RELATED RETURN TO COMPLIANCE LETTER/INSPECTION REPORT DATED 01-13-2021 |
 |
2020.12.21 |
INSPECTION RELATED STATUS REPORT - EXIT INTERVIEW |
 |
2020.12.17 |
SITE PHOTOS |
 |
2019.07.01 |
INSPECTION RELATED ATTACHMENT - CORRECTIVE ACTION TAKEN BY THE FACILITY |
 |
2019.06.25 |
INSPECTION RELATED INFORMAL VERBAL ENFORCEMENT - RTC LETTER- CWOE |
 |
2019.06.25 |
INSPECTION RELATED LETTER - RTC LETTER - CWOE |
 |
2019.06.07 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2019.06.05 |
INSPECTION RELATED REQUEST FOR ADDITIONAL INFORMATION - RAI- TIMELINE OF THE REMOVAL OF TANK #4 |
 |
2019.06.05 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT - CEMEX RESPONSE TO THE DEPARTMENT -RELATED TO SAR |
 |
2019.05.08 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT - AST REMOVAL - TCAR REPORT FOR 30,000 GALLON TANK |
 |
2019.05.02 |
INSPECTION RELATED STATUS REPORT - EXIT INTERVIEW |
 |
2018.02.28 |
MONITORING PLANS AND REPORTS RELATED ANNUAL UO REPORT AND REGISTRATION REVISED FORM |
 |
2017.12.21 |
INSPECTION RELATED LETTER IN COMPLIANCE |
 |
2017.12.21 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2017.12.20 |
INSPECTION RELATED DOCUMENTS REVIEWED DURING THE INSPECTION- PROVIDED VIA EMAIL FOR REFERENCE |
 |
2017.11.08 |
INSPECTION RELATED EXIT INTERVIEW |
 |
2017.11.08 |
SITE PHOTOS DETAILED SITE ACTIVITIES |
 |
2015.04.22 |
INSPECTION RELATED VIOLATION CHARACTERIZATION SPREADSHEET |
 |
2015.04.22 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2015.04.22 |
NONCOMPLIANCE RELATED INFORMAL VERBAL ENFORCEMENT RETURN TO COMPLIANCE LETTER |
 |
2015.03.10 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT COMPLETE COMPLIANCE SUBMITTAL |
 |
2015.02.24 |
INSPECTION RELATED STATUS REPORT EXIT INTERVIEW |
 |
2015.02.24 |
INSPECTION RELATED SITE PHOTOS SITE PHOTOS |
 |
2014.03.17 |
INSPECTION RELATED LTR RE: ID NUMBER & FL NOTIFICATION OF REGULATED WASTE ACTIVITY REPORT |
 |
2013.07.01 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2013.04.15 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT COMPLIANCE SUBMITTAL |
 |
2013.03.20 |
INSPECTION RELATED HW INSPECTION REPORT |
 |
2013.03.19 |
SITE PHOTOS SITE PHOTOS SITE PHOTOS |
 |
2013.03.19 |
INSPECTION RELATED STATUS REPORT EXIT INTERVIEW |
 |
2012.02.23 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2012.02.22 |
INCOMING CORRESPONDENCE SUBMITTAL RECEIVED BY DEPARTMENT EMAI FROM WALZ |
 |
2012.02.22 |
INCOMING CORRESPONDENCE SITE PHOTOS COMPLIANCE PHOTOS |
 |
2012.01.09 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT COMPLIANCE PHOTOS |
 |
2011.12.19 |
NONCOMPLIANCE RELATED INFORMAL VERBAL ENFORCEMENT |
 |
2011.12.19 |
INSPECTION RELATED HW INSPECTION REPORT |
 |
2010.10.08 |
INSPECTION RELATED LETTER PROJECT CLOSED LETTER |
 |
2010.10.04 |
INSPECTION RELATED INSPECTION REPORT FINAL |
 |
2010.09.29 |
INSPECTION RELATED SUBMITTAL RECEIVED BY DEPARTMENT COMPLIANCE SUBMITTAL |
 |
2010.08.27 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2010.07.19 |
INSPECTION RELATED INFORMAL VERBAL ENFORCEMENT DRAFT INSPECTION REPORT |
 |
2010.07.19 |
SITE PHOTOS SITE PHOTOS |
 |
2008.07.30 |
INSPECTION RELATED PROJEC CLOSED LETTER - FINAL REPORT |
 |
2008.04.16 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2008.04.07 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2008.04.07 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2008.03.17 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2008.03.05 |
INSPECTION RELATED COMPLIANCE SUBMITTAL |
 |
2008.03.05 |
INSPECTION RELATED EMAIL SUMMARIZING COMPLIANCE SUBMITTAL |
 |
2008.02.21 |
INSPECTION RELATED EXIT INTERVIEW |
 |
2008.02.21 |
INSPECTION RELATED MANIFEST LOGS |
 |
2008.02.21 |
INSPECTION RELATED ADDITIONAL INFORMATION PROVIDED AT INSPECTION |
 |
2008.01.08 |
OUTGOING CORRESPONDENCE COST EST MEMO |
 |
2006.05.22 |
INSPECTION RELATED RCRA COMPLIANCE EVALUATION INSPECTION |
 |
2006.05.22 |
SITE VISIT RELATED RCRA COMPLIANCE EVALUATION INSPECTION |
 |
2004.04.06 |
CONSENT ORDER DEP SENDS EXECUTED CONSENT ORDER |
 |
2003.07.29 |
WARNING LETTER POSSIBLE VIOLATIONS |
 |
2000.06.15 |
INSPECTION RELATED SEPT. 2000 INSP.- RINKER MATERIALS CORP. |
 |
2000.02.15 |
INSPECTION RELATED MARCH 2000 INSP.- RINKER MATERIALS CORP. |
 |
1999.12.29 |
INSPECTION RELATED DEC 1999 INSP.- RINKER MATERIALS CORP. |
 |
1999.09.14 |
INSPECTION RELATED SEPT. 1999 INSP.- RINKER MATERIALS CORP. |
 |
1999.05.15 |
INSPECTION RELATED JUNE 1999 INSP.- RINKER MATERIALS CORP. |
 |
1999.05.15 |
INSPECTION RELATED JUNE 1999 INSP.- RINKER MATERIALS CORP. |
 |
1998.11.09 |
INSPECTION RELATED JAN 1999 INSP.- RINKER MATERIALS CORP. |
 |
1998.09.24 |
INSPECTION RELATED SEPT 1998 INSP.- RINKER MATERIALS CORP. |
 |
1998.03.04 |
INSPECTION RELATED MARCH 1998 INSP.- RINKER MATERIALS CORP. |
 |
1997.09.26 |
INSPECTION RELATED JUNE 1998 INSP. |
 |
1997.08.20 |
INSPECTION RELATED QUARTERLY REPORT OF GROUNDWATER MONITORING (RINKER MATERIALS CORP.) |
 |
1997.05.15 |
INSPECTION RELATED JUNE 1997 INSP.- RINKER MATERIALS CORP. |
 |
1996.12.06 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1996.09.12 |
INSPECTION RELATED JUNE 1996 INSP.- RINKER MATERIALS CORP. |
 |
1996.09.12 |
INSPECTION RELATED OCT 1996 INSP.- RINKER MATERIALS CORP. |
 |
1996.03.07 |
INSPECTION RELATED APRIL 1996 INSP.- RINKER MATERIALS CORP. |
 |
1996.03.07 |
INSPECTION RELATED DEC 1997 INSP.- RINKER MATERIALS CORP. |
 |
1995.06.01 |
INSPECTION RELATED JULY 1995 INSP.- RINKER MATERIALS CORP. |
 |
1995.01.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1994.06.03 |
INSPECTION RELATED CERCLA OFF-SITE RULE:AFFIRMATIVE DETERMINIATION OF ACCEPTABILITY FOR RINKER MATERIALS CORP. MIAMI, FL |
 |
1994.01.01 |
INSPECTION RELATED RINKER MATERIALS MARCH 1995 INSP. |
 |
1993.08.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1993.08.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1993.07.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1993.02.03 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1993.01.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1992.04.23 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1992.04.23 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1991.12.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1991.11.06 |
INSPECTION RELATED MISC FROM FILE-PERMIT, MONITOR REPORTS |
 |
1991.11.06 |
INCOMING CORRESPONDENCE MISC. PAMPHLETS |
 |
1991.11.06 |
SITE MAPS - SKETCHES - DRAWINGS BLUE PRINTS (FROM FILE WITH SAME DATES) |
 |
1991.08.16 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1991.05.01 |
INSPECTION RELATED FILE RE: SOIL THERMAL TREATMENT FACILITY INSPECTION REPORT |
 |
1990.08.31 |
INSPECTION RELATED ENTIRE FILE |
 |
1990.08.31 |
INSPECTION RELATED LETTER FORM MORGAN, LEWIS & BOCKIUS TO SATISH N. KASTURY WE REPRESENT RINKER MATERIALS CORP. |
 |
1989.01.25 |
CASE CLOSURE RELATED CEMEX MIAMI CEMENT PLANT |
 |
1986.10.27 |
INSPECTION RELATED NABORS TRAILERS RESPONSE TO MR. ERNEST E. FREY (DER) LETTER ON 10/23/1986 |
 |